Contractor dossier
73 projects on file, including joint ventures this contractor is part of.
Total projects
73
Total budget
₱731.5M
Average progress
90.0%
Completion rate
67.1%
Below 70%
Average risk score
42.1
Medium risk on average, out of 100
Flagged as unusual
2
2.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 72 | ₱724M | 42.1 | 2 | 89.8% |
| Region VII | 1 | ₱7.5M | 42.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 28 | ₱261.6M | 44.1 | 0 | 88.7% |
| Roads | 24 | ₱345.8M | 43.2 | 0 | 87.4% |
| Water Provision and Storage | 13 | ₱52.2M | 33.3 | 1 | 91.2% |
| Bridges | 6 | ₱23.7M | 38.1 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱8.9M | 93.7 | 1 | 100.0% |
| Flood Control and Drainage | 1 | ₱39.2M | 44.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LG0067REHABILITATION OF MULTI- PURPOSE BUILDING, GOVERNOR GENEROSO, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱8.9M | 100% | High risk94 | Flagged0.013 |
| 22LF0109CONSTRUCTION OF NHJ LINGAYAO TO SITIO SUMANDING LEADING TO SITIO KATAGBAKAN, BRGY. HOLY CROSS, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱99M | 100% | High risk62 | —-0.062 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25LF0110CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY BARANGAY CAYAWAN MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱7.8M | 0% | Medium risk49 | Flagged0.015 |
| 25LG0067REHABILITATION OF MULTI- PURPOSE BUILDING, GOVERNOR GENEROSO, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱8.9M | 100% | High risk94 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 25LF0087REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT), BARANGAY SAN FERMIN MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱7.9M | 70% | Medium risk46 | —-0.036 |
| 27 | 25LF0077CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM COVERED COURT) SITIO LIBUAC BARANGAY OLD MACOPA MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱7.9M | 81% | Medium risk46 | —-0.041 |
| 28 | 25LF0020SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD-K1691+440-K1691+517, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱22.3M | 90% | Medium risk46 | —-0.043 |
| 29 | 25LF0100REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM) BARANGAY CONCEPCION MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱7.9M | 51% | Medium risk46 | —-0.029 |
| 30 | 25LF0031NHJ-LINGAYAO TO SITIO SUMANDING OF BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT PROCESSING, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱6.8M | 0% | Medium risk46 | —-0.013 |
| 31 | 24LF0099CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), HOLY CROSS ELEMENTARY SCHOOL, BARANGAY HOLY CROSS, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱7.9M | 100% | Medium risk46 | —-0.081 |
| 32 | 25LF0048CONSTRUCTION OF ROAD, FROM SITIO GUICOB TO PUROK BASIO TO PUROK MAPAYO, BARANGAY SAN IGNACIO, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱5.9M | 77% | Medium risk46 | —-0.038 |
| 33 | 24LF0077JUNCTION ROSARIO HILLS TO SITIO ENRIQUEZ, BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT, CACAO & BANANA CHIPS PROCESSING SITE, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱6.2M | 95% | Medium risk46 | —-0.038 |
| 34 | 22LF0097CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, DAVAO ORIENTAL STATE COLLEGE OF SCIENCE AND TECHNOLOGY-CATEEL CAMPUS, MAINIT, CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱14.8M | 100% | Medium risk46 | —-0.078 |
| 35 | 23LF0017SURIGAO DEL SUR BDRY.-DAVAO OR COASTAL RD - K1532+183 - K1533+000, BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱20.2M | 100% | Medium risk46 | —-0.077 |
| 36 | 24LF0122CONSTRUCTION OF ROAD FROM HIGHWAY JUNCTION TO SITIO LOWER NAPO, ZARAGOSA, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.078 |
| 37 | 22LF0069NHJ - LINGAYAO TO SITIO SUMANDING OF BRGY. SAN IGNACIO CONNECTING MANAY PUBLIC TERMINAL TO COCONUT PROCESSING, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.078 |
| 38 | 24LF0059SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD-K1659+472-K1659+518, BARANGAY HOLY CROSS, MANAY, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱10M | 100% | Medium risk46 | —-0.079 |
| 39 | 24LF0015CONSTRUCTION OF DPWH OFFICE BUILDING (AREA SHOP), DAVAO ORIENTAL 1ST DEO, BAGANGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱22.5M | 100% | Medium risk46 | —-0.076 |
| 40 | 23LF0108CONSTRUCTION OF DPWH OFFICE BUILDING (MAINTENANCE SECTION), DAVAO ORIENTAL 1ST DEO, LUCOD, BAGANGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.076 |
| 41 | 24LF0061SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD-K1687+050-K1687+082, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱13.7M | 100% | Medium risk46 | —-0.076 |
| 42 | 23LF0015SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD - K1529+793 - K1530+000, BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱5.1M | 100% | Medium risk45 | —-0.074 |
| 43 | 23LF0008SURIGAO DEL SUR BDRY.-DAVAO OR COASTAL RD-K1528+579-K1529+000, BOSTON, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱9.6M | 100% | Medium risk45 | —-0.077 |
| 44 | 23LF0023SURIGAO DEL SUR BDRY-DAVAO OR COASTAL RD - K1541+1011 - K1543+000, CATEEL, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱22M | 100% | Medium risk45 | —-0.077 |
| 45 | 24LF0012CONSTRUCTION (COMPLETION) OF DPWH MAINTENANCE SECTION, DAVAO ORIENTAL 1ST DEO, BAGANGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱14.7M | 100% | Medium risk45 | —-0.079 |
| 46 | 24LG0093REPAIR/REHABILITATION/RECONSTRUCTION OF TAGABAKID-BOGAKAN RD. ,BRGY. TAGABAKID, MATI CITY, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | Completed | ₱28.8M | 100% | Medium risk45 | —-0.075 |
| 47 | 25LF0016CONSTRUCTION (COMPLETION) OF DPWH OFFICE BUILDING (CONSTRUCTION SECTION), DAVAO ORIENTAL 1ST DEO, BAGANGA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | On-Going | ₱9.7M | 100% | Medium risk45 | —-0.051 |
| 48 | 24LF0135CONSTRUCTION/COMPLETION OF MULTIPURPOSE BUILDING (BFP FIRE STATION WITH MEZZANINE), CENTRAL, TARRAGONA, DAVAO ORIENTAL | Region XI | Davao Oriental 1st DEO | Completed | ₱7.4M | 100% | Medium risk45 | —-0.079 |
| 49 | 24LG0100CONSTRUCTION OF MULTI-PURPOSE BUILDING (VISITORS' FACILITIES), MOUNT HAMIGUITAN, SAN ISIDRO, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱9.8M | 12% | Medium risk45 | —-0.013 |
| 50 | 24LG0096CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BATOBATO, SAN ISIDRO, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱9.8M | 100% | Medium risk45 | —-0.050 |