172 projects on file, including joint ventures this contractor is part of.
Total projects
172
Total budget
₱2.3B
Average progress
92.7%
Completion rate
82.0%
Average risk score
40.8
Medium risk on average, out of 100
Flagged as unusual
2
1.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 129 | ₱2B | 40.6 | 1 | 93.2% |
| Region IV-A | 41 | ₱271.9M | 41.7 | 1 | 90.9% |
| Region III | 2 | ₱4.8M | 35.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 101 | ₱1B | 40.5 | 0 | 93.6% |
| Roads | 34 | ₱235.6M | 33.7 | 0 | 92.3% |
| Flood Control and Drainage | 23 | ₱900.8M | 48.3 | 0 | 91.3% |
| Water Provision and Storage | 7 | ₱21.8M | 30.6 | 0 | 99.7% |
| OTHER | 4 | ₱43.6M | 45.7 | 0 | 100.0% |
| GAA 2025 SSP | 3 | ₱66.3M | 93.4 | 2 | 52.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0063CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.7M | 28% | High risk94 | Flagged0.013 |
| 25OB0148REHABILITATION OF PULONG KENDI 1 ST., BURGOS ST. AND BONIFACIO ST. AT BARANGAY STA. ANA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱37.2M | 30% | High risk94 | Flagged0.018 |
| 25OB0344CONSTRUCTION OF MULTI PURPOSE BUILDING (NEAR ACTIVITY CENTER), NATIONAL CENTER FOR MENTAL HEALTH, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱19.4M | 100% | High risk92 | —-0.002 |
| 25DN0054CONSTRUCTION OF MULTIPURPOSE BUILDING AT RIZAL PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱39.1M | 41% | High risk72 | —-0.025 |
| 24DN0056BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (MULTI-PURPOSE HALL), BARANGAY SAN PEDRO ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱4.9M | 83% | High risk71 | —-0.027 |
| 24DN0018BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BLOOMINGDALE HOMES, BARANGAY SAN PEDRO ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱7.9M | 86% | High risk71 | —-0.028 |
| 25OB0133CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CONGA CREEK (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94M | 100% | High risk65 | —-0.051 |
| 22OB0158CONSTRUCTION OF SLOPE PROTECTION AT HAGONOY PUMPING STATION RETARDING POND, TAGUIG CITY (PACKAGE 3) | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.076 |
| 24OB0184CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.077 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OB0148REHABILITATION OF PULONG KENDI 1 ST., BURGOS ST. AND BONIFACIO ST. AT BARANGAY STA. ANA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱37.2M | 30% | High risk94 | Flagged0.018 |
| 25DN0063CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.7M | 28% | High risk94 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23DN0088BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SUNSTRIP GREEN VILLAGE, BARANGAY SAN ISIDRO ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱6.9M | 100% | Medium risk50 | —-0.105 |
| 27 | 22DN0156CONSTRUCTION OF TWO-STOREY EVACUATION CENTER, BARANGAY PAG-ASA BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱14.8M | 100% | Medium risk50 | —-0.103 |
| 28 | 24DN0154CONSTRUCTION OF MULTI-PURPOSE BUILDING (GREENWOODS EXEC. VILLAGE) CAINTA, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱4.9M | 93% | Medium risk50 | —-0.060 |
| 29 | 23DN0100BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING PERIMETER FENCE, BINANGONAN INTEGRATED NATIONAL HIGH SCHOOL, BARANGAY TATALA, BINANGONAN, RIZAL (FIRST DISTRICT | Region IV-A | Rizal 1st DEO | Completed | ₱9.9M | 100% | Medium risk50 | —-0.105 |
| 30 | 22OB0288REHABILITATION OF MULTI-PURPOSE BUILDING (SEN. GONZALES ACADEMIC HALL) AT RIZAL TECHNOLOGICAL UNIVERSITY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱28.5M | 100% | Medium risk50 | —-0.101 |
| 31 | 21DN0118CONSTRUCTION OF MULTI-PURPOSE BUILDING (LIVELIHOOD TRAINING CENTER), BARANGAY GULOD BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.7M | 100% | Medium risk50 | —-0.105 |
| 32 | 25OB0134CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CONGA CREEK (PHASE 4), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱48M | 100% | Medium risk50 | —-0.058 |
| 33 | 24OB0402CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES INSIDE CITY HALL COMPLEX AT BARANGAY PLAINVIEW | National Capital Region | Metro Manila 1st DEO | Completed | ₱19.3M | 100% | Medium risk49 | —-0.103 |
| 34 | 23OB0178CONSTRUCTION OF MULTI-PURPOSE BUILDING (MORTUARY) AT BARANGAY MAUWAY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱23.8M | 100% | Medium risk49 | —-0.101 |
| 35 | 22OB0043CONSTRUCTION OF MULTIPURPOSE BUILDING (RESEARCH AND DEVELOPMENT) AT BARANGAY MAUWAY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱23.5M | 100% | Medium risk49 | —-0.101 |
| 36 | 20OB0277CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PLAINVIEW, INCLUDING SITE DEVELOPMENT, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.102 |
| 37 | 20OB0282REHABILITATION OF MULTI-PURPOSE BUILDING (OLD BUILDING) AT RIZAL TECHNOLOGICAL UNIVERSITY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.102 |
| 38 | 25OB0392CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING (MORTUARY) AT BARANGAY MAUWAY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.6M | 100% | Medium risk48 | —-0.103 |
| 39 | 23OB0330CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) AT BRGY. LIGID TIPAS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.7M | 100% | Medium risk48 | —-0.103 |
| 40 | 22OB0298CONSTRUCTION OF MULTIPURPOSE BUILDING (PUBLIC ORDER & SAFETY FACILITY) AT JOSE FABELLA CENTER (DSWD-NCR) INCLUDING UPGRADING OF ELECTRICAL FACILITIES, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱15.2M | 100% | Medium risk48 | —-0.102 |
| 41 | 23OB0157CONSTRUCTION OF MULTI-PURPOSE BUILDING (CISTERN), MANDALUYONG ELEMENTARY SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.103 |
| 42 | 23OB0159CONSTRUCTION OF MULTI-PURPOSE BUILDING (CISTERN), EULOGIO RODRIGUEZ INTEGRATED SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.103 |
| 43 | 25OB0380CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND UPGRADING OF ELECTRICAL FACILITIES AT BARANGAY MABINI-J.RIZAL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.102 |
| 44 | 24OB0386CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CISTERN) INCLUDING UPGRADING OF ELECTRICAL FACILITIES AT PEDRO P. CRUZ ELEMENTARY SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱9.7M | 89% | Medium risk48 | —-0.052 |
| 45 | 22OB0272CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING AT MANDALUYONG CITY SCIENCE HIGH SCHOOL INCLUDING UPGRADING OF ELECTRICAL FACILITIES, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.3M | 100% | Medium risk48 | —-0.085 |
| 46 | 22OB0269CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT PLAINVIEW ELEMENTARY SCHOOL INCLUDING UPGRADING OF ELECTRICAL FACILITIES, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.3M | 100% | Medium risk48 | —-0.103 |
| 47 | 23OB0328CONSTRUCTION (COMPLETION) OF PATEROS SPORTS COMPLEX, BRGY. SAN PEDRO, PATEROS, METRO MANILA | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.3M | 100% | Medium risk48 | —-0.103 |
| 48 | 21OB0218CONSTRUCTION OF MULTI-PURPOSE BUILDING AT NATIONAL CENTER FOR MENTAL HEALTH, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱13.4M | 100% | Medium risk48 | —-0.103 |
| 49 | 24OB0433CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES AT SENATE PRESIDENT NEPTALI GONZALES INTEGRATED SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.103 |
| 50 | 24OB0428CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES AT ISAAC LOPEZ INTEGRATED SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.103 |