86 projects on file, including joint ventures this contractor is part of.
Total projects
86
Total budget
₱1.1B
Average progress
95.5%
Completion rate
88.4%
Average risk score
36.3
Medium risk on average, out of 100
Flagged as unusual
5
5.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 83 | ₱1B | 35.1 | 2 | 98.4% |
| Region VI | 3 | ₱43.3M | 71.0 | 3 | 17.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 53 | ₱357.4M | 30.6 | 4 | 93.7% |
| Roads | 27 | ₱513.3M | 44.0 | 0 | 100.0% |
| Flood Control and Drainage | 5 | ₱203.5M | 44.9 | 0 | 100.0% |
| OTHER | 1 | ₱11.9M | 88.3 | 1 | 50.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24G00120CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - HINOBAAN SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.9M | 51% | High risk88 | Flagged0.063 |
| 25GN0059CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY CALUMANGAN (BARANGAY HALL), BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 80% | High risk68 | —-0.030 |
| 25GN0060CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY CALUMANGAN (COVERED COURT), BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 86% | High risk68 | —-0.031 |
| 24GO0019CONSTRUCTION OF REVETMENT IN SUM-AG RIVER, BACOLOD CITY,NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱144.8M | 100% | High risk64 | —-0.043 |
| 24G00136LGU HOSPITALS- LA CASTELLANA MUNICIPAL HOSPITAL, NEGROS OOCIDENTAL | Region VI | Region VI | On-Going | ₱19.6M | 0% | High risk63 | Flagged0.045 |
| 24G00082CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - LA CASTELLANA SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.7M | 0% | High risk62 | Flagged0.050 |
| 17RB0223CONSTRUCTION OF FARM TO MILL ROAD OF STA. TERESITA, BRGY. DOS HERMANAS - HIYANG HIYANG (STA. 0+000 - STA. 0+574), TALISAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱11.5M | 100% | High risk61 | —-0.013 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24G00120CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - HINOBAAN SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.9M | 51% | High risk88 | Flagged0.063 |
| 24G00082CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - LA CASTELLANA SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.7M | 0% | High risk62 | Flagged0.050 |
| 24G00136LGU HOSPITALS- LA CASTELLANA MUNICIPAL HOSPITAL, NEGROS OOCIDENTAL | Region VI | Region VI | On-Going | ₱19.6M | 0% | High risk63 | Flagged0.045 |
| 24GN0083CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING IN A. SIAN ELEMENTARY SCHOOL, BARANGAY NAPOLES, BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 100% | Medium risk50 | Flagged0.008 |
| 24GN0091CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING IN SAN MIGUEL ELEMENTARY SCHOOL II, SITIO DULOM, BARANGAY SAN MIGUEL, LA CARLOTA CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 100% | Medium risk49 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24G00120CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - HINOBAAN SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.9M | 51% | High risk88 | Flagged0.063 |
| 2 | 25GN0059CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY CALUMANGAN (BARANGAY HALL), BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 80% | High risk68 | —-0.030 |
| 3 | 25GN0060CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY CALUMANGAN (COVERED COURT), BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 86% | High risk68 | —-0.031 |
| 4 | 24GO0019CONSTRUCTION OF REVETMENT IN SUM-AG RIVER, BACOLOD CITY,NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱144.8M | 100% | High risk64 | —-0.043 |
| 5 | 24G00136LGU HOSPITALS- LA CASTELLANA MUNICIPAL HOSPITAL, NEGROS OOCIDENTAL | Region VI | Region VI | On-Going | ₱19.6M | 0% | High risk63 | Flagged0.045 |
| 6 | 24G00082CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - LA CASTELLANA SUPER HEALTH CENTER, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱11.7M | 0% | High risk62 | Flagged0.050 |
| 7 | 17RB0223CONSTRUCTION OF FARM TO MILL ROAD OF STA. TERESITA, BRGY. DOS HERMANAS - HIYANG HIYANG (STA. 0+000 - STA. 0+574), TALISAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱11.5M | 100% | High risk61 | —-0.013 |
| 8 | 21GK0032CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO IMBANG SAN FERNANDO TUNANGAN (SAN ANTONIO) ROAD, BRGY. SAN FERNANDO, TALISAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱71.9M | 100% | Medium risk52 | —-0.086 |
| 9 | 24GN0083CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING IN A. SIAN ELEMENTARY SCHOOL, BARANGAY NAPOLES, BAGO CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 100% | Medium risk50 | Flagged0.008 |
| 10 | 24GO0100CONSTRUCTION OF ROAD ALONG BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SEGMENT 1,BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱49.5M | 100% | Medium risk49 | —-0.091 |
| 11 | 24GN0091CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING IN SAN MIGUEL ELEMENTARY SCHOOL II, SITIO DULOM, BARANGAY SAN MIGUEL, LA CARLOTA CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱4.9M | 100% | Medium risk49 | Flagged0.007 |
| 12 | 23GL0030CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH BUILDING, NEGROS OCCIDENTAL 2ND DEO, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱29M | 100% | Medium risk47 | —-0.079 |
| 13 | 21GL0020CONSTRUCTION (EXPANSION) OF MULTI-PURPOSE BUILDING (HEMODIALYSIS CENTER) AT IGNACIO L. ARROYO MEMORIAL DISTRICT HOSPITAL, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱19.8M | 100% | Medium risk46 | —-0.083 |
| 14 | 24GL0078CONSTRUCTION OF HEMODIALYSIS CENTER, IGNACIO L. ARROYO MEMORIAL DISTRICT HOSPITAL, ISABELA, NEGROS OCCIDENTAL (PHASE 3) | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱20.3M | 100% | Medium risk46 | —-0.084 |
| 15 | 20GL0084CONSTRUCTION/REHABILITATION OF HEMODIALYSIS CENTER AT IGNACIO L. ARROYO SR. MEMORIAL DISTRICT HOSPITAL INCLUDING SITE DEVELOPMENT, ISABELA, PROVINCE OF NEGROS OCCIDENTAL IN DUMIRANO, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.084 |
| 16 | 23GK0132CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - BACOLOD NORTH RD (S00406NR) - K0033 + 676 - K0035 + 000 | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱31.4M | 100% | Medium risk45 | —-0.091 |
| 17 | 22GK0067RECONSTRUCTION OF CONCRETE ROAD-BANGGA DOSE-FIRST FARMER'S MILL-BARANGAY CONCEPCION TOURISM ROAD, BRGY. DOS HERMANAS, TALISAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱33.4M | 100% | Medium risk45 | —-0.092 |
| 18 | 23GL0020ROAD WIDENING - HINIGARAN-ISABELA RD - K0065 + 680 - K0066 + 348 | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱29.6M | 100% | Medium risk45 | —-0.091 |
| 19 | 22GK0016CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MATAGOY CREEK (UPSTREAM), SILAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.068 |
| 20 | 23GO0032CONSTRUCTION OF DRAINAGE STRUCTURE - CONSTRUCTION OF DRAINAGE SYSTEM, LUZURIAGA ST., BACOLOD CITY, NEGROS OCCIDENTAL | Negros Island Region | Bacolod City DEO | Completed | ₱18.6M | 100% | Medium risk45 | —-0.068 |
| 21 | 21GK0170CONSTRUCTION FLOOD CONTROL STRUCTURE, BRGY. LANTAD, SILAY CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.068 |
| 22 | 23GK0099CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINOYAN, MURCIA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱5.9M | 100% | Medium risk45 | —-0.087 |
| 23 | 23GN0072CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. GOMEZ, PONTEVEDRA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | Completed | ₱7.9M | 100% | Medium risk45 | —-0.087 |
| 24 | 23GK0098CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BLUMENTRITT, MURCIA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.087 |
| 25 | 25GL0079CONSTRUCTION OF HEMODIALYSIS CENTER, IGNACIO L. ARROYO MEMORIAL DISTRICT HOSPITAL, ISABELA, NEGROS OCCIDENTAL (PHASE 4) | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱14.7M | 100% | Medium risk45 | —-0.061 |