Opening the dossier…
Opening the dossier…
Contractor dossier
2 projects on file, including joint ventures this contractor is part of.
Total projects
2
Total budget
₱58.5M
Average progress
97.3%
Completion rate
0.0%
Below 70%
Average risk score
28.6
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 2 | ₱58.5M | 28.6 | 0 | 97.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 1 | ₱48.8M | 30.0 | 0 | 98.6% |
| Roads | 1 | ₱9.8M | 27.2 | 0 | 96.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24MC0033CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER STA. 63+370 - STA. 63+710 R/S, BARANGAY NEW BULATUKAN, MAKILALA, COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱48.8M | 99% | Low risk30 | —-0.029 |
| 2 | 25MC0033CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO DON BOSCO BIODYNAMIC FARM, SANGGAWAN FALLS AND HOT SPRING, BRGY. BATASAN, MAKILALA, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱9.8M | 96% | Low risk27 | —-0.053 |