Contractor dossier
287 projects on file, including joint ventures this contractor is part of.
Total projects
287
Total budget
₱6.3B
Average progress
94.2%
Completion rate
81.9%
Average risk score
45.9
Medium risk on average, out of 100
Flagged as unusual
12
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 287 | ₱6.3B | 45.9 | 12 | 94.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 132 | ₱3B | 44.1 | 2 | 96.2% |
| Flood Control and Drainage | 94 | ₱2.4B | 46.7 | 0 | 96.7% |
| Buildings and Facilities | 41 | ₱510.1M | 40.8 | 2 | 84.6% |
| OTHER | 6 | ₱115.8M | 76.5 | 2 | 94.2% |
| Water Provision and Storage | 5 | ₱25.4M | 32.2 | 1 | 89.9% |
| GAA 2025 SSP | 4 | ₱42.6M | 93.8 | 4 | 73.0% |
| Bridges, Roads | 2 | ₱174.7M | 55.7 | 0 | 100.0% |
| Bridges | 2 | ₱20.4M | 41.2 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱74.9M | 90.9 | 1 | 71.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25A00197SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD CONNECTING SUYO-ALILEM, SUYO, ILOCOS SUR (PHASE 2) | Region I | Region I | On-Going | ₱18.7M | 76% | High risk95 | Flagged0.023 |
| 25AD0040BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE, BARANGAY CABUGAO, SUYO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱4.8M | 91% | High risk94 | Flagged0.018 |
| 25A00157BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY BATBATO, ALILEM, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 66% | High risk94 | Flagged0.024 |
| 25AD0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 59% | High risk93 | Flagged0.027 |
| 25AD0042CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, STA. 0+000 - STA. 0+780, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱74.9M | 71% | High risk91 | Flagged0.004 |
| 25AD0076CONCRETING OF BAGANI GABOR-TOCGO-DALDAGAN-OAIGDAYA FMR, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 65% | High risk86 | Flagged0.055 |
| 24AD0101CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, BUGNAY ELEMENTARY SCHOOL, BRGY. BUGNAY, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱12.4M | 100% | High risk86 | Flagged0.045 |
| 24AD0051FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF VILLARICA-TALOGTOG CATERMAN FLOOD CONTROL, CANDON CITY ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱54.4M | 100% | High risk73 | —-0.019 |
| 22AD0117CONSTRUCTION OF BARANGAY ALLANGIGAN 2ND ROAD, BRGY. ALLANGIGAN 2ND, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.9M | 100% | High risk72 | —-0.026 |
| 24AD0043CONSTRUCTION OF ROAD, PALALI-NORTE-PALACAPAC ROAD, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.7M | 100% | High risk71 | —-0.026 |
| 24AD0046FLOOD MITIGATION STRUCTURES PROTECTING MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TALOGTOG CATERMAN, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.7M | 100% | High risk71 | —-0.027 |
| 17A00037CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS, CANDON-SANTIAGO-SAN ESTEBAN COASTAL ROAD LEADING TO SANTIAGO COVE, SANTIAGO, ILOCOS SUR | Region I | Region I | Completed | ₱96.5M | 100% | High risk67 | —-0.035 |
| 16AD0161CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF CARCARABASA RIVER CONTROL ALONG JCT. SANTIAGO-BANAYOYO- LIDLIDDA-SAN EMILIO-QUIRINO ROAD, STA. 0+160-STA. 0+630, LIDLIDDA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱20.1M | 100% | High risk65 | —-0.041 |
| 17AD0003CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF RIVER CONTROL ALONG TABLAC-BAGAR, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱29.4M | 100% | High risk65 | —-0.039 |
| 17AD0002CONSTRUCTIN/MAINTENANCE OF FLOOD MITIGATION STRUCTURES: CONSTRUCTION OF FLOOD CONTROL STRUCTURE-BUCAO WEST, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱34.3M | 100% | High risk65 | —-0.040 |
| 16AD0170CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF CALUNGBUYAN TO DARAPIDAP SEAWALL, CANDON CITY, ILOCOS SUR 2ND LD | Region I | Ilocos Sur 2nd DEO | Completed | ₱27.9M | 100% | High risk65 | —-0.039 |
| 16AD0163CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG CAVITE BRIDGE 1 & 2 , MNR, STA. LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱24.5M | 100% | High risk65 | —-0.040 |
| 16AD0165CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF OAIG-DAYA-SAN NICOLAS FLOOD CONTROL (GABION REVETMENT WALL ), CANDON CITY, ILOCOS SUR 2ND LD | Region I | Ilocos Sur 2nd DEO | Completed | ₱24.5M | 100% | High risk65 | —-0.040 |
| 17AD0001CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURE: CONSTRUCTION OF FLOOD CONTROL STRUCTURE-BUCAO EAST, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱26.2M | 100% | High risk65 | —-0.040 |
| 17AD0019ASSET PRESERVATION OF NATIONAL ROADS: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS ,PRIMARY ROADS, MANILA NORTH ROAD, K0348+000-K0349+000 | Region I | Ilocos Sur 2nd DEO | Completed | ₱29.4M | 100% | High risk65 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AD0076CONCRETING OF BAGANI GABOR-TOCGO-DALDAGAN-OAIGDAYA FMR, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 65% | High risk86 | Flagged0.055 |
| 24AD0101CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, BUGNAY ELEMENTARY SCHOOL, BRGY. BUGNAY, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱12.4M | 100% | High risk86 | Flagged0.045 |
| 24A00590CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - ALILEM SUPER HEALTH CENTER, ILOCOS SUR | Region I | Region I | On-Going | ₱11.6M | 31% | Medium risk39 | Flagged0.037 |
| 25AD0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 59% | High risk93 | Flagged0.027 |
| 25A00157BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY BATBATO, ALILEM, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 66% | High risk94 | Flagged0.024 |
| 25A00197SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD CONNECTING SUYO-ALILEM, SUYO, ILOCOS SUR (PHASE 2) | Region I | Region I | On-Going | ₱18.7M | 76% | High risk95 | Flagged0.023 |
| 24A00622REPAIR AND RENOVATION OF ACADEMIC BUILDING (COLLEGE OF TEACHER EDUCATION BUILDING) PHASE III, STA. MARIA - ILOCOS SUR POLYTECHNIC STATE COLLEGE | Region I | Region I | On-Going | ₱14.9M | 40% | Medium risk44 | Flagged0.018 |
| 25AD0040BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE, BARANGAY CABUGAO, SUYO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱4.8M | 91% | High risk94 | Flagged0.018 |
| 25AD0042CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, STA. 0+000 - STA. 0+780, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱74.9M | 71% | High risk91 | Flagged0.004 |
| 17AD0032CONCRETING OF BRGY. PALACAPAC FMR,BRGY. PALACAPAC, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱3.8M | 100% | Low risk22 | Flagged0.001 |
| 25AD0071CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE /RAINWATER COLLECTOR SYSTEM-RAINWATER COLLECTOR SYSTEM | Region I | Ilocos Sur 2nd DEO | On-Going | ₱2.5M | 50% | Medium risk33 | Flagged0.001 |
| 17AD0033CONCRETING OF BRGY. SAPANG FMR, BRGY. SAPANG, STA. LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 251 | 24AD0084ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OF ROAD, BARANGAY RUBIO, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.086 |
| 252 | 16AD0178CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAIANGE SYSTEM: CONSTRUCTION FLOOD CONTROL STRUCTURES, PUDOC WEST, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.7M | 100% | Medium risk41 | —-0.045 |
| 253 | 19AD0124CONCRETING OF BRGY. BANUCAL FMR, BRGY. BANUCAL, LIDLIDDA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.7M | 100% | Medium risk40 | —-0.035 |
| 254 | 24A00590CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - ALILEM SUPER HEALTH CENTER, ILOCOS SUR | Region I | Region I | On-Going | ₱11.6M | 31% | Medium risk39 | Flagged0.037 |
| 255 | 19AD0122CONCRETING OF BRGY. SUYSUYAN FMR, BRGY. SUYSUYAN, LIDLIDDA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.7M | 100% | Medium risk39 | —-0.035 |
| 256 | 17AD0025CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING-MAPISI ROCK PARK TOURISM | Region I | Ilocos Sur 2nd DEO | Completed | ₱2.8M | 100% | Medium risk39 | —-0.054 |
| 257 | 20AD0113CONCRETING OF SITIO MACAAG TO DAMUCO FMR, BRGY. SUYO PROPER, SUYO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱12.4M | 100% | Medium risk39 | —-0.035 |
| 258 | 23AD0090CONCRETING OF BRGY. BAGANI GABOR, CANDON CITY, TO BRGY. DALDAGAN, GALIMUYOD FMR, BRGY. BAGANI GABOR, CANDON CITY AND BRGY. DALDAGAN, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱12.1M | 100% | Medium risk39 | —-0.031 |
| 259 | 19AD0126CONCRETING OF BRGY. BUCAO WEST FMR, BRGY. BUCAO WEST, TAGUDIN, ILOCOS | Region I | Ilocos Sur 2nd DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.036 |
| 260 | 17AD0197CONSTRUCTION OF CLASSROOMS, CANDON CITY HIGH SCHOOL, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱8.7M | 100% | Medium risk39 | —-0.016 |
| 261 | 23AD0092CONCRETING OF BRGY SAN NICOLAS-PAYPAYAD-DARAPIDAP FMR, BRGY. SAN NICOLAS AND PAYPAYAD AND DARAPIDAP, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱12.1M | 100% | Medium risk39 | —-0.030 |
| 262 | 17AD0198CONSTRUCTION OF CLASSROOMS , DR. RICARDO GACULA MEMORIAL NHS, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱8.9M | 100% | Medium risk39 | —-0.010 |
| 263 | 22AD0137CONCRETING OF BRGY. AMBUGAT FMR, BRGY. AMBUGAT, BURGOS, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱11.6M | 100% | Medium risk39 | —-0.025 |
| 264 | 18AD0094CONCRETING OF ALLANGIGAN 1ST FMR, BRGY. ALLANGIGAN 1ST, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱5.7M | 100% | Medium risk39 | —-0.028 |
| 265 | 25AD0071CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE /RAINWATER COLLECTOR SYSTEM-RAINWATER COLLECTOR SYSTEM | Region I | Ilocos Sur 2nd DEO | On-Going | ₱2.5M | 50% | Medium risk33 | Flagged0.001 |
| 266 | 23AD0065CONSTRUCTION OF BAOS BRIDGE, STA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱3.8M | 100% | Low risk28 | —-0.049 |
| 267 | 20AD0065CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BIGBIGA, SANTIAGO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱2.8M | 100% | Low risk28 | —-0.082 |
| 268 | 19AD0017ASSET PRESERAVATION : PREVENTIVE MAINTENANCE-SECONDARY ROADS : SULVEC PORT RD - K0376 + (-626) - K0377 + 000, NARVACAN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.6M | 100% | Low risk27 | —-0.086 |
| 269 | 25AD0009REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - ALILEM -SUGPON-SUDIPEN RD K0321+590-K0321+723 | Region I | Ilocos Sur 2nd DEO | On-Going | ₱2.7M | 100% | Low risk26 | —-0.056 |
| 270 | 19AD0075REHABILITATION OF CANDON CITY MULTI-PURPOSE BUILDING (SLAUGHTERHOUSE), BRGY.SAN ISIDRO,CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱2.4M | 100% | Low risk26 | —-0.083 |
| 271 | 19AD0008NETWORK DEVELOPMENT: OFF CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS ALONG ILOCOS SUR-ABRA ROAD, K0385+261-K0386+046, NARVACAN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.1M | 100% | Low risk26 | —-0.085 |
| 272 | 20AD0032JCT SANTIAGO-BANAYOYO-LIDLIDDA-SN EMILIO-QUIRINO RD - K0362 + 400 - K0362 + 530 | Region I | Ilocos Sur 2nd DEO | Completed | ₱3.7M | 100% | Low risk25 | —-0.086 |
| 273 | 20AD0037JCT CANDON-SALCEDO-DEL PILAR RD - K0356 + 650 | Region I | Ilocos Sur 2nd DEO | Completed | ₱2.8M | 100% | Low risk25 | —-0.086 |
| 274 | 20AD0031JCT CANDON-SALCEDO-DEL PILAR RD - K0354+ 250 - K0354+ 450 | Region I | Ilocos Sur 2nd DEO | Completed | ₱2.8M | 100% | Low risk24 | —-0.084 |
| 275 | 17AD0032CONCRETING OF BRGY. PALACAPAC FMR,BRGY. PALACAPAC, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱3.8M | 100% | Low risk22 | Flagged0.001 |