Contractor dossier
138 projects on file, including joint ventures this contractor is part of.
Total projects
138
Total budget
₱5.4B
Average progress
89.1%
Completion rate
42.8%
Below 70%
Average risk score
56.3
Medium risk on average, out of 100
Flagged as unusual
18
13.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 138 | ₱5.4B | 56.3 | 18 | 89.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 80 | ₱3.6B | 52.3 | 5 | 89.8% |
| Buildings and Facilities | 21 | ₱223.9M | 51.1 | 0 | 97.0% |
| Bridges | 10 | ₱199.3M | 49.0 | 0 | 99.0% |
| OTHER | 9 | ₱677.1M | 84.2 | 8 | 66.7% |
| Flood Control and Drainage | 9 | ₱291.6M | 48.5 | 0 | 100.0% |
| GAA 2025 SSP | 5 | ₱183M | 95.6 | 4 | 65.5% |
| GAA 2025 OO-1 | 2 | ₱57.9M | 91.9 | 1 | 50.3% |
| GAA 2025 OO-2 | 2 | ₱76M | 86.2 | 0 | 81.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0755+085 - K0755+170, K0755+170 - K0756+000, K | Region VIII | Region VIII | On-Going | ₱46.6M | 41% | High risk96 | Flagged0.024 |
| 25IK0047CSSP- SIPAG- INTERJURISDICTIONALROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION) CONST. OF ROAD, BRGY. BAGACAY TO BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 75% | High risk96 | Flagged0.014 |
| 25IK0052CSSP-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ACCESS ROAD, POB. 1 TO BRGY, BOTAERA, ZUMARRAGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.3M | 18% | High risk96 | Flagged0.027 |
| 25IJ0002CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.9M | 94% | High risk96 | Flagged0.004 |
| 25IJ0008CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TAGAPUL-AN, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.8M | 100% | High risk96 | —-0.000 |
| 25IJ0060OO1: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED ROADS - TERTIARY ROADS CALBAYOG DIVERSION RD. K0739+000 - K0740+000 | Region VIII | Samar 1st DEO | On-Going | ₱34.4M | 10% | High risk92 | Flagged0.017 |
| 24IJ0102(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98M | 62% | High risk92 | Flagged0.068 |
| 25IJ0026OO1: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CALBAYOG DIVERSION RD. - K0733+030 - K0733+347, K0738+000 - K0738+505, K0738+700 - K0739+000 | Region VIII | Samar 1st DEO | On-Going | ₱23.5M | 90% | High risk92 | —-0.004 |
| 25IK0033CONCRETING OF BRGY. ALBALATE TO BRGY. CAGUTIAN TO BRGY. CAGUSIPAN FMR, BRGY. ALBALATE, BRGY. CAGUTIAN, BRGY. CAGUSIPAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 34% | High risk89 | Flagged0.059 |
| 25IK0034CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 64% | High risk89 | Flagged0.051 |
| 25IJ0017OO2: CONTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GANDARA RIVER, PHASE II, BARANGAY PIZARRO, GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱42.8M | 82% | High risk87 | —-0.014 |
| 25IK0037CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DOLONGAN, BASEY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱33.2M | 80% | High risk85 | —-0.012 |
| 24IK0079CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BASEY-MAYDOLONG ROAD, BASEY SECTION, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱270.5M | 56% | High risk85 | Flagged0.042 |
| 24IK0094CONSTRUCTION OF CONCRTE ROAD, BRGY. LAGUNDI TO BRGY. SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.4M | 59% | High risk83 | Flagged0.018 |
| 24IJ0078CSSP: CONSTRUCTION OF ROAD, BRGY. DEIT - BRGY. MAHAYAG, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59M | 86% | High risk81 | Flagged0.006 |
| 24IK0069CONST. OF ROAD, POBLACION TO BARANGAY SOONG, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 77% | High risk80 | Flagged0.006 |
| 24IK0068CONST. OF ROAD, BARANGAY ASTORGA TO BARANGAY SAN VICENTE, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 63% | High risk80 | Flagged0.012 |
| 17IK0001CLUSTER I - PREVENTIVE MAINT. WRIGHT OLD ROUTE, KO826+797-KO826+182; SAN JUANICO-BASEY-SOHOTON ROAD, KO896+290-KO900+500 & KO900+850-KO907+450; SAN JUANICO-BASEY-SOHOTON ROAD, KO909+278-KO909+422 | Region VIII | Samar 2nd DEO | Completed | ₱27.9M | 100% | High risk78 | —-0.035 |
| 21I00056CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO - LAYO - MAGDAWAT - PELAON OF PINABACDAO TO MABINI IN BASEY CONNECTING ...SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱443.9M | 95% | High risk66 | Flagged0.010 |
| 22IK0082CONST. OF MULTI-PURPOSE BUILDING, BRGY. ROÑO, MARABUT, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.073 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IJ0102(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98M | 62% | High risk92 | Flagged0.068 |
| 25IK0033CONCRETING OF BRGY. ALBALATE TO BRGY. CAGUTIAN TO BRGY. CAGUSIPAN FMR, BRGY. ALBALATE, BRGY. CAGUTIAN, BRGY. CAGUSIPAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 34% | High risk89 | Flagged0.059 |
| 25IK0034CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 64% | High risk89 | Flagged0.051 |
| 24IK0079CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BASEY-MAYDOLONG ROAD, BASEY SECTION, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱270.5M | 56% | High risk85 | Flagged0.042 |
| 25IK0052CSSP-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ACCESS ROAD, POB. 1 TO BRGY, BOTAERA, ZUMARRAGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.3M | 18% | High risk96 | Flagged0.027 |
| 17IK0020ROAD WIDENING - DAANG MAHARLIKA (SM) (SAN ISIDRO-SAN JUANICO BR) K0883+000-KO833+600; KO886+210-KO886+719; KO886+735-KO886+846; KO886+862-KO887+200; KO887+850-KO887+800; KO888+950-KO889+480; KO890+460-KO890+600; KO890+710-KO891+419...,KO893+230-KO894+100 | Region VIII | Samar 2nd DEO | On-Going | ₱147.9M | 100% | High risk63 | Flagged0.025 |
| 25I00059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0755+085 - K0755+170, K0755+170 - K0756+000, K | Region VIII | Region VIII | On-Going | ₱46.6M | 41% | High risk96 | Flagged0.024 |
| 21IK0056CONCRETING OF BRGY. SAN ANDRES TO BRGY. INARUMBACAN FMR, VILLAREAL, SAMAR, STA. 0+000.000 - STA. 0+700.00 | Region VIII | Samar 2nd DEO | On-Going | ₱16.1M | 64% | Medium risk51 | Flagged0.024 |
| 24IK0094CONSTRUCTION OF CONCRTE ROAD, BRGY. LAGUNDI TO BRGY. SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.4M | 59% | High risk83 | Flagged0.018 |
| 25IJ0060OO1: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED ROADS - TERTIARY ROADS CALBAYOG DIVERSION RD. K0739+000 - K0740+000 | Region VIII | Samar 1st DEO | On-Going | ₱34.4M | 10% | High risk92 | Flagged0.017 |
| 25IK0047CSSP- SIPAG- INTERJURISDICTIONALROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION) CONST. OF ROAD, BRGY. BAGACAY TO BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 75% | High risk96 | Flagged0.014 |
| 24IK0068CONST. OF ROAD, BARANGAY ASTORGA TO BARANGAY SAN VICENTE, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 63% | High risk80 | Flagged0.012 |
| 21I00056CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO - LAYO - MAGDAWAT - PELAON OF PINABACDAO TO MABINI IN BASEY CONNECTING ...SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱443.9M | 95% | High risk66 | Flagged0.010 |
| 22IK0037CONST. OF ROAD, BRGY. LOKILOKON-PARANAS-LAWAAN-CONCEPTION-CANLIGUES-PACO-CALAPI-HINICA-AN-CARANAS-BABACLAYON-HIDUROMA-SAN JOSE DE BUAN-CANAPOTE-SAN NICOLAS-SITIO SALVACION-AGUINAYAN-GUSA, SAMAR, BRGY. CARANAS, MOTIONG, SAMAR, BRGY. BABACLAYON, HIDUROMA, H | Region VIII | Samar 2nd DEO | On-Going | ₱86M | 92% | Medium risk59 | Flagged0.009 |
| 24IK0069CONST. OF ROAD, POBLACION TO BARANGAY SOONG, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 77% | High risk80 | Flagged0.006 |
| 24IJ0078CSSP: CONSTRUCTION OF ROAD, BRGY. DEIT - BRGY. MAHAYAG, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59M | 86% | High risk81 | Flagged0.006 |
| 25IJ0002CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.9M | 94% | High risk96 | Flagged0.004 |
| 23IK0082CONCRETING OF BRGY. CONCORD FMR, BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱12.8M | 100% | Medium risk44 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23IJ0036LOCAL PROGRAM (LP): CONSTRUCTION OF DPWH-SAMAR FIRST DISTRICT ENGINEERING OFFICE BUILDING, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱57.7M | 100% | High risk61 | —-0.043 |
| 27 | 23IK0053CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BASEY - MAYDOLONG ROAD, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱106.1M | 100% | High risk61 | —-0.036 |
| 28 | 23IJ0059CSSP: CONSTRUCTION OF BARANGAY NABANG - GADGARAN ROAD, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱95.8M | 100% | Medium risk60 | —-0.078 |
| 29 | 17IK0019ROAD WIDENING - DAANG MAHARLIKA (SM) (SAN ISIDRO-SAN JUANICO BR) KO878+190-KO879+180;KO879+203-KO879+265;KO879+470-KO879+680;KO880+370-KO880+515;KO880+534-KO880+726;KO881+880-KO882+100 | Region VIII | Samar 2nd DEO | Completed | ₱55M | 100% | Medium risk59 | —-0.054 |
| 30 | 22IK0037CONST. OF ROAD, BRGY. LOKILOKON-PARANAS-LAWAAN-CONCEPTION-CANLIGUES-PACO-CALAPI-HINICA-AN-CARANAS-BABACLAYON-HIDUROMA-SAN JOSE DE BUAN-CANAPOTE-SAN NICOLAS-SITIO SALVACION-AGUINAYAN-GUSA, SAMAR, BRGY. CARANAS, MOTIONG, SAMAR, BRGY. BABACLAYON, HIDUROMA, H | Region VIII | Samar 2nd DEO | On-Going | ₱86M | 92% | Medium risk59 | Flagged0.009 |
| 31 | 25IJ0047CSSP: CONSTRUCTION OF ROAD, BARANGAY NALIHUGAN - BARANGAY RAWIS, GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱49.2M | 9% | Medium risk59 | —-0.003 |
| 32 | 17IK0018OFF CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONST. OF SAN JUANICO - BASEY - SOHOTON ROAD, KO900+659 - KO904+687 - KO907+160 | Region VIII | Samar 2nd DEO | Completed | ₱58.4M | 100% | Medium risk59 | —-0.053 |
| 33 | 22IK0035CONSTRUCTION OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO-LAYO-MAGDAWAT-PELAON OF PINABACDAO TO MABINI, BASEY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱86.4M | 66% | Medium risk57 | —-0.019 |
| 34 | 23IK0046PREVENTIVE MAINT. - PRIMARY ROADS ALONG DAANG MAHARLIKA (SM) (SAN ISIDRO-SN JUANICO BR), K0819+200-K082+800 | Region VIII | Samar 2nd DEO | On-Going | ₱58.4M | 99% | Medium risk57 | —-0.043 |
| 35 | 23IK0049PREVENTIVE MAINT. - PRIMARY ROADS, SAN SEBASTIAN TO CALBIGA, SAMAR ALONG DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BR)-K0842+660-K0843+000, K0843+356-K0847+896 | Region VIII | Samar 2nd DEO | On-Going | ₱72M | 100% | Medium risk56 | —-0.042 |
| 36 | 24IK0058CONSTRUCTION OF MULTI-PURPOSE BUILDING, JIABONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.6M | 98% | Medium risk56 | —-0.051 |
| 37 | 23IK0033NETWORK DEVELOPMENT - OFF CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS, BRGY. MERCEDES, CATBALOGAN CITY | Region VIII | Samar 2nd DEO | On-Going | ₱62.1M | 100% | Medium risk56 | —-0.042 |
| 38 | 22IK0072CONSTRUCTION OF ROAD, CANMUCAT - TOMABE - INASUDLAN, VILLAREAL STA. 0+660 - STA. 2+500, BRGY. CANMUCAT - TOMABE - INASUDLAN, VILLAREAL, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱67.5M | 100% | Medium risk56 | —-0.091 |
| 39 | 25IK0030CSSP- SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS FACILITIES- CONST. OF ACCESS ROAD LEADING TO CATBALOGAN NEW DEEP SEA PORT, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱64.5M | 0% | Medium risk56 | —-0.025 |
| 40 | 24IK0098RECONSTRUCTION TO CONCRETE PAVEMENT - CONST. OF NEW BURI BRIDGE INCLUDING APPROACH ALONG BURI ACCESS ROAD, CATBALOGAN CITY SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱58.1M | 62% | Medium risk56 | —-0.043 |
| 41 | 22IK0064CONSTRUCTION OF LAGUNDI-SAN ANDRES ROAD, STA. 0+000 - STA. 3+600, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱67.2M | 44% | Medium risk56 | —-0.011 |
| 42 | 24IK0091REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - SECONDARY ROADS, BASEY - MARABUT - PINAMITINAN RD., K0915+958 - K0916+020, K0916+580 - K0916+651, K0917+039 - K0917+055, K0917+384 - K0917+412, K0917+503 - K0917+512, K0917+538 - K0917+6 | Region VIII | Samar 2nd DEO | On-Going | ₱53.1M | 93% | Medium risk55 | —-0.053 |
| 43 | 24IK0028ASSET PRESERVATION- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS- WRIGHT-TAFT-BORONGAN ROAD- K0852+100-K0852+121, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱48.3M | 100% | Medium risk54 | —-0.049 |
| 44 | 24IK0022ASSET PRESERVATION PROGRAM- REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, BASEY-MARABUT-PINAMITINAN RD- K0948+000-K0948+210, K0949+000-K0950+000, K0951+000-K0951+112, MARABUT, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱54.4M | 100% | Medium risk54 | —-0.048 |
| 45 | 23IK0039CONST. OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO - LAYO - MAGDAWAT - PELAON OF PINABACDAO TO MABINI, BASEY, SAMAR, STA. 0+000.00 - STA. 1+025.50 | Region VIII | Samar 2nd DEO | Completed | ₱47.8M | 100% | Medium risk54 | —-0.094 |
| 46 | 23IJ0042CSSP: (RE-ADVERTISED) CONSTRUCTION OF ROAD, BARANGAY PUHAGAN - LIBERTAD - KABUGAW - MATALUD, SAN JORGE, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱48.5M | 100% | Medium risk54 | —-0.095 |
| 47 | 24IK0027CONSTRUCTION OF ROAD, BARANGAY LAGUNDI TO BARANGAY PANGDAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.3M | 79% | Medium risk54 | —-0.045 |
| 48 | 24IK0081CONSTRUCTION OF CONCRETE ROAD-BURI CIRCUMFERENTIAL ROAD AT BURI ISLAND, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱49M | 52% | Medium risk53 | —-0.039 |
| 49 | 24IJ0046CSSP: CONSTRUCTION OF ROAD, BARANGAY DAP-DAP - BARANGAY TALINGA - BARANGAY LAHONG - BARANGAY TARANGNAN, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱49.5M | 100% | Medium risk53 | —-0.056 |
| 50 | 24IJ0066CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TAGAPUL-AN, SAMAR (PHASE 4) | Region VIII | Samar 1st DEO | On-Going | ₱49.4M | 90% | Medium risk53 | —-0.055 |