Contractor dossier
297 projects on file, including joint ventures this contractor is part of.
Total projects
297
Total budget
₱38.4B
Average progress
90.0%
Completion rate
65.7%
Below 70%
Average risk score
66.2
High risk on average, out of 100
Flagged as unusual
71
23.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 296 | ₱38.3B | 66.2 | 71 | 90.0% |
| Region IX | 1 | ₱140M | 74.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 151 | ₱18.9B | 58.5 | 8 | 93.2% |
| Flood Control and Drainage | 61 | ₱6.7B | 60.0 | 4 | 92.8% |
| OTHER | 49 | ₱8.3B | 83.2 | 33 | 84.9% |
| GAA 2025 OO-1 | 14 | ₱2B | 95.1 | 10 | 82.4% |
| GAA 2025 SSP | 10 | ₱1.3B | 96.2 | 10 | 78.9% |
| GAA 2025 OO-2 | 6 | ₱1.1B | 93.5 | 6 | 50.1% |
| Bridges | 3 | ₱62.8M | 48.0 | 0 | 100.0% |
| Water Provision and Storage | 3 | ₱7.4M | 34.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IL0063CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, LIMASAWA CIR | Region VIII | Southern Leyte 1st DEO | On-Going | ₱144.8M | 52% | High risk96 | Flagged0.035 |
| 25IF0011CONSTRUCTION OF BURAUEN-ALBUERA ROAD, STA. 11+700 - STA. 11+810, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱144.6M | 89% | High risk96 | Flagged0.025 |
| 25IF0017CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG JARO - RUBAS - ORMOC RAOD (ORMOC CITY SIDE), STA. 9+180 - STA. 9+230, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱144.6M | 93% | High risk96 | Flagged0.024 |
| 25IF0015CONSTRUCTION OF BURAUEN-ALBUERA ROAD, STA. 10+480 - STA. 10+580, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱144.6M | 90% | High risk96 | Flagged0.024 |
| 25IF0018CONSTRUCTION OF BURAUEN-ALBUERA ROAD, STA. 10+700 - STA. 10+790, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱144.6M | 91% | High risk96 | Flagged0.024 |
| 25IF0007CONSTRUCTION OF BURAUEN-ALBUERA ROAD, STA. 10+580 - STA. 10+700, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱144.6M | 90% | High risk96 | Flagged0.024 |
| 25IL0061CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, LIMASAWA CIR | Region VIII | Southern Leyte 1st DEO | On-Going | ₱96.4M | 75% | High risk96 | Flagged0.024 |
| 25IL0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, LIMASAWA CIR | Region VIII | Southern Leyte 1st DEO | On-Going | ₱96.4M | 75% | High risk96 | Flagged0.024 |
| 25I00024ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0691+000 - K0691+150 | Region VIII | Region VIII | On-Going | ₱192.9M | 76% | High risk96 | Flagged0.023 |
| 25I00127ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL ROADS - BILIRAN CIRCUMFERENTIAL RD. - K1036+657 - K1036+778, K1036+885 - K1036+951 | Region VIII | Region VIII | On-Going | ₱144.6M | 75% | High risk96 | Flagged0.014 |
| 25I00139SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMALBAGAN CREEK, BARANGAY TELEGRAFO, TOLOSA, LEYTE | Region VIII | Region VIII | On-Going | ₱163.9M | 61% | High risk95 | Flagged0.034 |
| 25I00128ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD. - K1071+895 - K1072+180 | Region VIII | Region VIII | On-Going | ₱144.6M | 78% | High risk95 | Flagged0.015 |
| 25I00033ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0864+261 - K0864+552 | Region VIII | Region VIII | On-Going | ₱193M | 71% | High risk95 | Flagged0.027 |
| 25I00034ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - SN POLICARPO - ARTECHE - LAPINIG RD - K0863+750 - K0864+000 | Region VIII | Region VIII | On-Going | ₱192.9M | 88% | High risk95 | Flagged0.024 |
| 25I00038ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - WRIGHT - TAFT - BORONGAN RD - K0881+985 - K0882+170 (LS) | Region VIII | Region VIII | On-Going | ₱144.6M | 65% | High risk95 | Flagged0.021 |
| 25I00030NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN CITY BY-PASS ROAD EXTENSION, PACKAGE P, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱337.6M | 80% | High risk95 | Flagged0.031 |
| 25I00147SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES CONSTRUCTION OF DRAINAGE AND FLOOD CONTROL STRUCTURE ALONG GUINARONA RIVER, BARANGAY TELEGRAFO, TOLOSA, LEYTE | Region VIII | Region VIII | On-Going | ₱62.7M | 72% | High risk95 | Flagged0.016 |
| 25IA0118REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - NAVAL-CAIBIRAN CROSS COUNTRY RD., K1039+660 - K1039+710 | Region VIII | Biliran DEO | On-Going | ₱48.9M | 85% | High risk95 | —-0.005 |
| 25IA0119REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - NAVAL-CAIBIRAN CROSS COUNTRY RD., K1039+710 - K1039+750 | Region VIII | Biliran DEO | On-Going | ₱48.9M | 90% | High risk95 | —-0.007 |
| 25IA0120REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - NAVAL-CAIBIRAN CROSS COUNTRY RD., K1039+750 - K1039+780 | Region VIII | Biliran DEO | On-Going | ₱49M | 100% | High risk95 | —-0.011 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23I00224SIPAG - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - ROAD OPENING AND CONCRETING OF BURAUEN SOUTHEAST SEMI-CIRCUMFERENTIAL ROAD TRAVERSING BRGY. POBLACION | Region VIII | Region VIII | On-Going | ₱144.7M | 25% | High risk91 | Flagged0.088 |
| 24I00399CLUSTER 14: 1.) ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG ROAD - K0811+951 - K0812+085; 2.) ASSET PRESERVATION - REHABILITATION/ RECONS | Region VIII | Region VIII | On-Going | ₱192.9M | 35% | High risk92 | Flagged0.085 |
| 23I00216CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM) INCLUDING ROAD RIGHT OF WAY, PHASE 1-B, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱134.8M | 92% | High risk92 | Flagged0.072 |
| 24IF0126CONSTRUCTION OF BURAUEN - ALBUERA ROAD, STA. 9+795 - STA. 9+850, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96.4M | 100% | High risk92 | Flagged0.055 |
| 24IF0127CONSTRUCTION OF BURAUEN - ALBUERA ROAD, STA. 9+850 - STA. 9+920, ALBUERA, LEYTE | Region VIII | Leyte 4th DEO | On-Going | ₱96.4M | 100% | High risk92 | Flagged0.055 |
| 24I00017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM), PHASE 2, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱236.1M | 31% | High risk84 | Flagged0.049 |
| 23I00215CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM) INCLUDING ROAD RIGHT OF WAY, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱91.4M | 40% | High risk65 | Flagged0.046 |
| 24I00416BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF BENJAMIN ROMUALDEZ INTERNATIONAL CONVENTION CENTER WITH SITE DEVELOPMENT PHASE II, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱247.5M | 17% | High risk84 | Flagged0.044 |
| 24I00100NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN CITY BYPASS ROAD EXTENSION, (PACKAGE J), TACLOBAN CITY LD | Region VIII | Region VIII | On-Going | ₱356.2M | 71% | High risk84 | Flagged0.044 |
| 24I00197CLUSTER 9: 1. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - ALPINIG ROAD - K0809+676 - K0809+780; 2. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - | Region VIII | Region VIII | On-Going | ₱385.9M | 86% | High risk83 | Flagged0.037 |
| 24I00027CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TARUSAN RIVER, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱147.5M | 37% | High risk84 | Flagged0.037 |
| 24I00156CLUSTER 6: 1. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - SAN RICARDO - BILATAN RD - K1101+595 - K1101+625 AND OTHER SIX (6) LOCATIONS, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱331.6M | 87% | High risk85 | Flagged0.036 |
| 25IL0063CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, LIMASAWA CIR | Region VIII | Southern Leyte 1st DEO | On-Going | ₱144.8M | 52% | High risk96 | Flagged0.035 |
| 24I00003SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE A-1, BARANGAY CAMPETIC, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱289.3M | 98% | High risk84 | Flagged0.035 |
| 25I00139SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMALBAGAN CREEK, BARANGAY TELEGRAFO, TOLOSA, LEYTE | Region VIII | Region VIII | On-Going | ₱163.9M | 61% | High risk95 | Flagged0.034 |
| 24I00158CLUSTER 7: NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - SAN RICARDO - BILATAN RD - K1101+830 - K1101+860; AND SIX (6) OTHER LOCATIONS | Region VIII | Region VIII | On-Going | ₱331.6M | 93% | High risk85 | Flagged0.034 |
| 24I00207CLUSTER 4: 1. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - WRIGHT - TAFT - BORONGAN RD - K0887+800 - K0887+890 (RS); 2. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - WRIGHT - TAFT - BORONGAN RD - K0887+890 | Region VIII | Region VIII | On-Going | ₱293.8M | 94% | High risk85 | Flagged0.032 |
| 23IM0131CONSTRUCTION OF CROSSING SAN ROQUE - SITIO KULAPNITAN FMR, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱74.6M | 21% | High risk60 | Flagged0.032 |
| 24I00139SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. NALIBUNAN, BARANGAY LOYONSAWANG, AND BARANGAY BUNTAY, ABUYOG, LEYTE | Region VIII | Region VIII | On-Going | ₱192.9M | 79% | High risk84 | Flagged0.032 |
| 25I00030NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN CITY BY-PASS ROAD EXTENSION, PACKAGE P, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱337.6M | 80% | High risk95 | Flagged0.031 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 19I00116CLUSTER 1: 1. CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A). SITIO BAGANG, BRGY. CABACUNGAN, DULAG, LEYTE 2. CONSTRUCTION (EXTENSION) OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE A), BRGY. FATIMA, DULAG, LEYTE | Region VIII | Region VIII | Completed | ₱233.5M | 100% | High risk83 | —-0.006 |
| 52 | 23I00115SIPAG - INTERJURISDICTIONAL ROADS AND/OR ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS - CONSTRUCTION OF TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, BARANGAY 89, TACLOBAN CITY | Region VIII | Region VIII | Completed | ₱96.4M | 100% | High risk83 | —-0.020 |
| 53 | 18I00045ROAD WIDENING - CATARMAN DIVERSION ROAD 2, KO744+(-198) - KO745+710; KO745+942 - KO747+187, CATARMAN, NORTHERN SAMAR 1ST LD | Region VIII | Region VIII | Completed | ₱95.6M | 100% | High risk83 | —-0.025 |
| 54 | 24I00197CLUSTER 9: 1. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - ALPINIG ROAD - K0809+676 - K0809+780; 2. NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - | Region VIII | Region VIII | On-Going | ₱385.9M | 86% | High risk83 | Flagged0.037 |
| 55 | 24I00177NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG ROAD - K0810+751 - K0810+840 | Region VIII | Region VIII | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.018 |
| 56 | 24I00228NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG ROAD - K0812+312 - K812+392, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Region VIII | On-Going | ₱144.7M | 97% | High risk83 | Flagged0.015 |
| 57 | 24I00217NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - PANGPANG - PALAPAG - MAPANAS - GAMAY - LAPINIG ROAD - K0810+840 - K0810+948 | Region VIII | Region VIII | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.014 |
| 58 | 24I00181NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE A-2, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱115.7M | 92% | High risk83 | Flagged0.016 |
| 59 | 23I00120NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN - PALO DIVERSION ROAD INCLUDING DRAINAGE SYSTEM, PACKAGE A, BRGY. CAMPETIC, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱124.7M | 95% | High risk83 | Flagged0.026 |
| 60 | 24I00229NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0703+770 - K0703+840, K0704+960 - K0705+010, SAMAR 1ST DISTRICT | Region VIII | Region VIII | On-Going | ₱141.3M | 95% | High risk83 | Flagged0.016 |
| 61 | 24IC0068CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINAHAAN RIVER, BRGY. MALAGUICAY AND BRGY. BINONGTOAN, TANAUAN, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱144.7M | 100% | High risk83 | Flagged0.018 |
| 62 | 24I00193NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - LIBUNGAO - MATAG-OB - PALOMPON RD - K1008+640 - K1008+790, K1008+830 - K1008+880 | Region VIII | Region VIII | Completed | ₱144.6M | 100% | High risk83 | —-0.017 |
| 63 | 22I00061CONSTRUCTION (COMPLETION) OF STORM SURGE PROTECTION: BACKWATER DIKE AND EARLY WARNING STRUCTURE, PALO, LEYTE | Region VIII | Region VIII | On-Going | ₱97.5M | 91% | High risk82 | Flagged0.030 |
| 64 | 18I00053ROAD OPENING / CONCRETING OF SAN ISIDRO - LOPE DE VEGA ROAD, SAN ISIDRO, NORTHERN SAMAR | Region VIII | Region VIII | Completed | ₱144.5M | 100% | High risk82 | —-0.014 |
| 65 | 18I00001CONSTRUCTION OF BY-PASSES / DIVERSION ROADS, TACLOBAN CITY BY-PASS ROAD EXTENSION, INCLUDING ROW, LEYTE | Region VIII | Region VIII | Completed | ₱112.5M | 100% | High risk82 | —-0.007 |
| 66 | 20I00005CLUSTER I: 1. CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE B), SITIO BAGANG, BRGY. CABACUNGAN, DULAG, LEYTE; 2. CONSTRUCTION (EXTENSION) OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES (PACKAGE B), BRGY. FATIMA, DULAG, LEYTE | Region VIII | Region VIII | Completed | ₱155.9M | 100% | High risk82 | —-0.015 |
| 67 | 18I00034CONSTRUCTION OF MISSING LINKS / NEW ROADS, JARO - RUBAS - ORMOC ROAD (JARO SIDE), INCLUDING RROW, LEYTE, LEYTE 2ND LD | Region VIII | Region VIII | Completed | ₱133.6M | 100% | High risk82 | —-0.018 |
| 68 | 17I00076CONSTRUCTION OF BY-PASSES / DIVERSION ROADS, TACLOBAN CITY BY-PASS ROAD, LEYTE | Region VIII | Region VIII | Completed | ₱93.5M | 100% | High risk82 | —-0.015 |
| 69 | 24I00159NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - (S00001SM) K0680+(-697) - K680+000, K0680+529 - K0680+565, K0681+020 - K0681+022, K0684+435 - K0684+476, K0684+650 - K0684+750, K0685+070 - K0685+165, | Region VIII | Region VIII | On-Going | ₱189.5M | 80% | High risk82 | Flagged0.025 |
| 70 | 24I00384REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - TIGBAO - STA. FE - SAN MIGUEL ROAD - K0904+093 - K0905+000, K0907+250 - K0907+268, K0907+745 - K0907+775, K0907+940 - K0908+000 | Region VIII | Region VIII | On-Going | ₱90.2M | 42% | High risk81 | Flagged0.017 |
| 71 | 18I00002CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURES AND CHANNELIZATION, BATUG, DULAG, LEYTE | Region VIII | Region VIII | Completed | ₱144.7M | 100% | High risk81 | —-0.015 |
| 72 | 17I00015IMPROVEMENT / WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (LT), KO941+1488 - KO943+277; KO944+225 - KO945+212; KO946+460 - KO947+000; KO949+000 - KO949+290; KO954+448 - KO955+550, (S00083LT), LEYTE | Region VIII | Region VIII | Completed | ₱86.4M | 100% | High risk81 | —-0.025 |
| 73 | 21I00019NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - JARO - RUBAS - ORMOC ROAD (JARO SIDE), LEYTE, LEYTE 2ND LD | Region VIII | Region VIII | Completed | ₱83.2M | 100% | High risk81 | —-0.030 |
| 74 | 20I00041NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PALO WEST BYPASS ROAD, LEYTE, PALO, LEYTE | Region VIII | Region VIII | Completed | ₱78.2M | 100% | High risk81 | —-0.027 |
| 75 | 24I00221NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0703+705 - K0703+770 | Region VIII | Region VIII | On-Going | ₱91.3M | 0% | High risk80 | Flagged0.030 |