Contractor dossier
52 projects on file, including joint ventures this contractor is part of.
Total projects
52
Total budget
₱1.1B
Average progress
86.0%
Completion rate
57.7%
Below 70%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
1
1.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 52 | ₱1.1B | 51.3 | 1 | 86.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 23 | ₱306.1M | 49.9 | 0 | 78.6% |
| Flood Control and Drainage | 14 | ₱504.8M | 49.5 | 0 | 93.9% |
| OTHER | 6 | ₱164.3M | 70.3 | 1 | 91.7% |
| Roads | 5 | ₱65.9M | 43.0 | 0 | 79.7% |
| Bridges | 3 | ₱43.5M | 47.5 | 0 | 99.7% |
| Water Provision and Storage | 1 | ₱13.2M | 47.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DI0158REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0068 + (-282) - K0069 + 098 | Region IV-A | Laguna 2nd DEO | On-Going | ₱120.5M | 50% | High risk75 | Flagged0.011 |
| 23DI0086REHABILITATION OF DRAINAGE AT BARANGAY BUCAL, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱6.7M | 100% | High risk71 | —-0.043 |
| 23DI0099IMPROVEMENT OF ROAD WITH DRAINAGE AT BARANGAY PACIANO RIZAL, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱10.6M | 100% | High risk69 | —-0.042 |
| 23DI0090REHABILITATION OF ROAD WITH DRAINAGE, BRGY.BATINO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱11.6M | 100% | High risk69 | —-0.042 |
| 23DI0088REHABILITATION OF ROAD AND DRAINAGE, BARANGAY PULONG SANTA CRUZ, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱9.9M | 100% | High risk69 | —-0.042 |
| 23DI0074REHABILITATION OF ROAD AND DRAINAGE, BARANGAY RIVERSIDE, CITY OF SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.9M | 100% | High risk69 | —-0.042 |
| 25DI0065CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION AT SAN CRISTOBAL RIVER, BRGY. PACIANO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 76% | High risk65 | —-0.039 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DI0158REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0068 + (-282) - K0069 + 098 | Region IV-A | Laguna 2nd DEO | On-Going | ₱120.5M | 50% | High risk75 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24DI0158REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CALAMBA-STA CRUZ-FAMY JCT RD - K0068 + (-282) - K0069 + 098 | Region IV-A | Laguna 2nd DEO | On-Going | ₱120.5M | 50% | High risk75 | Flagged0.011 |
| 2 | 23DI0086REHABILITATION OF DRAINAGE AT BARANGAY BUCAL, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱6.7M | 100% | High risk71 | —-0.043 |
| 3 | 23DI0099IMPROVEMENT OF ROAD WITH DRAINAGE AT BARANGAY PACIANO RIZAL, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱10.6M | 100% | High risk69 | —-0.042 |
| 4 | 23DI0090REHABILITATION OF ROAD WITH DRAINAGE, BRGY.BATINO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱11.6M | 100% | High risk69 | —-0.042 |
| 5 | 23DI0088REHABILITATION OF ROAD AND DRAINAGE, BARANGAY PULONG SANTA CRUZ, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱9.9M | 100% | High risk69 | —-0.042 |
| 6 | 23DI0074REHABILITATION OF ROAD AND DRAINAGE, BARANGAY RIVERSIDE, CITY OF SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.9M | 100% | High risk69 | —-0.042 |
| 7 | 25DI0065CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION AT SAN CRISTOBAL RIVER, BRGY. PACIANO, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 76% | High risk65 | —-0.039 |
| 8 | 24DI0167CONSTRUCTION OF MULTI-PURPOSE BUILDING, STO. NINO ELEMENTARY SCHOOL, BARANGAY STO NINO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱49.5M | 90% | Medium risk56 | —-0.058 |
| 9 | 24DI0033CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION ALONG SAN JUAN RIVER BRGY.BANADERO AND BRGY SAN JUAN CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱84.4M | 89% | Medium risk53 | —-0.034 |
| 10 | 24DI0085CONSTRUCTION OF REVETMENT ALONG SAN JUAN RIVER, BRGY. PARIAN, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱58.9M | 100% | Medium risk53 | —-0.045 |
| 11 | 24DI0042CONSTRUCTION OF RIVER PROTECTION STRUCTURE AT CABUYAO RIVER, NEAR MALITLIT-ETON ACCESS ROAD, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱85.4M | 100% | Medium risk53 | —-0.076 |
| 12 | 21DI0120CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY LANGGAM, SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱29M | 100% | Medium risk53 | —-0.101 |
| 13 | 24DI0195CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALAMBA, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29.2M | 95% | Medium risk53 | —-0.067 |
| 14 | 23DI0129REHABILITATION OF MULTI-PURPOSE BUILDING OF BARANGAY LABAS, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29M | 0% | Medium risk52 | —-0.016 |
| 15 | 25DI0020CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BACLARAN ELEMENTARY SCHOOL, BARANGAY BACLARAN, CABUYAO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱29M | 39% | Medium risk52 | —-0.046 |
| 16 | 23DI0110REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PACITA 1, CITY OF SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.9M | 100% | Medium risk52 | —-0.105 |
| 17 | 23DI0039CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY STO. DOMINGO, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.8M | 100% | Medium risk52 | —-0.105 |
| 18 | 23DI0160CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ESTRELLA, CITY OF SAN PEDRO, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.8M | 10% | Medium risk52 | —-0.023 |
| 19 | 22DI0022REHABILITATION OF MAGSAYSAY ROAD AT BARANGAY SAN ANTONIO, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱48.2M | 99% | Medium risk51 | —-0.048 |
| 20 | 24DI0164CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VI, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.9M | 0% | Medium risk51 | —-0.030 |
| 21 | 24DI0142REHABILITATION OF COVERED COURT, TADLAC ELEMENTARY SCHOOL, BRGY. TADLAC, LOS BANOS, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.104 |
| 22 | 24DI0103REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SAN AGUSTIN, MUNICIPALITY OF BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱4.8M | 90% | Medium risk51 | —-0.057 |
| 23 | 23DI0206CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN OFFICE), BARANGAY TRANCA, BAY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.106 |
| 24 | 21DI0078CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PHASE 3 GARDEN VILLAS SUBDIVISION, BARANGAY MALUSAK, SANTA ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱19.3M | 100% | Medium risk51 | —-0.104 |
| 25 | 24DI0194CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALAMBA, CALAMBA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱19.5M | 0% | Medium risk51 | —-0.033 |