1 project on file, including joint ventures this contractor is part of.
Total projects
1
Total budget
₱4.9M
Average progress
89.7%
Completion rate
0.0%
Below 70%
Average risk score
93.6
High risk on average, out of 100
Flagged as unusual
1
100.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 1 | ₱4.9M | 93.6 | 1 | 89.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| GAA 2025 SSP | 1 | ₱4.9M | 93.6 | 1 | 89.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NE0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OSMENA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 90% | High risk94 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NE0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OSMENA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 90% | High risk94 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25NE0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OSMENA, LIBJO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 90% | High risk94 | Flagged0.005 |