Contractor dossier
138 projects on file, including joint ventures this contractor is part of.
Total projects
138
Total budget
₱5.4B
Average progress
89.1%
Completion rate
42.8%
Below 70%
Average risk score
56.3
Medium risk on average, out of 100
Flagged as unusual
18
13.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 138 | ₱5.4B | 56.3 | 18 | 89.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 80 | ₱3.6B | 52.3 | 5 | 89.8% |
| Buildings and Facilities | 21 | ₱223.9M | 51.1 | 0 | 97.0% |
| Bridges | 10 | ₱199.3M | 49.0 | 0 | 99.0% |
| OTHER | 9 | ₱677.1M | 84.2 | 8 | 66.7% |
| Flood Control and Drainage | 9 | ₱291.6M | 48.5 | 0 | 100.0% |
| GAA 2025 SSP | 5 | ₱183M | 95.6 | 4 | 65.5% |
| GAA 2025 OO-1 | 2 | ₱57.9M | 91.9 | 1 | 50.3% |
| GAA 2025 OO-2 | 2 | ₱76M | 86.2 | 0 | 81.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0755+085 - K0755+170, K0755+170 - K0756+000, K | Region VIII | Region VIII | On-Going | ₱46.6M | 41% | High risk96 | Flagged0.024 |
| 25IK0047CSSP- SIPAG- INTERJURISDICTIONALROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION) CONST. OF ROAD, BRGY. BAGACAY TO BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 75% | High risk96 | Flagged0.014 |
| 25IK0052CSSP-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ACCESS ROAD, POB. 1 TO BRGY, BOTAERA, ZUMARRAGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.3M | 18% | High risk96 | Flagged0.027 |
| 25IJ0002CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.9M | 94% | High risk96 | Flagged0.004 |
| 25IJ0008CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TAGAPUL-AN, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.8M | 100% | High risk96 | —-0.000 |
| 25IJ0060OO1: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED ROADS - TERTIARY ROADS CALBAYOG DIVERSION RD. K0739+000 - K0740+000 | Region VIII | Samar 1st DEO | On-Going | ₱34.4M | 10% | High risk92 | Flagged0.017 |
| 24IJ0102(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98M | 62% | High risk92 | Flagged0.068 |
| 25IJ0026OO1: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CALBAYOG DIVERSION RD. - K0733+030 - K0733+347, K0738+000 - K0738+505, K0738+700 - K0739+000 | Region VIII | Samar 1st DEO | On-Going | ₱23.5M | 90% | High risk92 | —-0.004 |
| 25IK0033CONCRETING OF BRGY. ALBALATE TO BRGY. CAGUTIAN TO BRGY. CAGUSIPAN FMR, BRGY. ALBALATE, BRGY. CAGUTIAN, BRGY. CAGUSIPAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 34% | High risk89 | Flagged0.059 |
| 25IK0034CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 64% | High risk89 | Flagged0.051 |
| 25IJ0017OO2: CONTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GANDARA RIVER, PHASE II, BARANGAY PIZARRO, GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱42.8M | 82% | High risk87 | —-0.014 |
| 25IK0037CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DOLONGAN, BASEY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱33.2M | 80% | High risk85 | —-0.012 |
| 24IK0079CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BASEY-MAYDOLONG ROAD, BASEY SECTION, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱270.5M | 56% | High risk85 | Flagged0.042 |
| 24IK0094CONSTRUCTION OF CONCRTE ROAD, BRGY. LAGUNDI TO BRGY. SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.4M | 59% | High risk83 | Flagged0.018 |
| 24IJ0078CSSP: CONSTRUCTION OF ROAD, BRGY. DEIT - BRGY. MAHAYAG, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59M | 86% | High risk81 | Flagged0.006 |
| 24IK0069CONST. OF ROAD, POBLACION TO BARANGAY SOONG, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 77% | High risk80 | Flagged0.006 |
| 24IK0068CONST. OF ROAD, BARANGAY ASTORGA TO BARANGAY SAN VICENTE, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 63% | High risk80 | Flagged0.012 |
| 17IK0001CLUSTER I - PREVENTIVE MAINT. WRIGHT OLD ROUTE, KO826+797-KO826+182; SAN JUANICO-BASEY-SOHOTON ROAD, KO896+290-KO900+500 & KO900+850-KO907+450; SAN JUANICO-BASEY-SOHOTON ROAD, KO909+278-KO909+422 | Region VIII | Samar 2nd DEO | Completed | ₱27.9M | 100% | High risk78 | —-0.035 |
| 21I00056CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO - LAYO - MAGDAWAT - PELAON OF PINABACDAO TO MABINI IN BASEY CONNECTING ...SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱443.9M | 95% | High risk66 | Flagged0.010 |
| 22IK0082CONST. OF MULTI-PURPOSE BUILDING, BRGY. ROÑO, MARABUT, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱4.8M | 100% | High risk66 | —-0.073 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IJ0102(RE-ADVERTISED) CONSTRUCTION OF BRGY. MADUROTO BRIDGE (ALONG MATUGUINAO - LAS NAVAS ROAD) PHASE IV - BRGY. MADUROTO, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱98M | 62% | High risk92 | Flagged0.068 |
| 25IK0033CONCRETING OF BRGY. ALBALATE TO BRGY. CAGUTIAN TO BRGY. CAGUSIPAN FMR, BRGY. ALBALATE, BRGY. CAGUTIAN, BRGY. CAGUSIPAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 34% | High risk89 | Flagged0.059 |
| 25IK0034CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱14.9M | 64% | High risk89 | Flagged0.051 |
| 24IK0079CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BASEY-MAYDOLONG ROAD, BASEY SECTION, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱270.5M | 56% | High risk85 | Flagged0.042 |
| 25IK0052CSSP-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ACCESS ROAD, POB. 1 TO BRGY, BOTAERA, ZUMARRAGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.3M | 18% | High risk96 | Flagged0.027 |
| 17IK0020ROAD WIDENING - DAANG MAHARLIKA (SM) (SAN ISIDRO-SAN JUANICO BR) K0883+000-KO833+600; KO886+210-KO886+719; KO886+735-KO886+846; KO886+862-KO887+200; KO887+850-KO887+800; KO888+950-KO889+480; KO890+460-KO890+600; KO890+710-KO891+419...,KO893+230-KO894+100 | Region VIII | Samar 2nd DEO | On-Going | ₱147.9M | 100% | High risk63 | Flagged0.025 |
| 25I00059SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0755+085 - K0755+170, K0755+170 - K0756+000, K | Region VIII | Region VIII | On-Going | ₱46.6M | 41% | High risk96 | Flagged0.024 |
| 21IK0056CONCRETING OF BRGY. SAN ANDRES TO BRGY. INARUMBACAN FMR, VILLAREAL, SAMAR, STA. 0+000.000 - STA. 0+700.00 | Region VIII | Samar 2nd DEO | On-Going | ₱16.1M | 64% | Medium risk51 | Flagged0.024 |
| 24IK0094CONSTRUCTION OF CONCRTE ROAD, BRGY. LAGUNDI TO BRGY. SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.4M | 59% | High risk83 | Flagged0.018 |
| 25IJ0060OO1: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED ROADS - TERTIARY ROADS CALBAYOG DIVERSION RD. K0739+000 - K0740+000 | Region VIII | Samar 1st DEO | On-Going | ₱34.4M | 10% | High risk92 | Flagged0.017 |
| 25IK0047CSSP- SIPAG- INTERJURISDICTIONALROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION) CONST. OF ROAD, BRGY. BAGACAY TO BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 75% | High risk96 | Flagged0.014 |
| 24IK0068CONST. OF ROAD, BARANGAY ASTORGA TO BARANGAY SAN VICENTE, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 63% | High risk80 | Flagged0.012 |
| 21I00056CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ACCESS ROAD FROM LITERON - ANTOL IN CALBIGA TO CANLOBO - LAYO - MAGDAWAT - PELAON OF PINABACDAO TO MABINI IN BASEY CONNECTING ...SAMAR 2ND | Region VIII | Region VIII | On-Going | ₱443.9M | 95% | High risk66 | Flagged0.010 |
| 22IK0037CONST. OF ROAD, BRGY. LOKILOKON-PARANAS-LAWAAN-CONCEPTION-CANLIGUES-PACO-CALAPI-HINICA-AN-CARANAS-BABACLAYON-HIDUROMA-SAN JOSE DE BUAN-CANAPOTE-SAN NICOLAS-SITIO SALVACION-AGUINAYAN-GUSA, SAMAR, BRGY. CARANAS, MOTIONG, SAMAR, BRGY. BABACLAYON, HIDUROMA, H | Region VIII | Samar 2nd DEO | On-Going | ₱86M | 92% | Medium risk59 | Flagged0.009 |
| 24IK0069CONST. OF ROAD, POBLACION TO BARANGAY SOONG, STA. 0+000.00-STA. 1+965.00, DARAM, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱47.7M | 77% | High risk80 | Flagged0.006 |
| 24IJ0078CSSP: CONSTRUCTION OF ROAD, BRGY. DEIT - BRGY. MAHAYAG, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59M | 86% | High risk81 | Flagged0.006 |
| 25IJ0002CSSP: CONSTRUCTION OF CIRCUMFERENTIAL ROAD, STO. NIÑO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱38.9M | 94% | High risk96 | Flagged0.004 |
| 23IK0082CONCRETING OF BRGY. CONCORD FMR, BRGY. CONCORD, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱12.8M | 100% | Medium risk44 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 23IK0057CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, BARANGAY GUINSORONGAN, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱19.6M | 100% | Medium risk49 | —-0.046 |
| 102 | 23IK0056CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), BRGY. SOCORRO - GUINSORONGAN - BUNU-ANAN - BRGY. IBOL CIRCUMFERENTIAL ROAD, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱19.6M | 100% | Medium risk49 | —-0.095 |
| 103 | 22IK0011REHAB./RECON./UPGRADING OF DAMAGED PAVED ROADS - DOLONGAN - BASEY ROAD, K0890+523 - K0891+000, BRGY. DOLONGAN, BASEY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱11.4M | 100% | Medium risk49 | —-0.095 |
| 104 | 24IK0031CONSTRUCTION OF ROAD, BASEY NATIONAL HIGH SCHOOL, BARANGAY BUSCADA, BASEY, SAMAR, STA. 0+000.00- STA. 0+038.00, STA. 0+055.00-STA. 0+253.00, BASEY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱5.9M | 100% | Medium risk49 | —-0.054 |
| 105 | 23IK0092CONST. OF STANDARD 1- STOREY 3 CLASSROOM SCHOOL BUILDING, SAN SEBASTIAN CES, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱6.6M | 99% | Medium risk49 | —-0.009 |
| 106 | 23IK0020CONSTRUCTION OF ROAD, BARANGAY BERI - BARANGAY BULUAN, STA. 0+841 - STA. 1+191.50, BRGY. BERI, CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱9.6M | 100% | Medium risk49 | —-0.044 |
| 107 | 24IK0029NETWORK DEVELOPMENT- ROAD WIDENING- TERTIARY ROADS- HINABANGAN DIVERSION RD- K0837+(-075)-K0837+(-010), K0837+120-K0837+244 | Region VIII | Samar 2nd DEO | Completed | ₱6.4M | 100% | Medium risk49 | —-0.093 |
| 108 | 22IK0080CONST. OF ROAD, BRGY. SOCORRO TO BRGY. GUINSORONGAN, STA. 0+000 - STA. 0+280, BRGY. SOCORRO TO BRGY. GUINSORONGAN, CATBALOGAN CITY | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.095 |
| 109 | 23IK0022BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - CARBON BRIDGES II (B00443SM) ALONG WRIGHT - TAFT - BORONGAN ROAD, BRGY. FATIMA, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.059 |
| 110 | 23IK0023BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - TIGA BRIDGE (B00443SM) ALONG WRIGHT - TAFT - BORONGAN ROAD, BRGY. BAGACAY, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.059 |
| 111 | 23IK0024BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - PISAK BRIDGE (B00444SM) ALONG WRIGHT - TAFT - BORONGAN ROAD, BRGY. FATIMA, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.059 |
| 112 | 23IK0032BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES CABUGAO BR. (B00385SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.), CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.060 |
| 113 | 23IK0031BRIDGE PROGRAM - RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, POLANGI BR. (B00386SM) ALONG DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR.), CALBIGA, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.060 |
| 114 | 22IK0047BRGY. SOCORRO - GUINSORONGAN - BUNU-ANAN - BRGY. IBOL CIRCUMFERENTIAL ROAD, BRGY. SOCORRO-GUINSORONGAN-BUNU-ANAN-BRGY. IBOL, CATBALOGAN CITY, STA. 3+580 - STA. 3+690 | Region VIII | Samar 2nd DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.095 |
| 115 | 23IK0060CONSTRUCTION OF ROAD LEADING TO BANQUIL PORT, VILLAREAL, SAMAR, STA. 0+927.00 - STA. 1+260.50 | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.095 |
| 116 | 22IK0069REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSED AND LANDSLIDE, BASEY - MARABUT - PINAMITINAN ROAD, K0922+820 - K0922+880, BRGY. LEGASPI, MARABUT, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.095 |
| 117 | 22IK0061CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ANDRES, VILLAREAL, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱4.8M | 99% | Medium risk48 | —-0.040 |
| 118 | 24IJ0060CSSP: CONSTRUCTION OF ROAD, BRGY. LIMARAYON TO BRGY. KILO-KILI, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱39.6M | 100% | Medium risk48 | —-0.094 |
| 119 | 23IK0095CONST. OF MODIFIED DESIGN WITH PARAPET 1- STOREY 3- CL SCHOOL BLDG., BONTOD ES, SAN SEBASTIAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱8.8M | 100% | Medium risk48 | —-0.054 |
| 120 | 23IK0085CONST. OF MODIFIED DESIGN W/ PARAPET 1-STOREY 2- CL SB, TATABUNAN IS, TALALORA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱6.5M | 100% | Medium risk48 | —-0.011 |
| 121 | 24IJ0057CSSP: CONSTRUCTION OF ACCESS ROAD, STA. MARGARITA SPORTS COMPLEX, STA. MARGARITA, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.095 |
| 122 | 24IJ0032OO1: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS, CALBAYOG - CATARMAN RD. K0797+043 - K0797+070, K0797+810 - K0797+882 | Region VIII | Samar 1st DEO | Completed | ₱25.6M | 100% | Medium risk48 | —-0.094 |
| 123 | 23IJ0076CSSP: CONSTRUCTION OF THE GANDARA - MATUGINAO - LAS NAVAS ROAD, GANDARA, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱19.7M | 100% | Medium risk47 | —-0.094 |
| 124 | 22IK0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUCALAN BRIDGE ALONG DAANG MAHARLIKA, HINABANGAN, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱19.6M | 100% | Medium risk47 | —-0.079 |
| 125 | 24IK0025ACCESS ROAD FROM SITIO WESPAL, BRGY. GUIRANG TO BRGY. SAN FERNANDO LEADING TO SOHOTON CAVE AND BALANTAK FALLS, BRGY. SAN FERNANDO (NOUVELAS ORIENTAL), BASEY, SAMAR- STA. 0+667-STA. 0+867.00 | Region VIII | Samar 2nd DEO | On-Going | ₱4.8M | 100% | Medium risk47 | —-0.051 |