Opening the dossier…
Opening the dossier…
Contractor dossier
6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱68.5M
Average progress
93.1%
Completion rate
66.7%
Below 70%
Average risk score
43.7
Medium risk on average, out of 100
Flagged as unusual
1
16.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 6 | ₱68.5M | 43.7 | 1 | 93.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 2 | ₱19.5M | 26.5 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱14.8M | 18.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱14.7M | 91.3 | 1 | 58.8% |
| GAA 2025 OO-2 | 1 | ₱19.5M | 80.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MG0059CONSTRUCTION OF ROAD JCT. NATIONAL HIGHWAY AT SOCOTECO TO PUROK HECHANOVA, BARANGAY PARAISO, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱14.7M | 59% | High risk91 | Flagged0.027 |
| 25MG0079CONSTRUCTION OF RIVERBANK PROTECTION ALONG B'LOK CREEK, BRGY. NEW LAMBUNAO, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱19.5M | 100% | High risk81 | —-0.018 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MG0059CONSTRUCTION OF ROAD JCT. NATIONAL HIGHWAY AT SOCOTECO TO PUROK HECHANOVA, BARANGAY PARAISO, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱14.7M | 59% | High risk91 | Flagged0.027 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25MG0059CONSTRUCTION OF ROAD JCT. NATIONAL HIGHWAY AT SOCOTECO TO PUROK HECHANOVA, BARANGAY PARAISO, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱14.7M | 59% | High risk91 | Flagged0.027 |
| 2 | 25MG0079CONSTRUCTION OF RIVERBANK PROTECTION ALONG B'LOK CREEK, BRGY. NEW LAMBUNAO, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | On-Going | ₱19.5M | 100% | High risk81 | —-0.018 |
| 3 | 25MG0028CONSTRUCTION OF CONCRETE ROAD-BRGY. SAN JOSE PROPER-SITIO BOUNDARY-PUROK APOSTOL-TINAGO ROAD IN SUPPORT OF AGRI-PROCESSING ACTIVITIES IN THE AREA, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱14.7M | 100% | Low risk27 | —-0.088 |
| 4 | 25MB0090CONSTRUCTION OF ROAD, P.I. 16, BARANGAY CITY HEIGHTS, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱4.8M | 100% | Low risk26 | —-0.084 |
| 5 | 24MG0137CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ASSUMPTION, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱9.8M | 100% | Low risk21 | —-0.084 |
| 6 | 24MB0103CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CEBUANO ELEMENTARY SCHOOL - MAMBUSONG EXTENSION, BRGY. CEBUANO, TUPI, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱5M | 100% | Low risk16 | —-0.042 |