Contractor dossier
7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱116.2M
Average progress
89.8%
Completion rate
57.1%
Below 70%
Average risk score
55.3
Medium risk on average, out of 100
Flagged as unusual
1
14.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 7 | ₱116.2M | 55.3 | 1 | 89.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱66.1M | 45.0 | 0 | 98.4% |
| Buildings and Facilities | 2 | ₱24.3M | 52.4 | 0 | 86.3% |
| GAA 2025 SSP | 1 | ₱14.4M | 96.1 | 1 | 60.6% |
| Bridges | 1 | ₱11.4M | 51.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25AC0061CONSTRUCTION OF MULTI-PURPOSE BUILDING, KATIPUNAN ELEMENTRY SCHOOL, BARANGAY KATIPUNAN, SINAIT, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | On-Going | ₱14.4M | 61% | High risk96 | Flagged0.029 |
| 2 | 25AC0024CONSTRUCTION OF MULTI-PURPOSE BUILDING, SINAIT CENTRAL SCHOOL, BARANGAY RANG-AY, SINAIT, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | On-Going | ₱14.5M | 73% | Medium risk53 | —-0.034 |
| 3 | 24AC0057CONSRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CURTIN, MUNICIPALITY OF SINAIT, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱9.9M | 100% | Medium risk52 | —-0.081 |
| 4 | 17AC0042WIDENING OF SINAIT BRIDGE 1 ALONG MANILA NORTH ROAD | Region I | Ilocos Sur 1st DEO | Completed | ₱11.4M | 100% | Medium risk51 | —-0.024 |
| 5 | 18AC0052CONCRETING OF ACCESS ROAD LEADING TO STO. CRISTO SHRINE AND SINAIT PUBLIC BEACH, BRGY. TAPAO, SINAIT | Region I | Ilocos Sur 1st DEO | Completed | ₱32.5M | 100% | Medium risk46 | —-0.070 |
| 6 | 24AC0036CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS, MANILA NORTH RD - K0438+154 -K0439+641, SINAIT, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | On-Going | ₱19.2M | 95% | Medium risk45 | —-0.040 |
| 7 | 23AC0147CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS, MANILA NORTH - K0438+154 - K0439+000, SINAIT, ILOCOS SUR | Region I | Ilocos Sur 1st DEO | Completed | ₱14.4M | 100% | Medium risk44 | —-0.027 |