172 projects on file, including joint ventures this contractor is part of.
Total projects
172
Total budget
₱2.3B
Average progress
92.7%
Completion rate
82.0%
Average risk score
40.8
Medium risk on average, out of 100
Flagged as unusual
2
1.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 129 | ₱2B | 40.6 | 1 | 93.2% |
| Region IV-A | 41 | ₱271.9M | 41.7 | 1 | 90.9% |
| Region III | 2 | ₱4.8M | 35.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 101 | ₱1B | 40.5 | 0 | 93.6% |
| Roads | 34 | ₱235.6M | 33.7 | 0 | 92.3% |
| Flood Control and Drainage | 23 | ₱900.8M | 48.3 | 0 | 91.3% |
| Water Provision and Storage | 7 | ₱21.8M | 30.6 | 0 | 99.7% |
| OTHER | 4 | ₱43.6M | 45.7 | 0 | 100.0% |
| GAA 2025 SSP | 3 | ₱66.3M | 93.4 | 2 | 52.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0063CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.7M | 28% | High risk94 | Flagged0.013 |
| 25OB0148REHABILITATION OF PULONG KENDI 1 ST., BURGOS ST. AND BONIFACIO ST. AT BARANGAY STA. ANA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱37.2M | 30% | High risk94 | Flagged0.018 |
| 25OB0344CONSTRUCTION OF MULTI PURPOSE BUILDING (NEAR ACTIVITY CENTER), NATIONAL CENTER FOR MENTAL HEALTH, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱19.4M | 100% | High risk92 | —-0.002 |
| 25DN0054CONSTRUCTION OF MULTIPURPOSE BUILDING AT RIZAL PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱39.1M | 41% | High risk72 | —-0.025 |
| 24DN0056BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (MULTI-PURPOSE HALL), BARANGAY SAN PEDRO ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱4.9M | 83% | High risk71 | —-0.027 |
| 24DN0018BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BLOOMINGDALE HOMES, BARANGAY SAN PEDRO ANGONO, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱7.9M | 86% | High risk71 | —-0.028 |
| 25OB0133CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CONGA CREEK (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94M | 100% | High risk65 | —-0.051 |
| 22OB0158CONSTRUCTION OF SLOPE PROTECTION AT HAGONOY PUMPING STATION RETARDING POND, TAGUIG CITY (PACKAGE 3) | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.076 |
| 24OB0184CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.077 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OB0148REHABILITATION OF PULONG KENDI 1 ST., BURGOS ST. AND BONIFACIO ST. AT BARANGAY STA. ANA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱37.2M | 30% | High risk94 | Flagged0.018 |
| 25DN0063CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.7M | 28% | High risk94 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 23OB0167REHABILITATION (EXTENSION) OF MULTI PURPOSE BUILDING AT MOLAVE BARANGAY ADDITION HILLS, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱5.7M | 100% | Medium risk47 | —-0.102 |
| 77 | 22OB0258CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING AT JOSE FABELLA MEMORIAL SCHOOL BARANGAY ADDITION HILLS, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱5.7M | 100% | Medium risk47 | —-0.103 |
| 78 | 23OB0477CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), NO. 56 ML QUEZON ST., DISTRICT 1, NEW LOWER BICUTAN, TAGUIG CITY, NCR (FACILITIES TO SUPPORT SOCIAL SERVICES) | National Capital Region | Metro Manila 1st DEO | Completed | ₱38.2M | 100% | Medium risk47 | —-0.042 |
| 79 | 23OB0467CONSTRUCTION OF 7-STOREY SCHOOL BUILDING AT ANDRES BONIFACIO INTEGRATED SCHOOL, PHASE 1 (2STRY6CL) | National Capital Region | Metro Manila 1st DEO | Completed | ₱32.5M | 100% | Medium risk47 | —-0.047 |
| 80 | 20DN0134REHABILITATION OF ROADS WITH DRAINAGE SYSTEM, PUROK 4, COLLEGE VIEW PARK, BRGY. CUPANG, ANTIPOLO CITY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.105 |
| 81 | 23OE0238CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING FOR THE DSWD NATIONAL CAPITAL REGION, LEGARDA ST., MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱28.9M | 100% | Medium risk47 | —-0.048 |
| 82 | 20DN0048CONSTRUCTION OF ROAD AT YNARES AVENUE, PUROK 5 AND 6, LUPANG ARENDA, BRGY. STA. ANA, TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.104 |
| 83 | 25DN0112FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱2.5M | 100% | Medium risk47 | —-0.023 |
| 84 | 24DN0103FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF DRAINAGE AT 2ND ST., M. CRUZ TO 4TH AND 5TH ST., ROSE ANN, BARANGAY SAN ROQUE CAINTA, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱8.1M | 100% | Medium risk47 | —-0.089 |
| 85 | 21DN0115RIPRAPPING OF CREEKSIDE PALMERA I SUBDIVISION, BARANGAY SAN ISIDRO TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱10.9M | 100% | Medium risk47 | —-0.090 |
| 86 | 25DN0041CONSTRUCTION OF FLOOD CONTROL STRUCTURE, KAY MANGGA CIS, BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.4M | 0% | Medium risk47 | —-0.026 |
| 87 | 24DN0080CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CREEK AT SITIO CALVON, BARANGAY MAMBOG BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.082 |
| 88 | 23DN0095BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF CLOSE CANAL WITH GUTTER ALONG C. BOLADO AVE. (BOTH SIDES) BARANGAY TATALA BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.085 |
| 89 | 21DN0094CONSTRUCTION OF DIKE/RIVER WALL AT LAKESIDE, BARANGAY BOMBONG, BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱6.7M | 100% | Medium risk46 | —-0.090 |
| 90 | 20OB0381REHABILITATION OF ROADS, BARANGAY BAMBANG, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱27.9M | 100% | Medium risk46 | —-0.093 |
| 91 | 23OB0180REHABILITATION OF MULTI-PURPOSE BUILDING (FIRE SUBSTATION) AT BARANGAY MAUWAY, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.101 |
| 92 | 20OB0369PREVENTIVE MAINTENANCE OF ROAD IN KATIPUNAN VILLAGE, BRGY. WESTERN BICUTAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱15.8M | 100% | Medium risk46 | —-0.098 |
| 93 | 21DN0029CONSTRUCTION/REHABILITATION OF LAKESIDE ROAD, BARANGAY SAN VICENTE, ANGONO, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.108 |
| 94 | 22DN0084CONSTRUCTION OF ROAD WITH DRAINAGE BLK 1 AND BLK 5 PUROK 1 (SAMATHOA), BARANGAY STA. ANA TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | Completed | ₱10.3M | 100% | Medium risk46 | —-0.108 |
| 95 | 25OB0141CONSTRUCTION OF KATWIRAN ST., BARANGAY IBAYO - TIPAS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱18.9M | 42% | Medium risk46 | —-0.053 |
| 96 | 24OB0203REHABILITATION OF ROAD, BARANGAY HAGONOY, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱4.8M | 0% | Medium risk46 | —-0.025 |
| 97 | 20OB0315COMPLETION OF MULTI-PURPOSE BUILDING (HEALTH CENTER) AT BARANGAY LIGID TIPAS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.101 |
| 98 | 24OB0326CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG (PHASE 7) | National Capital Region | Metro Manila 1st DEO | Completed | ₱45.6M | 100% | Medium risk46 | —-0.087 |
| 99 | 24OB0199CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM, VILLA POLINTAN, BARANGAY PALINGON, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱4.8M | 100% | Medium risk46 | —-0.059 |
| 100 | 25OB0143IMPROVEMENT OF ROAD AND DRAINAGE AT BARANGAY LOWER BICUTAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱4.8M | 8% | Medium risk46 | —-0.037 |