Opening the dossier…
Opening the dossier…
Contractor dossier
127 projects on file, including joint ventures this contractor is part of.
Total projects
127
Total budget
₱2.1B
Average progress
95.5%
Completion rate
81.9%
Average risk score
39.1
Medium risk on average, out of 100
Flagged as unusual
5
3.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 119 | ₱1.9B | 38.8 | 5 | 96.8% |
| National Capital Region | 8 | ₱232.4M | 43.6 | 0 | 76.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 62 | ₱320.5M | 30.7 | 0 | 99.8% |
| Roads | 43 | ₱1.1B | 38.6 | 0 | 93.4% |
| Flood Control and Drainage | 12 | ₱375.2M | 39.9 | 0 | 93.1% |
| GAA 2025 SSP | 5 | ₱162.9M | 93.8 | 5 | 79.5% |
| GAA 2025 OO-1 | 4 | ₱90.5M | 91.3 | 0 | 86.7% |
| GAA 2025 OO-2 | 1 | ₱47.8M | 91.6 | 0 | 61.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EH0127CONSTRUCTION OF ROAD IN BARANGAY AGNIPA, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱48M | 36% | High risk95 | Flagged0.024 |
| 25EH0022CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 76% | High risk94 | Flagged0.019 |
| 25EH0069CONSTRUCTION OF LUNAS FLOOD CONTROL STRUCTURE, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱29M | 90% | High risk94 | Flagged0.009 |
| 25EH0092CONSTRUCTION OF MULTI-PURPOSE BUILDING (CSC BUILDING) CIVIL SERVICE COMMISSION, BARANGAY POBLACION, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.8M | 96% | High risk93 | Flagged0.007 |
| 25EH0114COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY TUGUIS, LOOC, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.007 |
| 25EH0049REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0121+724.00 - K0122+121 (AS PER RBIA), K0121+724.00 - K0122+112 (AS PER ACTUAL), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱28.7M | 84% | High risk93 | —-0.004 |
| 25EH0026REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0104+024.90 - K0104+564, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱27.8M | 82% | High risk92 | —-0.003 |
| 25EH0068REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0106+000.00 - K0106+392.00, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱29M | 87% | High risk92 | —-0.005 |
| 25EH0128CONSTRUCTION OF ILAYA WATER IMPOUNDING PROJECT, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱47.8M | 61% | High risk92 | —-0.008 |
| 25EH0146CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0127+760 - K0127+898.50, K0127+902.90 - K0128+022 AS PER RBIA, K0127+760 - K0127+898.50, K0127+902.90 - K0128+020 AS PER ACTUAL, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱5M | 94% | High risk88 | —-0.004 |
| 25EH0083CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), ROMBLON STATE UNIVERSITY (RSU), BARANGAY LIWANAG, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.8M | 100% | High risk67 | —-0.035 |
| 21E00034CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) CONSTRUCTION OF SANTA MARIA MUNICIPAL POLICE STATION BUI | Region IV-B | Region IV-B | Completed | ₱9.6M | 100% | High risk64 | —-0.058 |
| 21E00033CONST./IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS) CONST. OF SAN ANDRES MUNICIPAL POLICE STATION BUILDING, SAN ANDRES, ROMBLON | Region IV-B | Region IV-B | Completed | ₱9.6M | 100% | High risk63 | —-0.058 |
| 25EH0016ACCESS ROAD LEADING TO BLUE HOLE, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.8M | 100% | High risk62 | —-0.050 |
| 24EH0086REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG ROMBLON COGON SABLAYAN ROAD, K0000+070-K0000+390, K0002+000 - K0004+000, K0009+000 - K0010+505 AS PER ACTUAL RBIA, ROMBLON ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱144.8M | 82% | High risk61 | —-0.041 |
| 25EH0091CONSTRUCTION OF ROAD LEADING TO GROTTO, CONCEPCION, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.6M | 100% | High risk60 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EH0127CONSTRUCTION OF ROAD IN BARANGAY AGNIPA, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱48M | 36% | High risk95 | Flagged0.024 |
| 25EH0022CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 76% | High risk94 | Flagged0.019 |
| 25EH0069CONSTRUCTION OF LUNAS FLOOD CONTROL STRUCTURE, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱29M | 90% | High risk94 | Flagged0.009 |
| 25EH0092CONSTRUCTION OF MULTI-PURPOSE BUILDING (CSC BUILDING) CIVIL SERVICE COMMISSION, BARANGAY POBLACION, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.8M | 96% | High risk93 | Flagged0.007 |
| 25EH0114COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY TUGUIS, LOOC, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 24EH0138CONCRETING OF SITIO KABISIG, BRGY. TUGUIS FMR, BRGY. TUGUIS, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱14.9M | 100% | Medium risk37 | —-0.040 |
| 52 | 25EH0113REHABILITATION OF ROXAS AVENUE PROVINCIAL ROAD, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱4.9M | 43% | Medium risk37 | —-0.053 |
| 53 | 25EH0038CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GUINHA-YAAN, LOOC, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱4.9M | 96% | Medium risk37 | —-0.054 |
| 54 | 24EH0042CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0022+624 - K0022+990.42 (AS PER RBIA), K0022+636 - K0023+002.42 (AS PER ACTUAL), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.9M | 100% | Medium risk37 | —-0.091 |
| 55 | 22EH0027CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0013+154 - K0013+484, K0013+570 - K0013+693 (AS PER RBIA & ACTUAL), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.8M | 100% | Medium risk37 | —-0.091 |
| 56 | 25EH0065CONSTRUCTION OF MULTI-PURPOSE BUILDING (SCHOOL CANTEEN), LOOC CENTRAL ELEMENTARY SCHOOL, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.9M | 100% | Medium risk37 | —-0.087 |
| 57 | 24EH0007CONSTRUCTION OF ACCESS ROAD LEADING TO FUERZA SAN ANDRES FORT, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱24M | 71% | Medium risk37 | —-0.058 |
| 58 | 24EH0149CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT LIMON NORTE NATIONAL HIGH SCHOOL, BARANGAY LIMON NORTE, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk37 | —-0.046 |
| 59 | 24EH0006CONSTRUCTION OF ACCESS ROAD LEADING TO TRANGKALAN FALLS, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱24.1M | 100% | Medium risk36 | —-0.092 |
| 60 | 24EH0095CONSTRUCTION OF ACCESS ROAD - JUNCTION NATIONAL ROAD TO CAMANTAYA INTERIOR LOCAL ROAD, BRGY. CAMANTAYA, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱19.8M | 100% | Medium risk36 | —-0.092 |
| 61 | 24EH0054REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG ODIONGAN-EAST-WEST ROAD, K0005+362.00 - K0005+840.00, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱22.9M | 100% | Medium risk36 | —-0.094 |
| 62 | 19EH0018CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), POBLACION, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱7.4M | 100% | Medium risk36 | —-0.088 |
| 63 | 25EH0027ACCESS ROAD LEADING TO FUERZA SAN ANDRES FORT, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱9.7M | 41% | Medium risk36 | —-0.055 |
| 64 | 25EH0011CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CRISPIN GRIMARES ELEMENTARY SCHOOL, BARANGAY LIMON NORTE, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.9M | 100% | Medium risk36 | —-0.087 |
| 65 | 22EH0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUINHAYA-AN, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.8M | 100% | Medium risk36 | —-0.087 |
| 66 | 24EH0144CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT SINAPAWAN ELEMENTARY SCHOOL, BARANGAY SUGOD, CAJIDIOCAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk36 | —-0.048 |
| 67 | 24EH0094CONSTRUCTION OF ACCESS ROAD LEADING TO BLUE HOLE DIVE SITE PHASE II, BRGY. CAWAYAN, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱9.9M | 100% | Medium risk36 | —-0.090 |
| 68 | 22EH0104CONCRETING OF BRGY. CAMANTAYA FMR, STA. 00+000.00 - STA. 00+326.00, BRGY. CAMANTAYA, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱14.9M | 100% | Medium risk36 | —-0.040 |
| 69 | 20EH0081REHABILITATION/CONCRETING OF LOCAL ROAD, BRGY. MAPULA, ROMBLON, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱9.7M | 100% | Medium risk36 | —-0.091 |
| 70 | 18EH0002CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT) AT BUENAVISTA ELEMENTARY SCHOOL, BRGY. BUENAVISTA, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱7.2M | 100% | Medium risk36 | —-0.087 |
| 71 | 19EH0017CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), PROGRESO WESTE, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱6.9M | 100% | Medium risk36 | —-0.088 |
| 72 | 22EH0070CONSTRUCTION OF MULTI-PURPOSE BUILDING, LOOC CENTRAL ELEMENTARY SCHOOL, BARANGAY POBLACION, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱4.9M | 100% | Medium risk36 | —-0.087 |
| 73 | 24EH0014CONSTRUCTION OF MULTI-PURPOSE BUILDING, TUGUIS, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk36 | —-0.087 |
| 74 | 21EH0052OFF - CARRIAGEWAY IMPROVEMENT ALONG TABLAS CIRCUMFERENTIAL ROAD, K0001+243 - K0001+536, K0009+992.80 - K0011+130 (AS PER ACTUAL)/ K0001+243 - K0001+536, K0009+991.80 - K0011+133 (AS PER RBIA), TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱13.4M | 100% | Medium risk36 | —-0.092 |
| 75 | 24EH0001CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO BALINSASAYAO, BARANGAY BUENAVISTA, LOOC, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱5M | 100% | Medium risk36 | —-0.087 |