Contractor dossier
131 projects on file, including joint ventures this contractor is part of.
Total projects
131
Total budget
₱8.9B
Average progress
83.2%
Completion rate
61.1%
Below 70%
Average risk score
53.9
Medium risk on average, out of 100
Flagged as unusual
18
13.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 47 | ₱3B | 54.8 | 3 | 79.8% |
| Region III | 30 | ₱1.5B | 50.9 | 2 | 96.8% |
| Region IV-A | 13 | ₱1.1B | 57.4 | 0 | 81.2% |
| Region IV-B | 9 | ₱1.1B | 54.9 | 5 | 58.7% |
| Region XI | 9 | ₱353.5M | 47.2 | 0 | 100.0% |
| Negros Island Region | 7 | ₱398.2M | 51.1 | 0 | 100.0% |
| Region X | 6 | ₱190.7M | 45.8 | 0 | 83.1% |
| Region VII | 3 | ₱573.2M | 66.5 | 3 | 21.0% |
| Region I | 3 | ₱161M | 63.6 | 3 | 70.5% |
| Region VIII | 2 | ₱379.4M | 68.7 | 1 | 78.5% |
| Region VI | 2 | ₱138.8M | 64.8 | 1 | 65.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 65 | ₱5.9B | 58.5 | 8 | 86.8% |
| Buildings and Facilities | 36 | ₱1.9B | 48.4 | 6 | 71.3% |
| Roads | 26 | ₱819.4M | 46.1 | 1 | 93.4% |
| GAA 2025 SSP | 2 | ₱145.5M | 94.6 | 2 | 32.1% |
| OTHER | 1 | ₱106.1M | 79.6 | 1 | 100.0% |
| Bridges | 1 | ₱10.5M | 47.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OB0359CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 3) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱72.8M | 30% | High risk95 | Flagged0.024 |
| 25OB0360CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 4) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱72.8M | 34% | High risk95 | Flagged0.024 |
| 24GA0249CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER (PACKAGE 2-A), KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱105.1M | 30% | High risk83 | Flagged0.063 |
| 24CL0051CONSTRUCTION OF SANTO TOMAS RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 9, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.5M | 97% | High risk82 | —-0.013 |
| 24CL0024CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE I | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 63% | High risk80 | Flagged0.003 |
| 24CL0027CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE IV | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 65% | High risk80 | Flagged0.001 |
| 24CL0025CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE II | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 96% | High risk80 | —-0.012 |
| 24CL0060CONSTRUCTION OF MALOMA RIVER FLOOD CONTROL STRUCTURE, DOWNSTREAM, PACKAGE 3, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.044 |
| 24A00226CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SABO DAM ALONG BONGO RIVER, NUEVA ERA, ILOCOS NORTE | Region I | Region I | On-Going | ₱106.1M | 100% | High risk80 | Flagged0.018 |
| 24HM0014CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE PHASE III AT DATAG RIVER (DO | Negros Island Region | Siquijor DEO | Completed | ₱96.5M | 100% | High risk77 | —-0.027 |
| 24CC0385CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, POBLACION SECTION, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.059 |
| 23CC0532CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL PROJECT AND REHABILITATION OF WATERWAYS AT BRGY. SULIVAN BALIUAG, BULACAN STA.. 004+531 TO STA. 004+831 | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk75 | —-0.005 |
| 23CC0529CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL PROJECT AND REHABILITATION OF WATERWAYS AT BRGY. PAGALA BALIUAG, BULACAN STA. 003+462 TO SR=TA. 003+762 | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk75 | —-0.005 |
| 22CD0236REHABILITATION OF MUNICIPAL BUILDING, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱29.1M | 100% | High risk73 | —-0.071 |
| 24CC0407CONSTRUCTION OF ROAD, BRGY. KAPITANGAN, PAOMBONG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱39.6M | 100% | High risk70 | —-0.068 |
| 24I00042CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱190.9M | 67% | High risk69 | Flagged0.000 |
| 24I00043CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TAFT RIVER, BARANGAY MALINAO, TAFT, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱188.5M | 90% | High risk69 | —-0.005 |
| 24E00150SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC | Region IV-B | Region IV-B | On-Going | ₱232.4M | 90% | High risk68 | Flagged0.000 |
| 24E00053BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOODMITIGATION STUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACLITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER (EAST SIDE), SITIO MALINAO SECTION, BRGY. TAGUMPAY, NAUJAN, OR. MINDORO | Region IV-B | Region IV-B | Completed | ₱247.5M | 100% | High risk68 | —-0.039 |
| 24E00039FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, SITIO DIKE, BRGY. APITONG SECTION, NAUJAN, ORIENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk67 | —-0.045 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GA0249CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER (PACKAGE 2-A), KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱105.1M | 30% | High risk83 | Flagged0.063 |
| 24E00216POLYTECHNIC UNIVERSITY OF THE PHILIPPINES- CONST. OF ACADEMIC BUILDING, PUP, SABLAYAN, OCC. MINDORO | Region IV-B | Region IV-B | On-Going | ₱93.6M | 0% | Medium risk55 | Flagged0.039 |
| 24E00229POLYTECHNIC UNIVERSITY OF THE PHILIPPINES- CONSTRUCTION OF ACADEMIC BUILDING, PUP, BANSUD, ORIENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱93.4M | 0% | Medium risk54 | Flagged0.039 |
| 23H00043OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL | Region VII | Region VII | On-Going | ₱193M | 0% | High risk67 | Flagged0.032 |
| 23H00044OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, AGAPE SECTION, LOBOC, BOHOL | Region VII | Region VII | On-Going | ₱166.3M | 0% | High risk67 | Flagged0.025 |
| 25OB0359CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 3) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱72.8M | 30% | High risk95 | Flagged0.024 |
| 25OB0360CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 4) | National Capital Region | Metro Manila 1st DEO | On-Going | ₱72.8M | 34% | High risk95 | Flagged0.024 |
| 24E00253LGU HOSPITALS - SIBUYAN DISTRICT HOSPITAL, SIBUYAN ISLAND, RIOMBLON | Region IV-B | Region IV-B | On-Going | ₱61.9M | 17% | Medium risk53 | Flagged0.022 |
| 24A00226CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SABO DAM ALONG BONGO RIVER, NUEVA ERA, ILOCOS NORTE | Region I | Region I | On-Going | ₱106.1M | 100% | High risk80 | Flagged0.018 |
| 24E00251LGU HOSPITALS - ROMBLON PROVINCIAL HOSPITAL, ROMBLON, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱47.9M | 22% | Medium risk47 | Flagged0.018 |
| 23H00009OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL | Region VII | Region VII | On-Going | ₱213.9M | 63% | High risk66 | Flagged0.017 |
| 21O00075CONSTRUCTION OF LAS PIÑAS GENERAL HOSPITAL AND SATELLITE TRAUMA CENTER BUILDING, BRGY. PULANGLUPA 1, LAS PIÑAS CITY | National Capital Region | National Capital Region | On-Going | ₱494.9M | 61% | High risk65 | Flagged0.008 |
| 24A00063CONSTRUCTION OF MISSING LINKS/ NEW ROADS - JCT ILOCOS NORTE ABRA ROAD - NUEVA ERA - TINEG ROAD, NUEVA ERA, ILOCOS NORTE | Region I | Region I | On-Going | ₱14.2M | 16% | High risk65 | Flagged0.007 |
| 24AE0101CONSTRUCTION OF 4 STOREY-12 CLASSROOM SCHOOL BUILDING AT LA UNION NATIONAL HIGH SCHOOL, CITY OF SAN FERNANDO, LA UNION | Region I | La Union 1st DEO | On-Going | ₱40.6M | 96% | Medium risk46 | Flagged0.004 |
| 24CL0024CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE I | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 63% | High risk80 | Flagged0.003 |
| 24CL0027CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE IV | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 65% | High risk80 | Flagged0.001 |
| 24I00042CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱190.9M | 67% | High risk69 | Flagged0.000 |
| 24E00150SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC | Region IV-B | Region IV-B | On-Going | ₱232.4M | 90% | High risk68 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 21LE0020OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS-DEMOLOC-LITTLE BAGUIO-ALABEL ROAD, (SECTION 1-STA. 1648+420 TO STA. 1648+700; SECTION 2 - STA. 1658+220 TO STA. 1658+370; AND SECTION 3 - STA. 1659+480 TO STA. 1660+000). UPPER TIBULOG, MALITA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱14M | 100% | Medium risk46 | —-0.090 |
| 102 | 24KK0015ROAD WIDENING - PRIMARY ROADS - BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1360 + 000 - K1360 + 645 | Region X | Misamis Oriental 1st DEO | Completed | ₱29.9M | 100% | Medium risk45 | —-0.093 |
| 103 | 24HL0012ORGANIZATIONAL OUTCOME 002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF TIABANAN RIVER CONTROL | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱45.1M | 100% | Medium risk45 | —-0.066 |
| 104 | 24HL0036ORGANIZATIONAL OUTCOME 002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF BAYAWAN RIVER CONTROL, | Negros Island Region | Negros Oriental 3rd DEO | Completed | ₱45.1M | 100% | Medium risk45 | —-0.066 |
| 105 | 25KK0008ROAD WIDENING - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1366 + 392 - K1367 + 000, K1367 + 049 - K1367 + 089 | Region X | Misamis Oriental 1st DEO | On-Going | ₱27.7M | 50% | Medium risk45 | —-0.046 |
| 106 | 23KK0033ROAD WIDENING - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1308 + 864 - K1309 + 399 | Region X | Misamis Oriental 1st DEO | Completed | ₱22.4M | 100% | Medium risk45 | —-0.093 |
| 107 | 24KA0155REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBLACION,CABANGLASAN, BUKIDNONCABANGLASAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱12.7M | 52% | Medium risk43 | —-0.033 |
| 108 | 24KA0156REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL GYM), BARANGAY POBLACION,CABANGLASAN, BUKIDNONCABANGLASAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱6.9M | 100% | Medium risk42 | —-0.085 |
| 109 | 22CA0034NETWORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - GOV. J.J. LINAO RD - K0160+814 - K0162+000, K0162+419 - K0163+349, MORONG, BATAAN | Region III | Bataan 1st DEO | Completed | ₱19.6M | 100% | Medium risk42 | —-0.092 |
| 110 | 21LE0170CONCRETING OF COLONGAN-TANGLAD-COLAGSING ROAD, (TANGLAD-COLAGSING SECTION) BRGY. TANGLAD FMR, BRGY. TANGLAD STA. MARIA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.032 |
| 111 | 24CC0507CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY BULIHAN, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱54.4M | 96% | Medium risk41 | —-0.060 |
| 112 | 21LE0179CONCRETING OF BRGY. WEST LAMIDAN FMR, BRGY. WEST LAMIDAN, DON MARCELINO, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.029 |
| 113 | 21LE0171CONCRETING OF BASIAWAN - STO. ROSARIO - KISULAD - BUHANGIN ROAD, BRGY. SANTO ROSARIO, STA. MARIA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.032 |
| 114 | 21LE0172CONCRETING OF BRGY. LACARON FMR, BRGY. LACARON, MALITA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.032 |
| 115 | 23EA0053CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MOGPOG RIVER, BARANGAY SUMANGGA, MOGPOG, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱47.9M | 100% | Medium risk41 | —-0.074 |
| 116 | 21LE0178CONCRETING OF BRGY. BUCA FMR, BRGY. BUCA, STA. MARIA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.032 |
| 117 | 23EA0050CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOAC RIVER, BARANGAY TABIGUE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱48M | 100% | Medium risk41 | —-0.072 |
| 118 | 22CA0051CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - MULAWIN-TALA ROAD LEADING TO MT. NATIB, BATAAN NATIONAL PARK,ORANI, BATAAN | Region III | Bataan 1st DEO | Completed | ₱14.7M | 100% | Medium risk41 | —-0.100 |
| 119 | 22CD0011CONSTRUCTION OF ADDITIONAL PUMPING STATION AT BARANGAY LAWA, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱19.6M | 100% | Medium risk37 | —-0.093 |
| 120 | 24CD0013CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY SAN ROQUE, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱48.2M | 100% | Medium risk35 | —-0.093 |
| 121 | 22CC0251CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.9M | 100% | Medium risk34 | —-0.107 |
| 122 | 23CC0201SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD LIGHTING ALONG MACARTHUR HIGHWAY, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱24.5M | 100% | Medium risk33 | —-0.105 |
| 123 | 22CD0057REHABILITATION OF SCHOOL BUILDING OF MAASIM ELEMENTARY SCHOOL, SAN ILDEFONSO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.108 |
| 124 | 22CC0256CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. TANGOS, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.109 |
| 125 | 22CC0068REHABILITATION OF ROAD, BARANGAY BAGONG BARRIO, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱9.8M | 100% | Medium risk31 | —-0.106 |