Contractor dossier
25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱312.9M
Average progress
92.1%
Completion rate
56.0%
Below 70%
Average risk score
53.8
Medium risk on average, out of 100
Flagged as unusual
5
20.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 25 | ₱312.9M | 53.8 | 5 | 92.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 11 | ₱142.9M | 47.1 | 0 | 96.8% |
| Buildings and Facilities | 10 | ₱94.8M | 45.9 | 1 | 90.0% |
| GAA 2025 SSP | 2 | ₱13.8M | 91.6 | 2 | 92.4% |
| GAA 2025 OO-1 | 1 | ₱53.9M | 95.2 | 1 | 52.2% |
| OTHER | 1 | ₱7.5M | 89.4 | 1 | 99.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IC0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱53.9M | 52% | High risk95 | Flagged0.007 |
| 25IC0081REHABILITATION OF MULTI-PURPOSE BUILDING, REGIONAL EDUCATIONAL LEARNING CENTER (RELC) CONFERENCE ROOM AND OTHER RELATED WORKS PHASE 2, DEPED REGIONAL OFFICE 8, GOVERNMENT CENTER, BARANGAY CANDAHUG, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱5.9M | 100% | High risk92 | Flagged0.003 |
| 25ID0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VILLA PAZ,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.9M | 85% | High risk91 | Flagged0.011 |
| 23ID0107CONSTRUCTION OF 1-UNIT 1 STY3CL SCHOOL BUILDING BURAUEN NORTH CENTRAL SCHOOL, BURAUEN,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.5M | 99% | High risk89 | Flagged0.049 |
| 25IC0204CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ASLUM, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱4.9M | 100% | High risk66 | —-0.069 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23ID0107CONSTRUCTION OF 1-UNIT 1 STY3CL SCHOOL BUILDING BURAUEN NORTH CENTRAL SCHOOL, BURAUEN,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.5M | 99% | High risk89 | Flagged0.049 |
| 24I00338CONSTRUCTION OF WHITE COPRA RBDO (WHOLE NUT BUILDING), DARO, JARO, LEYTE | Region VIII | Region VIII | On-Going | ₱38M | 0% | Medium risk48 | Flagged0.043 |
| 25ID0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VILLA PAZ,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.9M | 85% | High risk91 | Flagged0.011 |
| 25IC0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱53.9M | 52% | High risk95 | Flagged0.007 |
| 25IC0081REHABILITATION OF MULTI-PURPOSE BUILDING, REGIONAL EDUCATIONAL LEARNING CENTER (RELC) CONFERENCE ROOM AND OTHER RELATED WORKS PHASE 2, DEPED REGIONAL OFFICE 8, GOVERNMENT CENTER, BARANGAY CANDAHUG, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱5.9M | 100% | High risk92 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25IC0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING -TERTIARY ROADS - BAGAHUPI-BABATNGON-STA CRUZ-BARUGO-CARIGARA ROAD - K0918 + 559 - K0918 + 992, K0922 + 000 - K0922 + 380, K0922 + 401 - K0923 + 000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱53.9M | 52% | High risk95 | Flagged0.007 |
| 2 | 25IC0081REHABILITATION OF MULTI-PURPOSE BUILDING, REGIONAL EDUCATIONAL LEARNING CENTER (RELC) CONFERENCE ROOM AND OTHER RELATED WORKS PHASE 2, DEPED REGIONAL OFFICE 8, GOVERNMENT CENTER, BARANGAY CANDAHUG, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱5.9M | 100% | High risk92 | Flagged0.003 |
| 3 | 25ID0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VILLA PAZ,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.9M | 85% | High risk91 | Flagged0.011 |
| 4 | 23ID0107CONSTRUCTION OF 1-UNIT 1 STY3CL SCHOOL BUILDING BURAUEN NORTH CENTRAL SCHOOL, BURAUEN,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.5M | 99% | High risk89 | Flagged0.049 |
| 5 | 25IC0204CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ASLUM, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱4.9M | 100% | High risk66 | —-0.069 |
| 6 | 23IC0081REHABILITATION OF MULTI-PURPOSE BUILDING, REGIONAL EDUCATIONAL LEARNING CENTER (RELC) CONFERENCE ROOM AND OTHER RELATED WORKS, DEPED REGIONAL OFFICE 8, GOVERNMENT CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.097 |
| 7 | 23IM0128CONSTRUCTION OF 1-UNIT 2STY6CL SCHOOL BUILDING, NORTH HILL ARBOURS INTEGRATED SCHOOL, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱15M | 100% | Medium risk50 | —-0.053 |
| 8 | 25ID0066CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 1, JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱5.9M | 100% | Medium risk50 | —-0.098 |
| 9 | 24ID0105CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY. SAN PEDRO, JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.098 |
| 10 | 24I00253ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LT) - K0908+605 - K0909+017, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱26.4M | 91% | Medium risk49 | —-0.052 |
| 11 | 23IM0062CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY 83-B, COGON, SAN JOSE, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱4.9M | 93% | Medium risk49 | —-0.043 |
| 12 | 23ID0034CONSTRUCTION OF ROAD, BRGY. OLOTAN-BRGY. CAGLAWAAN-BRGY. TUBA ROAD,JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱23.1M | 100% | Medium risk48 | —-0.091 |
| 13 | 24I00338CONSTRUCTION OF WHITE COPRA RBDO (WHOLE NUT BUILDING), DARO, JARO, LEYTE | Region VIII | Region VIII | On-Going | ₱38M | 0% | Medium risk48 | Flagged0.043 |
| 14 | 25ID0032CONSTRUCTION OF ROAD, BARANGAY ATIPOLO,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱19.8M | 81% | Medium risk48 | —-0.055 |
| 15 | 25ID0012CONSTRUCTION OF ROAD, SITIO SOLEDAD, BARANGAY SANTO NIÑO, JARO, LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.9M | 100% | Medium risk48 | —-0.063 |
| 16 | 25ID0020CONSTRUCTION OF ROAD,BARANGAY TINAMBACAN-PITOGO,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.9M | 100% | Medium risk48 | —-0.064 |
| 17 | 25ID0006CONSTRUCTION OF ROAD,BARANGAY PARASAN,JARO,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.8M | 100% | Medium risk48 | —-0.064 |
| 18 | 24ID0051CONSTRUCTION OF ROAD,BARANGAY TALINHUGON,DAGAMI,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.095 |
| 19 | 23ID0096CONSTRUCTION OF 1STY4CL SCHOOL BUILDING,BUENAVISTA ELEMENTARY SCHOOL,JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱12M | 100% | Medium risk47 | —-0.055 |
| 20 | 24ID0089CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CANAPUAN ELEMENTARY SCHOOL, BRGY. CANAPUAN,JARO, LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.055 |
| 21 | 24IC0175CONCRETING OF BRGY. BURI FMR, BRGY. BURI, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱11.9M | 100% | Medium risk45 | —-0.045 |
| 22 | 23IC0126CONCRETING OF BRGY. PATONG TO BRGY. LUKAY FMR, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱12.4M | 100% | Medium risk45 | —-0.044 |
| 23 | 23ID0114CONSTRUCTION OF ROAD,BARANGAY SAN AGUSTIN-BARANGAY ATIPOLO ROAD, JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱9.8M | 100% | Medium risk44 | —-0.044 |
| 24 | 24ID0033CONSTRUCTION (COMPLETION ) OF MULTI-PURPOSE BUILDING,BARANGAY KAGLAWAAN, JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱2M | 100% | Low risk26 | —-0.095 |
| 25 | 23IM0023CONSTRUCTION OF MULTI-PURPOSE FACILITY (WAITING SHED) AT TACLOBAN CITY RESETTLEMENT AREAS, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱2.1M | 100% | Low risk25 | —-0.094 |