21 projects on file, including joint ventures this contractor is part of.
Total projects
21
Total budget
₱429.6M
Average progress
94.1%
Completion rate
85.7%
Average risk score
46.7
Medium risk on average, out of 100
Flagged as unusual
2
9.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 21 | ₱429.6M | 46.7 | 2 | 94.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 11 | ₱185.3M | 38.1 | 0 | 99.6% |
| Flood Control and Drainage | 4 | ₱91M | 44.7 | 0 | 100.0% |
| Buildings and Facilities | 3 | ₱29.7M | 43.4 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱85.5M | 93.4 | 1 | 36.4% |
| GAA 2025 OO-2 | 1 | ₱14.4M | 84.7 | 1 | 44.8% |
| OTHER | 1 | ₱23.7M | 74.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BC0003ORGANIZATION OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - JCT.-LOGAC-LASAM-GAGABUTAN RD - (S00656LZ) CHAINAGE 5560 - CHAINAGE 7960 | Region II | Cagayan 2nd DEO | On-Going | ₱85.5M | 36% | High risk93 | Flagged0.019 |
| 25BC0020ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER BANK PROTECTION, ZINUNDUNGAN RIVER IRRIGATION SY | Region II | Cagayan 2nd DEO | On-Going | ₱14.4M | 45% | High risk85 | Flagged0.001 |
| 24BC0012ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT LOGAC-LASAM-GAGABUTAN RD. - K0716 + (-885) - K0716 + 265 | Region II | Cagayan 2nd DEO | Completed | ₱23.7M | 100% | High risk75 | —-0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BC0003ORGANIZATION OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - JCT.-LOGAC-LASAM-GAGABUTAN RD - (S00656LZ) CHAINAGE 5560 - CHAINAGE 7960 | Region II | Cagayan 2nd DEO | On-Going | ₱85.5M | 36% | High risk93 | Flagged0.019 |
| 25BC0020ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER BANK PROTECTION, ZINUNDUNGAN RIVER IRRIGATION SY | Region II | Cagayan 2nd DEO | On-Going | ₱14.4M | 45% | High risk85 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25BC0003ORGANIZATION OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - JCT.-LOGAC-LASAM-GAGABUTAN RD - (S00656LZ) CHAINAGE 5560 - CHAINAGE 7960 | Region II | Cagayan 2nd DEO | On-Going | ₱85.5M | 36% | High risk93 | Flagged0.019 |
| 2 | 25BC0020ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF RIVER BANK PROTECTION, ZINUNDUNGAN RIVER IRRIGATION SY | Region II | Cagayan 2nd DEO | On-Going | ₱14.4M | 45% | High risk85 | Flagged0.001 |
| 3 | 24BC0012ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT LOGAC-LASAM-GAGABUTAN RD. - K0716 + (-885) - K0716 + 265 | Region II | Cagayan 2nd DEO | Completed | ₱23.7M | 100% | High risk75 | —-0.027 |
| 4 | 24BC0123CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PACKAGE 3), ABULUG, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱19.8M | 100% | Medium risk50 | —-0.078 |
| 5 | 22BC0017OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS-JCT. LOGAC-LASAM-GAGABUTAN RD - K0717+027-K0720+028, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱53M | 100% | Medium risk48 | —-0.077 |
| 6 | 25BC0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) SAN PEDRO-MAGSAYSAY-CABATACAN WEST BARA | Region II | Cagayan 2nd DEO | On-Going | ₱12.2M | 95% | Medium risk46 | —-0.054 |
| 7 | 23BC0073OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CANAYUN FLOOD CONTROL ALONG ABULUG-APAYAO RIVER, BRGY. CANAYUN, ABULUG, CAGA | Region II | Cagayan 2nd DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.064 |
| 8 | 22BC0116CONCRETING OF BRGY. NICOLAS AGATEP TO BRGY. MALINTA FMR, BRGY. NICOLAS AGATEP AND BRGY. MALINTA, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱24.8M | 100% | Medium risk45 | —-0.021 |
| 9 | 23BC0076OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF BANK PROTECTION ALONG MATALAG RIVER, ILLURU SUR, RI | Region II | Cagayan 2nd DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.067 |
| 10 | 23BC0020OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- RESTORATION OF ZINUNDUNGAN FLOOD CONTROL, STA. 0 + 000 - STA. 0 + 100, SICALAO, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱22.8M | 100% | Medium risk45 | —-0.068 |
| 11 | 24BC0066OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONSTRUCTION OF SICALAO RIVER CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER,LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱19.3M | 100% | Medium risk44 | —-0.068 |
| 12 | 22BC0109CONCRETING OF BRGY. CALOG SUR TO BRGY. LIBERTAD FMR, BRGY. CALOG SUR AND BRGY, LIBERTAD, ABULUG, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱29.8M | 100% | Medium risk43 | —-0.023 |
| 13 | 23BC0005OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS-JCT LOGAC-LASAM-GAGABUTAN RD- K0734 + 885 - K0734 + 945, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱7.1M | 100% | Medium risk43 | —-0.082 |
| 14 | 23BC0072ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MANILA NORTH ROAD K0663+000 - K0663+500 | Region II | Cagayan 2nd DEO | Completed | ₱19.4M | 100% | Medium risk42 | —-0.080 |
| 15 | 23BC0071ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - MANILA NORTH RD K0632+679-K0633+236, SANCHEZ MIRA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱20.5M | 100% | Medium risk41 | —-0.076 |
| 16 | 24BC0109CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CALOG NORTE ELEMENTARY SCHOOL, BARANGAY CALOG NORTE, ABULUG, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱5M | 100% | Medium risk40 | —-0.039 |
| 17 | 24BC0108CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SIMAYUNG ELEMENTARY SCHOOL, BARANGAY SIMAYUNG, ABULUG, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱5M | 100% | Medium risk40 | —-0.040 |
| 18 | 24BC0116CONCRETING OF BRGY. MINANGA SUR FMR, BRGY. MINANGA SUR, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱9.7M | 100% | Medium risk39 | —-0.030 |
| 19 | 23BC0052CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-SAN PEDRO-MAGSAYSAY-CABATACAN WEST BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONNECTING TO BANANA, COCONUT, AND CACAO PLANTATION AND PROCESSING | Region II | Cagayan 2nd DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.080 |
| 20 | 23BC0038CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT)-AGGUNETAN-TAGAO-VIGA BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONNECTI | Region II | Cagayan 2nd DEO | Completed | ₱2.9M | 100% | Low risk24 | —-0.080 |
| 21 | 23BC0041CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-CABATACAN EAST BARANGAY ROAD TO JCT. LOGAC-LASAM-GAGABUTAN ROAD CONNECTING TO CACAO PLANTATION AND PROCESSING, CABATACAN EAST, LASAM, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱2.9M | 100% | Low risk24 | —-0.080 |