Contractor dossier
300 projects on file, including joint ventures this contractor is part of.
Total projects
300
Total budget
₱23.9B
Average progress
94.5%
Completion rate
69.0%
Below 70%
Average risk score
61.4
High risk on average, out of 100
Flagged as unusual
24
8.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 276 | ₱20.4B | 62.1 | 21 | 94.5% |
| Region X | 21 | ₱729.3M | 51.3 | 1 | 95.4% |
| Central Office | 2 | ₱2.8B | 79.0 | 2 | 90.2% |
| Region XI | 1 | ₱39.2M | 47.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 210 | ₱15.8B | 60.6 | 7 | 96.2% |
| Flood Control and Drainage | 33 | ₱2.7B | 65.9 | 1 | 87.6% |
| Buildings and Facilities | 20 | ₱585.5M | 46.9 | 1 | 100.0% |
| Bridges | 17 | ₱669.9M | 55.9 | 3 | 93.6% |
| GAA 2025 OO-1 | 7 | ₱512.1M | 93.8 | 4 | 67.7% |
| OTHER | 7 | ₱1.8B | 77.3 | 5 | 100.0% |
| GAA 2025 SSP | 2 | ₱151.4M | 94.8 | 2 | 64.6% |
| Bridges, Roads | 2 | ₱1.5B | 76.1 | 1 | 86.7% |
| Water Provision and Storage | 2 | ₱68.7M | 49.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KH0017INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CDO-AIRPORT-BUKIDNON RD - K1440 + 900 - K1442 + 422, K1445 + 000 - K1447 + 500, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱73.4M | 79% | High risk95 | Flagged0.009 |
| 25J00036PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱78M | 50% | High risk95 | Flagged0.032 |
| 25JB0069PREVENTIVE MAINTENANCE RIZAL-DAKAK-DAPITAN COASTAL LOOP ROAD K1828+673.20-K1829+000, K1829+000-K1830+000,K1830+000-K1831+000,K1831+000-K1831+208.30 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱93.5M | 95% | High risk94 | Flagged0.002 |
| 25JB0025PREVENTIVE MAINTENANCE DIPOLOG-PUNTA-DANSULLAN-S. OSMEÑA-ZAMBOANGA DEL NORTE/SUR BDRY RD K1872+402-K1873+887.70 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱53.5M | 57% | High risk94 | Flagged0.008 |
| 25JB0071PREVENTIVE MAINTENANCE POLANCO-MACLEODES ROAD K1832+013.40-K1833+000, K1833+000-K1834+704.10 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱93.5M | 55% | High risk94 | Flagged0.014 |
| 25KH0064ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD (S01247MN) - K1441+(-840) - K1441+817, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱77.2M | 79% | High risk94 | —-0.005 |
| 25KH0063ASSET PRES-PREV MAINT- PRIMARY ROADS BUT CITY-CAG DE ORO CITY-ILIGAN CITY RD (S01246MN) - K1441+291 - K1441+666, (S01246MN) - K1441+666 - K1441+832, (S01246MN) - K1441+832 - K1442+610, (S01246MN) - K1442+610 - K1443+350 (S01246MN) -K1443+350 - K1444+236 | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱77.1M | 80% | High risk94 | —-0.006 |
| 25J00056ROAD WIDENING - PRIMARY ROADS MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱64.3M | 12% | High risk94 | Flagged0.022 |
| 25KH0066ASSET PRES. - PREV. MAINT- TERTIARY RD CDO-CADRE CIRC. EXT RD (S00580MN) CH 0 - CH 755, (S00604MN) CH 0 - CH 556, CDO-CADRE CIRC EXT RD (S00581MN) CHAINAGE 0 - CHAINAGE 473, (S00581MN) CHAINAGE 0 - CHAINAGE 473, (S00602MN) CHAINAGE 0 - CHAINAGE 439, CDOC | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱53M | 95% | High risk93 | —-0.014 |
| 17J00071CONSTRUCTION OF KUMALARANG PSCG BRIDGE #3 AND APPROACHES ALONG IMELDA - BAYOG - KUMALARANG - LAPUYAN - MARGOSATUBIG ROAD, ZAMBOANGA DEL SUR, STA. 0+000.00 - STA. 0+600.00, ABUTMENT -A : STA. 0+260.00, ABUTMENT -B : STA. 0+350.84, RIVER PROTECTION NET LEN | Region IX | Region IX | Completed | ₱114.5M | 100% | High risk82 | —-0.017 |
| 23JA0021CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BUNGUIAO FLOOD CONTROL STRUCTURE, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.9M | 100% | High risk81 | Flagged0.017 |
| 18Z00023PR-06, ALICIA - MALANGAS ROAD, ZAMBOANGA SIBUGAY (K1769+648.00 - K1793+751.43) | Central Office | Roads Management Cluster II (Multilateral) | Completed | ₱1.4B | 100% | High risk79 | Flagged0.011 |
| 19Z00014PR-13, SIAY-GAPOL ROAD, ZAMBOANGA SIBUGAY K1761+473.00-K1797+234.10 UNDER ADB LOAN 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.3B | 80% | High risk78 | Flagged0.022 |
| 23JB0010CONSTRUCTION OF MULTIPURPOSE BUILDING (BARANGAY HALL) OPAO, DAPITAN CITY,ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱4.9M | 100% | High risk78 | Flagged0.009 |
| 23JB0048REHAB/RECONST OF NATIONAL RD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE DIPOLOG-PUNTA-DANSULLAN-S. OSMEÑA-ZAMBOANGA DEL NORTE/SUR BDRY ROAD K1878+900-K1878+979.60, K1879+100-K1879+180 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱24.2M | 100% | High risk77 | Flagged0.010 |
| 23J00160PREVENTIVE MAINTENANCE - PRIMARY ROADS - PAGADIAN CITY - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱143.7M | 55% | High risk75 | —-0.010 |
| 18JI0072CONSTRUCTION OF BRIDGE AND ROAD APPROACHES, BRGY. CONCEPCION, ALICIA, Z.S | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱44.9M | 100% | High risk75 | —-0.012 |
| 25J00011CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER AT KIPIT BR. 2 SECTION (B01183MN) ALONG LILOY-SIOCON RD (S01146MN) (DOWNSTREAM - LEFT SI | Region IX | Region IX | On-Going | ₱145.6M | 63% | High risk74 | —-0.008 |
| 24J00155CONSTRUCTION OF ROAD ALONG NRJ BARANGAY CAMUL - NRJ BARANGAY LUMBAYAO PACKAGE 2, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱173.6M | 93% | High risk74 | —-0.018 |
| 18J00015CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUENAVISTA - BOLONG COASTAL BYPASS ROAD (CURUAN - LUBIGAN SECTION) INCLUDING BRIDGE, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱127.7M | 100% | High risk73 | —-0.052 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24J00287ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONCRETING ALONG NRJ BARANGAY SAN ISIDRO - SAS - KALAWIT - NAMNAMA, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱154.3M | 60% | High risk66 | Flagged0.049 |
| 25J00036PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO-PAGADIAN-ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱78M | 50% | High risk95 | Flagged0.032 |
| 22J00123CONSTRUCTION OF MISSING LINKS/NEW ROADS - SINDANGAN - BAYOG - LAKEWOOD ROAD, BIWA BRIDGE, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱64.3M | 24% | High risk62 | Flagged0.023 |
| 21J00067CONSTRUCTION OF NEW BRIDGES - LIBA BRIDGE ALONG SINDANGAN - BAYOG - LAKEWOOD ROAD, ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱134.2M | 67% | High risk73 | Flagged0.022 |
| 25J00056ROAD WIDENING - PRIMARY ROADS MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱64.3M | 12% | High risk94 | Flagged0.022 |
| 19Z00014PR-13, SIAY-GAPOL ROAD, ZAMBOANGA SIBUGAY K1761+473.00-K1797+234.10 UNDER ADB LOAN 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.3B | 80% | High risk78 | Flagged0.022 |
| 19J00013REPLACEMENT OF PERMANENT WEAK BRIDGE - VITALI BRIDGE (PARALLEL BRIDGE) ALONG PAGADIAN CITY - ZAMBOANGA CITY ROAD, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱89.6M | 100% | High risk67 | Flagged0.017 |
| 23JA0021CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BUNGUIAO FLOOD CONTROL STRUCTURE, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.9M | 100% | High risk81 | Flagged0.017 |
| 25JB0071PREVENTIVE MAINTENANCE POLANCO-MACLEODES ROAD K1832+013.40-K1833+000, K1833+000-K1834+704.10 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱93.5M | 55% | High risk94 | Flagged0.014 |
| 18Z00023PR-06, ALICIA - MALANGAS ROAD, ZAMBOANGA SIBUGAY (K1769+648.00 - K1793+751.43) | Central Office | Roads Management Cluster II (Multilateral) | Completed | ₱1.4B | 100% | High risk79 | Flagged0.011 |
| 23JB0048REHAB/RECONST OF NATIONAL RD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE DIPOLOG-PUNTA-DANSULLAN-S. OSMEÑA-ZAMBOANGA DEL NORTE/SUR BDRY ROAD K1878+900-K1878+979.60, K1879+100-K1879+180 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱24.2M | 100% | High risk77 | Flagged0.010 |
| 23JB0010CONSTRUCTION OF MULTIPURPOSE BUILDING (BARANGAY HALL) OPAO, DAPITAN CITY,ZN | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱4.9M | 100% | High risk78 | Flagged0.009 |
| 25KH0017INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CDO-AIRPORT-BUKIDNON RD - K1440 + 900 - K1442 + 422, K1445 + 000 - K1447 + 500, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱73.4M | 79% | High risk95 | Flagged0.009 |
| 19J00134CONCRETING OF BRGY. GATA - GATA FMR, BRGY. GATA - GATA, PANGLIMA ESTINO, SULU | Region IX | Region IX | Completed | ₱14.7M | 100% | High risk67 | Flagged0.008 |
| 25JB0025PREVENTIVE MAINTENANCE DIPOLOG-PUNTA-DANSULLAN-S. OSMEÑA-ZAMBOANGA DEL NORTE/SUR BDRY RD K1872+402-K1873+887.70 | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱53.5M | 57% | High risk94 | Flagged0.008 |
| 19J00132CONCRETING OF BRGY. BATU UGIS FMR, BRGY. BATU UGIS, MAIMBUNG, SULU | Region IX | Region IX | Completed | ₱14.7M | 100% | High risk68 | Flagged0.008 |
| 21J00086CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - REHABILITATION OF JOLO MAINLAND WATER DISTRICT, BRGY. ASTURIAS, JOLO, SULU | Region IX | Region IX | Completed | ₱173.2M | 100% | High risk70 | Flagged0.007 |
| 25J00032ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (LANAO- PAGADIAN- ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱112.1M | 13% | High risk67 | Flagged0.006 |
| 22J00045CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT DIPLO RIVER, DIPLO BRIDGE (B00551MN) (DOWNSTREAM) ALONG PAGADIAN - ZAMBOANGA CITY ROAD (S01453MN), ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱63M | 63% | High risk62 | Flagged0.004 |
| 22J00112PREVENTIVE MAINTENANCE - TERTIARY ROADS SANGA - SANGA BATO - BATO ROAD | Region IX | Region IX | On-Going | ₱57.9M | 76% | High risk66 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 20JB0067CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD - JCT. DIPOLOG - SINDANGAN-ROAD CONNECTING TO BAGO DALONGDONG (JOAQUIN MACIAS) IN SUPPORT OF RICE, RUBBER, COCONUT, & ABACA INDUSTRIES, SINDANGAN, ZAMBOANGA DEL NORTE. | Region IX | Zamboanga del Norte 2nd DEO | Completed | ₱72.3M | 100% | High risk62 | —-0.076 |
| 152 | 22J00095ROAD WIDENING - SECONDARY ROADS - JOLO-INDANAN-PARANG-SILANGKAN ROAD (PACKAGE 1) | Region IX | Region IX | Completed | ₱113.7M | 100% | High risk62 | —-0.062 |
| 153 | 23JF0039ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG SALUG - GODOD - KABASALAN ROAD, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.7M | 100% | High risk62 | —-0.075 |
| 154 | 22J00131REHABILITATION OF ROAD - PARANG-MAIMBUNG ROAD | Region IX | Region IX | Completed | ₱96.4M | 100% | High risk62 | —-0.063 |
| 155 | 23JF0036ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG IPIL - LABASON ROAD (VIA TITAY AND KALAWIT), ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱85.9M | 100% | High risk62 | —-0.075 |
| 156 | 22J00044CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BOGAYO RIVER, KUMALARANG BR. 1 SECTION (B00549MN) (DOWNSTREAM RIGHT SIDE) ALONG PAGADIAN CITY - ZAMBOANGA CITY ROAD (S01453MN), BRGY. B | Region IX | Region IX | Completed | ₱82.3M | 100% | High risk62 | —-0.061 |
| 157 | 23JF0038ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG NAGA (BULANSING) - TITAY (PALOMOC) ROAD, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.2M | 100% | High risk62 | —-0.075 |
| 158 | 23J00185INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRANSVERSE MULTIPLE LGU JURISDICTIONS), REHABILITATION OF JOLO - TAGLIBI - TIPTIPON ROAD | Region IX | Region IX | Completed | ₱106M | 100% | High risk62 | —-0.062 |
| 159 | 22J00045CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT DIPLO RIVER, DIPLO BRIDGE (B00551MN) (DOWNSTREAM) ALONG PAGADIAN - ZAMBOANGA CITY ROAD (S01453MN), ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱63M | 63% | High risk62 | Flagged0.004 |
| 160 | 20J00017CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT SIBUGUEY RIVER, BRGY. KAHAYAGAN, BAYOG, ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱70.8M | 100% | High risk62 | —-0.008 |
| 161 | 22JG0027CONSTRUCTION OF MISSING LINK/NEW ROADS ALONG SINDANGAN - BAYOG - LAKEWOOD ROAD (DEPOREHAN BR.), BAYOG ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱68.3M | 100% | High risk62 | —-0.042 |
| 162 | 22J00124CONSTRUCTION OF MISSING LINKS/NEW ROADS SINDANGAN - BAYOG - LAKEWOOD ROAD (PACKAGE I), ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱63.5M | 99% | High risk62 | —-0.023 |
| 163 | 21JB0079CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DISAKAN RIVER (UPSTREAM AND DOWNSTREAM), MANUKAN AND JOSE DALMAN, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 2nd DEO | Completed | ₱67.4M | 100% | High risk62 | —-0.062 |
| 164 | 22J00123CONSTRUCTION OF MISSING LINKS/NEW ROADS - SINDANGAN - BAYOG - LAKEWOOD ROAD, BIWA BRIDGE, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱64.3M | 24% | High risk62 | Flagged0.023 |
| 165 | 21JB0092CONSTRUCTION OF CONCRETE ROAD - JCT. DIPOLOG-SINDANGAN - LILOY ROAD CONNECTING TO BAGO DALONGDONG (JOAQUIN MACIAS) IN SUPPORT OF RICE, RUBBER, COCONUT AND ABACA INDUSTRIES, SINDANGAN, ZAMBOANGA DEL NORTE. | Region IX | Zamboanga del Norte 2nd DEO | Completed | ₱58.9M | 100% | High risk62 | —-0.068 |
| 166 | 23JF0042ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG TITAY (NEW CANAAN) - NAGA (BULANSING) ROAD WITH RCDG BRIDGE, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.7M | 100% | High risk61 | —-0.074 |
| 167 | 23JF0040ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD ALONG - SANDAYONG - GODOD - SALUG ROAD (SANDAYONG - MIAMPIC SECTION, ZAMBOANGA SIBUGAY) | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱86.7M | 100% | High risk61 | —-0.075 |
| 168 | 20J00016CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF KUMALARANG RIVER FLOOD CONTROL, KUMALARANG, ZAMBOANGA DEL SUR | Region IX | Region IX | Completed | ₱75M | 100% | High risk61 | —-0.070 |
| 169 | 17JE0020CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS REPLACEMENT OF PERMANENT WEAK BRIDGES REPLACEMENT OF TUKURAN BRIDGE (BO1196MN) | Region IX | Zamboanga del Sur 1st DEO | Completed | ₱47.5M | 100% | High risk61 | —-0.033 |
| 170 | 23J00183ASSET PRESERVATION PROGRAM - REHABILITATION /RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ROADS JCT. TIMBANGAN ROMANDIER ROAD | Region IX | Region IX | Completed | ₱106M | 100% | High risk61 | —-0.060 |
| 171 | 23J00181ASSET PRESERVATION PROGRAM - REHABILITATION /RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ROADS JCT. TIMBANGAN ROMANDIER ROAD | Region IX | Region IX | Completed | ₱106.1M | 100% | High risk61 | —-0.060 |
| 172 | 23J00182ASSET PRESERVATION PROGRAM - REHABILITATION /RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ROADS JCT. TIMBANGAN ROMANDIER ROAD | Region IX | Region IX | Completed | ₱106.1M | 100% | High risk61 | —-0.060 |
| 173 | 21J00080REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS JOLO - INDANAN - PARANG - SILANGKAN ROAD | Region IX | Region IX | Completed | ₱57.6M | 100% | High risk60 | —-0.067 |
| 174 | 20J00086RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG JOLO-TAGLIBI-TIPTIPON ROAD, SULU | Region IX | Region IX | Completed | ₱85M | 100% | Medium risk60 | —-0.065 |
| 175 | 21J00091CONSTRUCTION OF CONCRETE ROAD CONCRETING OF ROAD AT BARANGAY MATATAL, MAIMBUNG, SULU | Region IX | Region IX | Completed | ₱59.2M | 100% | Medium risk60 | —-0.067 |