Contractor dossier
287 projects on file, including joint ventures this contractor is part of.
Total projects
287
Total budget
₱6.3B
Average progress
94.2%
Completion rate
81.9%
Average risk score
45.9
Medium risk on average, out of 100
Flagged as unusual
12
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 287 | ₱6.3B | 45.9 | 12 | 94.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 132 | ₱3B | 44.1 | 2 | 96.2% |
| Flood Control and Drainage | 94 | ₱2.4B | 46.7 | 0 | 96.7% |
| Buildings and Facilities | 41 | ₱510.1M | 40.8 | 2 | 84.6% |
| OTHER | 6 | ₱115.8M | 76.5 | 2 | 94.2% |
| Water Provision and Storage | 5 | ₱25.4M | 32.2 | 1 | 89.9% |
| GAA 2025 SSP | 4 | ₱42.6M | 93.8 | 4 | 73.0% |
| Bridges, Roads | 2 | ₱174.7M | 55.7 | 0 | 100.0% |
| Bridges | 2 | ₱20.4M | 41.2 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱74.9M | 90.9 | 1 | 71.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25A00197SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD CONNECTING SUYO-ALILEM, SUYO, ILOCOS SUR (PHASE 2) | Region I | Region I | On-Going | ₱18.7M | 76% | High risk95 | Flagged0.023 |
| 25AD0040BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE, BARANGAY CABUGAO, SUYO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱4.8M | 91% | High risk94 | Flagged0.018 |
| 25A00157BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY BATBATO, ALILEM, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 66% | High risk94 | Flagged0.024 |
| 25AD0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 59% | High risk93 | Flagged0.027 |
| 25AD0042CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, STA. 0+000 - STA. 0+780, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱74.9M | 71% | High risk91 | Flagged0.004 |
| 25AD0076CONCRETING OF BAGANI GABOR-TOCGO-DALDAGAN-OAIGDAYA FMR, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 65% | High risk86 | Flagged0.055 |
| 24AD0101CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, BUGNAY ELEMENTARY SCHOOL, BRGY. BUGNAY, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱12.4M | 100% | High risk86 | Flagged0.045 |
| 24AD0051FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF VILLARICA-TALOGTOG CATERMAN FLOOD CONTROL, CANDON CITY ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱54.4M | 100% | High risk73 | —-0.019 |
| 22AD0117CONSTRUCTION OF BARANGAY ALLANGIGAN 2ND ROAD, BRGY. ALLANGIGAN 2ND, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.9M | 100% | High risk72 | —-0.026 |
| 24AD0043CONSTRUCTION OF ROAD, PALALI-NORTE-PALACAPAC ROAD, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.7M | 100% | High risk71 | —-0.026 |
| 24AD0046FLOOD MITIGATION STRUCTURES PROTECTING MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TALOGTOG CATERMAN, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.7M | 100% | High risk71 | —-0.027 |
| 17A00037CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS, CANDON-SANTIAGO-SAN ESTEBAN COASTAL ROAD LEADING TO SANTIAGO COVE, SANTIAGO, ILOCOS SUR | Region I | Region I | Completed | ₱96.5M | 100% | High risk67 | —-0.035 |
| 16AD0161CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF CARCARABASA RIVER CONTROL ALONG JCT. SANTIAGO-BANAYOYO- LIDLIDDA-SAN EMILIO-QUIRINO ROAD, STA. 0+160-STA. 0+630, LIDLIDDA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱20.1M | 100% | High risk65 | —-0.041 |
| 17AD0003CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF RIVER CONTROL ALONG TABLAC-BAGAR, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱29.4M | 100% | High risk65 | —-0.039 |
| 17AD0002CONSTRUCTIN/MAINTENANCE OF FLOOD MITIGATION STRUCTURES: CONSTRUCTION OF FLOOD CONTROL STRUCTURE-BUCAO WEST, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱34.3M | 100% | High risk65 | —-0.040 |
| 16AD0170CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF CALUNGBUYAN TO DARAPIDAP SEAWALL, CANDON CITY, ILOCOS SUR 2ND LD | Region I | Ilocos Sur 2nd DEO | Completed | ₱27.9M | 100% | High risk65 | —-0.039 |
| 16AD0163CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG CAVITE BRIDGE 1 & 2 , MNR, STA. LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱24.5M | 100% | High risk65 | —-0.040 |
| 16AD0165CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION : CONSTRUCTION OF OAIG-DAYA-SAN NICOLAS FLOOD CONTROL (GABION REVETMENT WALL ), CANDON CITY, ILOCOS SUR 2ND LD | Region I | Ilocos Sur 2nd DEO | Completed | ₱24.5M | 100% | High risk65 | —-0.040 |
| 17AD0001CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURE: CONSTRUCTION OF FLOOD CONTROL STRUCTURE-BUCAO EAST, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱26.2M | 100% | High risk65 | —-0.040 |
| 17AD0019ASSET PRESERVATION OF NATIONAL ROADS: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS ,PRIMARY ROADS, MANILA NORTH ROAD, K0348+000-K0349+000 | Region I | Ilocos Sur 2nd DEO | Completed | ₱29.4M | 100% | High risk65 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AD0076CONCRETING OF BAGANI GABOR-TOCGO-DALDAGAN-OAIGDAYA FMR, GALIMUYOD, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 65% | High risk86 | Flagged0.055 |
| 24AD0101CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, BUGNAY ELEMENTARY SCHOOL, BRGY. BUGNAY, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱12.4M | 100% | High risk86 | Flagged0.045 |
| 24A00590CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - ALILEM SUPER HEALTH CENTER, ILOCOS SUR | Region I | Region I | On-Going | ₱11.6M | 31% | Medium risk39 | Flagged0.037 |
| 25AD0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, SANTA LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.6M | 59% | High risk93 | Flagged0.027 |
| 25A00157BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY BATBATO, ALILEM, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 66% | High risk94 | Flagged0.024 |
| 25A00197SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD CONNECTING SUYO-ALILEM, SUYO, ILOCOS SUR (PHASE 2) | Region I | Region I | On-Going | ₱18.7M | 76% | High risk95 | Flagged0.023 |
| 24A00622REPAIR AND RENOVATION OF ACADEMIC BUILDING (COLLEGE OF TEACHER EDUCATION BUILDING) PHASE III, STA. MARIA - ILOCOS SUR POLYTECHNIC STATE COLLEGE | Region I | Region I | On-Going | ₱14.9M | 40% | Medium risk44 | Flagged0.018 |
| 25AD0040BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE, BARANGAY CABUGAO, SUYO, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱4.8M | 91% | High risk94 | Flagged0.018 |
| 25AD0042CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, STA. 0+000 - STA. 0+780, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | On-Going | ₱74.9M | 71% | High risk91 | Flagged0.004 |
| 17AD0032CONCRETING OF BRGY. PALACAPAC FMR,BRGY. PALACAPAC, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱3.8M | 100% | Low risk22 | Flagged0.001 |
| 25AD0071CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE /RAINWATER COLLECTOR SYSTEM-RAINWATER COLLECTOR SYSTEM | Region I | Ilocos Sur 2nd DEO | On-Going | ₱2.5M | 50% | Medium risk33 | Flagged0.001 |
| 17AD0033CONCRETING OF BRGY. SAPANG FMR, BRGY. SAPANG, STA. LUCIA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 201 | 25A00196SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - IMPROVEMENT OF ROAD, ALILEM DAYA-SOY-OC-LAP-ANGAN, ALILEM, ILOCOS SUR | Region I | Region I | On-Going | ₱6.6M | 44% | Medium risk44 | —-0.036 |
| 202 | 25AD0007REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - TAGUDIN-CERVANTES RD - K0323+010 - K0323+092, K0323+698 - K0324+002, K0338+000 - K0338+268, K0342+250 - K0342+383 | Region I | Ilocos Sur 2nd DEO | On-Going | ₱21.5M | 67% | Medium risk44 | —-0.042 |
| 203 | 22AD0066NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS ALONG MANILA NORTH ROAD, K0325+050-K0325+250, K0336+457-K0336+887 | Region I | Ilocos Sur 2nd DEO | Completed | ₱19.6M | 100% | Medium risk44 | —-0.074 |
| 204 | 20AD0038MANILA NORTH RD - K0325 + 250 - K0325 + 838, K0334 + 396 - K0334 + 730 | Region I | Ilocos Sur 2nd DEO | Completed | ₱26M | 100% | Medium risk44 | —-0.085 |
| 205 | 17AD0023CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING-CANDON BEACH RESORT, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱4.7M | 100% | Medium risk44 | —-0.055 |
| 206 | 19AD0047NETWORK DEVELOPMENT: OFF-CARRIAGEWAY- SECONDARY ROADS ALONG TAGUDIN-CERVANTES ROADS, K0321+(-353) -K0322+697, BRGY. BITALAG, TAGUDIN, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱23.7M | 100% | Medium risk44 | —-0.089 |
| 207 | 23AD0093CONCRETING OF ALLANGIGAN 2ND TO OAIG DAYA, SITIO NAGREBCAN FMR, OAIG DAYA, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.5M | 100% | Medium risk44 | —-0.030 |
| 208 | 22AD0020CONSTRUCTION OF ROAD LEADING TO CANDON SPORTS CENTER AND CONVENTION CENTER, BARANGAY BAGANI CAMPO, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱16.7M | 100% | Medium risk43 | —-0.080 |
| 209 | 24AD0007REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROADS ALILEM SUGPON SUDIPEN RD K0321 + 382 K0321 + 585, K0323+000-K0323-092 | Region I | Ilocos Sur 2nd DEO | Completed | ₱8.2M | 100% | Medium risk43 | —-0.089 |
| 210 | 23AD0014ROAD WIDENING - TERTIARY ROADS - JCT SANTIAGO-BANAYOYO-LIDLIDDA-SN EMILIO-QUIRINO RD - K0352 + (-126) - K0352 + 097, K0352 + 113 - K0352 + 304, K0352 + 313 - K0352 + 400 | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.7M | 100% | Medium risk43 | —-0.079 |
| 211 | 19AD0081CONSTRUCTION/REPAIR/REHAB/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS: CONSTRUCTION OF CANDON-SANTIAGO-SAN ESTEBAN-STA.MARIA COASTAL ROAD (BRGY. DARAPIDAP SECTION) LEADING TO SANTIAGO COVE, BRGY. DARAPIDAP, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱16.8M | 100% | Medium risk43 | —-0.082 |
| 212 | 24AD0042CONSTRUCTION OF ROAD, BARANGAY SAN NICOLAS, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.3M | 100% | Medium risk43 | —-0.086 |
| 213 | 18AD0114CONSTRUCTION AND COMPLETION OF SCHOOL BUILDINGS IN THE ELEMENTARY AND SECONDARY CLASSROOMS, PATPATA ES, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱8.9M | 100% | Medium risk43 | —-0.040 |
| 214 | 23AD0006REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVE ROADS-TERTIARY ROADS, BURGOS-LIDLIDDA ROAD-K0367+000-K0367+680 | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.8M | 100% | Medium risk43 | —-0.081 |
| 215 | 23AD0091CONCRETING OF LANGLANGCA 1ST-SALVADOR FMR, BRGY. LANGLANGCA 1ST AND SALVADOR, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.5M | 100% | Medium risk43 | —-0.022 |
| 216 | 25A00156BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY TALOGTOG, CITY OF CANDON, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 31% | Medium risk43 | —-0.030 |
| 217 | 25A00173BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY TABLAS, CITY OF CANDON, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 47% | Medium risk43 | —-0.035 |
| 218 | 24AD0010REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. CANDON - SALCEDO - DEL PILAR - RD, K0350+454 - K0350+690, K0352+469 - K0352+963 | Region I | Ilocos Sur 2nd DEO | Completed | ₱14.1M | 100% | Medium risk43 | —-0.084 |
| 219 | 21AD0007REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- TERTIARY ROADS JCT. STA. LUCIA-SALCEDO ROAD, K0341+465-341+525 & K0345+000-345+800 | Region I | Ilocos Sur 2nd DEO | Completed | ₱18.1M | 100% | Medium risk43 | —-0.087 |
| 220 | 22AD0155CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS, LIDLIDDA NATIONAL HIGH SCHOOL | Region I | Ilocos Sur 2nd DEO | Completed | ₱11.6M | 100% | Medium risk43 | —-0.038 |
| 221 | 22AD0018CONSTRUCTION OF ECOPARK PALACAPAC-AMGUID ROAD CONNECTING CANDON-SALCEDO ROAD, BARANGAY PALACAPAC AND AMGUID, CANDON CITY, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.5M | 100% | Medium risk43 | —-0.084 |
| 222 | 25AD0018CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL IT)- SITIO MANGGAAN ROAD IN SUPPORT TO VEGETABLE, PIGEON PEA, PURPLE YAM, MUNG BEAN, BA | Region I | Ilocos Sur 2nd DEO | On-Going | ₱9.5M | 90% | Medium risk43 | —-0.052 |
| 223 | 24AD0017SITIO MANGGAAN ROAD IN SUPPORT TO VEGETABLE, PIGEON PEA, PURPLE YAM, MUNG BEAN, BANANA, COFFEE, GABI, ANNATO, PEANUT, CORN AND OTHER HIGH-VALUE CROPS PROCESSING CENTER, SUGPON, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.5M | 100% | Medium risk43 | —-0.091 |
| 224 | 23AD0059CONSTRUCTION OF KARDIS-BAKDEY ROAD, POBLACION NORTE, LIDLIDDA, ILOCOS SUR | Region I | Ilocos Sur 2nd DEO | Completed | ₱9.8M | 100% | Medium risk43 | —-0.084 |
| 225 | 25A00171BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, BARANGAY BAGANI CAMPO, BARANGAY TOCGO, BARANGAY DALDAGAN, CITY OF CANDON, ILOCOS SUR | Region I | Region I | On-Going | ₱9.6M | 57% | Medium risk43 | —-0.039 |