Contractor dossier
81 projects on file, including joint ventures this contractor is part of.
Total projects
81
Total budget
₱828M
Average progress
96.7%
Completion rate
75.3%
Average risk score
34.7
Medium risk on average, out of 100
Flagged as unusual
5
6.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 68 | ₱722.5M | 34.4 | 5 | 96.2% |
| Region XIII | 9 | ₱77.6M | 39.2 | 0 | 99.2% |
| Negros Island Region | 4 | ₱27.8M | 29.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 43 | ₱216.7M | 24.7 | 1 | 99.3% |
| Roads | 22 | ₱321M | 40.8 | 2 | 94.2% |
| Water Provision and Storage | 7 | ₱59.8M | 38.0 | 0 | 99.0% |
| GAA 2025 SSP | 3 | ₱107.8M | 94.3 | 2 | 67.8% |
| Flood Control and Drainage | 3 | ₱48.3M | 45.1 | 0 | 100.0% |
| Bridges | 2 | ₱37.8M | 46.2 | 0 | 98.4% |
| OTHER | 1 | ₱36.5M | 71.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00192CONSTRUCTION OF ROAD, BUBONG (LANAO DEL SUR) - KAPAI (LANAO DEL SUR) - TAGOLOAN (LANAO DEL NORTE) ROAD, PACKAGE 1, LANAO DEL SUR | Region X | Region X | On-Going | ₱93.1M | 52% | High risk96 | Flagged0.019 |
| 25KH0019REHABILITATION OF ROAD IN BARANGAY PATAG, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱9.8M | 96% | High risk94 | —-0.003 |
| 25KL0073CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LAGUINDINGAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱4.9M | 56% | High risk94 | Flagged0.009 |
| 24K00252REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS MARAWI-MASIU RD - (S01603MN) CHAINAGE 23249 - CHAINAGE 23821, CHAINAGE 28648 - CHAINAGE 29648 | Region X | Region X | On-Going | ₱36.5M | 100% | High risk71 | —-0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00192CONSTRUCTION OF ROAD, BUBONG (LANAO DEL SUR) - KAPAI (LANAO DEL SUR) - TAGOLOAN (LANAO DEL NORTE) ROAD, PACKAGE 1, LANAO DEL SUR | Region X | Region X | On-Going | ₱93.1M | 52% | High risk96 | Flagged0.019 |
| 25K00358CONCRETING OF BRGY. PALAO-SUGOD FMR, BRGY. PALAO, BUBONG, LANAO DEL SUR | Region X | Region X | On-Going | ₱39.8M | 59% | Medium risk47 | Flagged0.012 |
| 25KL0073CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LAGUINDINGAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱4.9M | 56% | High risk94 | Flagged0.009 |
| 24K00531CONCRETING OF ROAD, RAYA GUIMBA TO BARANGAY PAPANDAYAN (SECOND PHASE), MARAWI CITY | Region X | Region X | On-Going | ₱48.2M | 96% | Medium risk52 | Flagged0.005 |
| 24K00512CONSTRUCTION OF 2-STOREY 8-CLASSROOMS SCHOOL BUILDING IN SULTAN ALAUYA ALONTO CENTRAL ELEMENTARY SCHOOL, DITSAAN-RAMAIN, LANAO DEL SUR | Region X | Region X | On-Going | ₱29.8M | 72% | Medium risk44 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23KE0040CONSTRUCTION OF SOLAR WATER SYSTEM TUPSAN NATIONAL HIGH SCHOOL | Region X | Camiguin DEO | Completed | ₱9.4M | 100% | Medium risk44 | —-0.058 |
| 27 | 23KE0038CONSTRUCTION OF SOLAR WATER SYSTEM BENHAAN ELEMENTARY SCHOOL | Region X | Camiguin DEO | Completed | ₱9.5M | 100% | Medium risk44 | —-0.058 |
| 28 | 25K00025REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS MARAWI-MARANTAO RD - (S01602MN) CHAINAGE 5555 - CHAINAGE 5695 | Region X | Region X | On-Going | ₱4.8M | 99% | Medium risk44 | —-0.061 |
| 29 | 23NE0109CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. HELENE, LORETO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱9.8M | 93% | Medium risk43 | —-0.013 |
| 30 | 22K00035CONSTRUCTION OF ROAD, BARANGAY BASAGAD, PUALAS, LANAO DEL SUR (STA.0+000-STA.0+230) | Region X | Region X | Completed | ₱4.8M | 100% | Medium risk43 | —-0.093 |
| 31 | 21KH0006CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO HINAPLANON, BRGY. BAIKINGON, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | Completed | ₱5.8M | 100% | Medium risk43 | —-0.097 |
| 32 | 22KE0070CONSTRUCTION (COMPLETION) OF MULTIPURPOSE FACILITY IN BARANGAY BONBON, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱6.1M | 100% | Medium risk43 | —-0.096 |
| 33 | 22KC0047CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL IPMR TRIBAL TULUGAN HALL) , BARANGAY POBLACION, LIBONA, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.097 |
| 34 | 24K00464CONST. OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN FRANCFORT CENTRAL ELEMENTARY SCHOOL, BRGY. FRANCFORT, AMAI MANABILANG LANAO DEL SUR | Region X | Region X | On-Going | ₱9.9M | 100% | Medium risk42 | —-0.013 |
| 35 | 22KB0139CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAHAYAG, QUEZON,, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.093 |
| 36 | 24K00440CONCRETING OF BRGY. RAYA GUIMBA TO BRGY. PAPANDAYAN FMR, BRGY. RAYA GUIMBA AND BRGY. PAPANDAYAN, MARAWI CITY, LANAO DEL SUR | Region X | Region X | On-Going | ₱9.9M | 100% | Medium risk41 | —-0.002 |
| 37 | 23KA0154CONSTRUCTION OF MULTI-PURPOSE BUILDING (TALAANDIG TRIBAL GUEST HOUSE), BRGY. SONGCO, LANTAPAN, BUKIDNONBRGY. SONGCO, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk41 | —-0.095 |
| 38 | 22KA0107REHABILITATION OF MULTI PURPOSE BUILDING,BRGY. SONGCO, LANTAPAN, BUKIDNON, LANTAPAN, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk41 | —-0.095 |
| 39 | 21KK0088CONSTRUCTION OF EVACUATION CENTER/MULTI-PURPOSE HALL, BARANGAY ARTADI, MAGSAYSAY, MISAMIS ORIENTAL | Region X | Misamis Oriental 1st DEO | Completed | ₱6.9M | 100% | Medium risk41 | —-0.093 |
| 40 | 23NE0107CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. IMELDA, TUBAJON, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱9.8M | 100% | Medium risk41 | —-0.048 |
| 41 | 24KA0152CONSTRUCTION OF MULTI-PURPOSE BUILDING (PROVINCIAL CULTURAL HERITAGE CENTER), BRGY. KALASUNGAY, MALAYBALAY CITY, BUKIDNONBARANGAY KALASUNGAY, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.093 |
| 42 | 19KB0163CONCRETING OF BRGY LIBERTAD FMR, BRGY LIBERTAD, QUEZON, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱8.3M | 100% | Medium risk40 | —-0.039 |
| 43 | 23NE0096CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. ROMA, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱9.5M | 100% | Medium risk40 | —-0.041 |
| 44 | 19KB0164CONCRETING OF SITIO BAKBAKON, BRGY CABADIANGAN FMR, BRGY CABADIANGAN, KADINGILAN, BUKIDNON | Region X | Bukidnon 2nd DEO | Completed | ₱9.4M | 100% | Medium risk40 | —-0.041 |
| 45 | 23NE0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES SITIO MARAGUING TO GENERAL AGUINALDO TO NATIONAL ROAD IN SUPPORT TO AGRI-INDUSTRIES ZONE, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱7.3M | 100% | Medium risk39 | —-0.088 |
| 46 | 23NE0108CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. BOA, CAGDIANAO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱9.8M | 100% | Medium risk39 | —-0.045 |
| 47 | 23NE0033CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS MAHAYAHAY (SAN JOSE) - GOMEZ (DINAGAT) ROAD LEADING TO TAGBUYAKHAW TOURISM AREA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱7.3M | 100% | Medium risk39 | —-0.088 |
| 48 | 23NE0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HELEN, LORETO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.075 |
| 49 | 21GO0099COMPLETION/CONSTRUCTION OF 4-STOREY-4 LABORATORY (2-SCIENCE LABORATORY & 2 -ICT W/ 4 CLASSROOM) AT LUISA MEDEL NATIONAL HIGH SCHOOL, BRGY. TANGUB, BACOLOD CITY | Negros Island Region | Bacolod City DEO | Completed | ₱12.8M | 100% | Medium risk39 | —-0.046 |
| 50 | 24KE0102CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CATOHUGAN ELEMENTARY SCHOOL, BARANGAY CATOHUGAN, MUNICIPALITY OF MAHINOG, PROVINCE OF CAMIGUIN | Region X | Camiguin DEO | Completed | ₱5M | 100% | Medium risk38 | —-0.048 |