25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱147.6M
Average progress
100.0%
Completion rate
100.0%
Average risk score
34.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 25 | ₱147.6M | 34.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 14 | ₱83.1M | 35.1 | 0 | 100.0% |
| Buildings and Facilities | 10 | ₱59.7M | 28.8 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.8M | 83.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BB0092CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MABANGUC, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.8M | 100% | High risk84 | —-0.022 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25BB0092CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MABANGUC, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.8M | 100% | High risk84 | —-0.022 |
| 2 | 24BB0137CSSP- BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING BISAGU ELEMENTARY SCHOOL, BARANGAY BISAGU, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱9.9M | 100% | Medium risk50 | —-0.080 |
| 3 | 18BB0009LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES CONSTRUCTION OF CONCRETE ROAD, BRGY. MASIN, ALCALA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱5.7M | 100% | Medium risk45 | —-0.081 |
| 4 | 21BC0017CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-CABATACAN EAST BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONNECTING TO CACAO PLANTATION AND PROCESSING, CABATACAN EAST, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.082 |
| 5 | 18BB0199CONSTRUCTION AND COMPLETION OF 1-STOREY THREE (3)-CLASSROOM SCHOOL BUILDING WITH TOILET, PADDAYA ESTE ES AND PADDAYA WESTE ES, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱8.8M | 100% | Medium risk42 | —-0.037 |
| 6 | 18BB0187CONSTRUCTION AND COMPLETION OF TWO-STOREY 4-CL (SCIENCE LAB., ICT) SCHOOL BUILDING (9.5M X 23.00M), CABIRAOAN NATIONAL HIGH SCHOOL, GONZAGA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱12.2M | 100% | Medium risk41 | —-0.034 |
| 7 | 23BB0144CONCRETING OF BARANGAY NAVAGAN FMR, BRGY. NAVAGAN, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱19.9M | 100% | Medium risk41 | —-0.024 |
| 8 | 23BB0071CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY ZINARAG, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | Medium risk41 | —-0.080 |
| 9 | 20BB0069LOCAL PROGRAM CONST./ REPAIR/ REHAB./ IMPROVEM'T OF VARIOUS INFRASTRUCTURE INCL.-LOCAL ROADS-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONSTRUCTION OF CONCRETE ROAD-CONSTRUCTION OF ROAD AT BRGY. BANTAY-FUSINA, CAMALANIUGAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | Medium risk40 | —-0.081 |
| 10 | 23BB0077OO1: ENSURE SAFE & RELIABLE NAT'L RD SYSTEM - ASSET PRESERVATN - REHAB./ RECONST./UPGRADING OF DAMAGED PAVED RDS - SECONDARY RDS - RECONST. TO CONC. PAVEMENT- JCT. AYAGA (ABULUG) -BALLESTEROS RD - (S00891LZ) CHAINAGE 135 - CHAINAGE 570, APARRI,CAG | Region II | Cagayan 1st DEO | Completed | ₱8.2M | 100% | Medium risk40 | —-0.080 |
| 11 | 21BB0048CONVERGENCE AND SPECIAL SUPPORT PROG. - CONSTRUCTION/ IMPROV'T OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES-CONST. OF CONCRETE ROAD-ACCESS ROAD LEADING TO FISH LANDING & BAGOONG PROCESSING , SITIO NAMUYUCAN, SAN JOSE, GONZAGA,CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱9.4M | 100% | Medium risk40 | —-0.078 |
| 12 | 18BB0147CONSTRUCTION AND COMPLETION OF ONE-STOREY 3-CL (WITH TOILET) SCHOOL BUILDING, SAN VICENTE ES, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.7M | 100% | Medium risk40 | —-0.039 |
| 13 | 22BB0093CSSP - BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF BARANGAY ROAD AT BARANGAY SAN LORENZO, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.080 |
| 14 | 20BB0044CONVERGENCE&SPECIAL SUPPORT PROG-CONSTRUCTION/IMPROVT OF ACCESS RDS LEADING TO TRADES, INDUSTRIES&ECONOMICS ZONES-CONST OF CONC RD-ACCESS RD LEADING TO FISH LANDING& BAGOONG PROCESSING, SITIO NAMUYUCAN,SAN JOSE, GONZAGA,CAG, BRGY.SAN JOSE, GONZAGA,CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱7.6M | 100% | Medium risk39 | —-0.078 |
| 15 | 23BB0061CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS TO TRADES, INDUSTRIES AND ECONOMIC ZONES ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - (ROLL-IT) - CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD L | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | Medium risk38 | —-0.071 |
| 16 | 17BB0142CONSTRUCTION OF VARIOUS CLASSROOMS SCHOOL BUILDING WITH TOILET, SAN VICENTE ES, BAGGAO, CAGAYAN AND VALLEY COVE, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱10.3M | 100% | Medium risk37 | —-0.005 |
| 17 | 17BB0077CONSTRUCTION OF VARIOUS SCHOOL BUILDING WITH TOILET, BIRAO ELEMENTARY SCHOOL, BAGGAO, CAGAYAN; VALLEY COVE INTEGRATED SCHOOL, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱5.4M | 100% | Medium risk37 | —-0.001 |
| 18 | 18BB0031LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF CONCRETE ROAD, BRGY. CASICALLAN NORTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2M | 100% | Low risk22 | —-0.075 |
| 19 | 18BB0046LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF CONCRETE ROAD, BRGY. SAN JOSE, LAL-LO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2M | 100% | Low risk21 | —-0.076 |
| 20 | 18BB0026LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF CONCRETE ROAD, BRGY. CATUGAN, LAL-LO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2M | 100% | Low risk21 | —-0.079 |
| 21 | 18BB0025LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF CONCRETE ROAD, POJAS AND LANDETA, BRGY. DUGO, CAMALANIUGAN, CAGAYAN CAMALANIUGAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2M | 100% | Low risk21 | —-0.078 |
| 22 | 18BB0156CONSTRUCTION AND COMPLETION OF UNIQUE WORKSHOP (7.0M X 22.50M) CABIRAOAN NHS, GONZAGA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.6M | 100% | Low risk13 | —-0.036 |
| 23 | 18BB0013CONSTRUCTION OF MULTI-PURPOSE HALL (STAGE ONLY WITHOUT ROOF) , BINALAN, APARRI, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱976.8K | 100% | Low risk12 | —-0.081 |
| 24 | 21BB0180CONSTRUCTION OF CLASSROOMS - CONSTRUCTION/COMPLETION OF 4STY20CL (4CL 2-SCI. LAB, 2-ICT, 4-REG. WORKSHOP), AFUSING NHS, ALCALA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱301.6K | 100% | Low risk9 | —-0.037 |
| 25 | 17BB0073CONSTRUCTION OF 1-STOREY TWO (2) CLASSROOM WITH TOILET (SCHOOL ID 102569), PADDAYA ESTE ELEMENTARY SCHOOL, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2.6M | 100% | Low risk7 | —-0.016 |