Opening the dossier…
Opening the dossier…
Contractor dossier
3 projects on file, including joint ventures this contractor is part of.
Total projects
3
Total budget
₱27.3M
Average progress
80.8%
Completion rate
33.3%
Below 70%
Average risk score
50.5
Medium risk on average, out of 100
Flagged as unusual
1
33.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 3 | ₱27.3M | 50.5 | 1 | 80.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 2 | ₱12.8M | 28.8 | 0 | 93.8% |
| GAA 2025 SSP | 1 | ₱14.5M | 93.7 | 1 | 55.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0143SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD, MARAYOS-SABANG, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱14.5M | 55% | High risk94 | Flagged0.021 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0143SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD, MARAYOS-SABANG, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱14.5M | 55% | High risk94 | Flagged0.021 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EI0143SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD, MARAYOS-SABANG, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱14.5M | 55% | High risk94 | Flagged0.021 |
| 2 | 24EI0104CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ZONE 2, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱9.9M | 100% | Medium risk36 | —-0.087 |
| 3 | 25EI0102CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY SABANG, PINAMALAYAN, ORIENTAL MINDORO, PHASE II | Region IV-B | Southern Mindoro DEO | On-Going | ₱2.9M | 88% | Low risk21 | —-0.050 |