Contractor dossier
126 projects on file, including joint ventures this contractor is part of.
Total projects
126
Total budget
₱6.5B
Average progress
89.9%
Completion rate
74.6%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
11
8.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 76 | ₱3.8B | 50.3 | 5 | 91.5% |
| Region IV-A | 42 | ₱1.8B | 51.4 | 5 | 86.8% |
| Region III | 8 | ₱821M | 59.5 | 1 | 90.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 57 | ₱2.2B | 46.6 | 5 | 89.9% |
| Flood Control and Drainage | 50 | ₱3B | 53.8 | 1 | 91.4% |
| Buildings and Facilities | 8 | ₱414.2M | 53.8 | 2 | 71.5% |
| OTHER | 5 | ₱459M | 69.3 | 3 | 92.2% |
| Roads | 5 | ₱260.8M | 48.0 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱59.9M | 93.6 | 0 | 95.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OB0218RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C.P. GARCIA BR. (B01875LZ) ALONG C-5 ROAD | National Capital Region | Metro Manila 1st DEO | On-Going | ₱59.9M | 96% | High risk94 | —-0.018 |
| 23D00219REPLACEMENT OF PERMANENT WEAK BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RD | Region IV-A | Region IV-A | On-Going | ₱62.7M | 79% | High risk87 | Flagged0.048 |
| 25CD0186REPLACEMENT OF MARCOS BRIDGE (PHASE III), MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱140.4M | 30% | High risk75 | Flagged0.020 |
| 23DF0197ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD FLOOD MANAGEMENT PROGRAM CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONST OF PUMPING STATION INCLUDING DRAINAGE SYSTEM ALONG IMUS R | Region IV-A | Cavite 1st DEO | On-Going | ₱48.5M | 10% | High risk72 | Flagged0.012 |
| 18OE0269CONSTRUCTION OF FOUR (4) STOREY TWENTY EIGHT (28) CLASSROOM SCHOOL BUILDING AT MABINI ELEMENTARY SCHOOL QUIAPO, MANILA CITY (BASED ON 2017 PLAN, REVISED 3-24-17) | National Capital Region | North Manila DEO | Completed | ₱221M | 100% | High risk71 | Flagged0.052 |
| 25DN0038CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY SAN ISIDRO, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱47M | 30% | High risk71 | —-0.011 |
| 25CD0134CONSTRUCTION OF PINAGTULAYAN BRIDGE (PHASE II), NORZAGARAY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱56.2M | 96% | High risk70 | —-0.015 |
| 25DF0138CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF BYPASS ROAD (AGUINALDO HI | Region IV-A | Cavite 1st DEO | On-Going | ₱93.5M | 0% | High risk69 | Flagged0.019 |
| 24OH0055ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-CONSTRUCTION OF LOADING AND UNLOADING BAY AT ROXAS BOULEVARD CORNER EDSA, PASAY CITY PHASE II | National Capital Region | South Manila DEO | On-Going | ₱94.5M | 82% | High risk68 | Flagged0.006 |
| 25OE0178CONSTRUCTION OF RETARDING BASIN AT ESTERO DE QUIAPO (PHASE II), MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱141.1M | 49% | High risk68 | —-0.027 |
| 25OE0061CONSTRUCTION OF RETARDING BASIN AT ESTERO DE MAGDALENA, PHASE I, TONDO, MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱141.8M | 83% | High risk67 | —-0.034 |
| 24D00018CONSTRUCTION OF BY-PASS AND DIVERSION ROADSBACOOR DIVERSION ROAD, PACKAGE A, CAVITE | Region IV-A | Region IV-A | On-Going | ₱142.1M | 78% | High risk67 | —-0.005 |
| 23D00134CONSTRUCTION OF MALAGASANG FLYOVER, IMUS CITY, CAVITE | Region IV-A | Region IV-A | On-Going | ₱149.6M | 70% | High risk67 | Flagged0.002 |
| 24OE0012CONSTRUCTION OF RETARDING BASIN AT ESTERO DELA REINA (PHASE XXII), TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱144.7M | 100% | High risk67 | —-0.062 |
| 25OE0188REHABILITATION OF DRAINAGE SYSTEM ALONG DAPITAN ST. MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱94.7M | 28% | High risk65 | —-0.031 |
| 23OE0199CONSTRUCTION OF RETENTION BASIN AT ESTERO DELA REINA (PHASE XV), TONDO, MANILA | National Capital Region | North Manila DEO | Completed | ₱94.8M | 100% | High risk65 | —-0.066 |
| 18OE0106ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF VALENCIA PUMPING STATION RETARDING BASIN, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱96.1M | 100% | High risk65 | —-0.069 |
| 22D00091CONSTRUCTION OF MALAGASANG FLYOVER AT MALAGASANG SEGMENT 1, IMUS CITY | Region IV-A | Region IV-A | Completed | ₱119.2M | 100% | High risk65 | —-0.049 |
| 25OE0053REHABILITATION OF DRAINAGE ALONG ZONE 58 - 67, MANILA CITY (PHASE V) | National Capital Region | North Manila DEO | On-Going | ₱103.9M | 43% | High risk64 | —-0.035 |
| 24OE0028REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - LEGARDA FLY - OVER (B03350LZ) ALONG LEGARDA FLYOVER | National Capital Region | North Manila DEO | Completed | ₱115M | 100% | High risk64 | —-0.052 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18OE0269CONSTRUCTION OF FOUR (4) STOREY TWENTY EIGHT (28) CLASSROOM SCHOOL BUILDING AT MABINI ELEMENTARY SCHOOL QUIAPO, MANILA CITY (BASED ON 2017 PLAN, REVISED 3-24-17) | National Capital Region | North Manila DEO | Completed | ₱221M | 100% | High risk71 | Flagged0.052 |
| 23D00219REPLACEMENT OF PERMANENT WEAK BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RD | Region IV-A | Region IV-A | On-Going | ₱62.7M | 79% | High risk87 | Flagged0.048 |
| 22OG0140COMPLETION OF PROPOSED CONSTRUCTION OF THE UNIVERSITY OF THE PHILIPPINES DILIMAN SWIMMING POOL AND STADIUM, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱62.8M | 0% | Medium risk56 | Flagged0.033 |
| 21OG0149PROPOSED CONSTRUCTION OF THE UNIVERSITY OF THE PHILIPPINES DILIMAN SWIMMING POOL AND STADIUM, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱84.5M | 25% | Medium risk56 | Flagged0.031 |
| 25CD0186REPLACEMENT OF MARCOS BRIDGE (PHASE III), MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱140.4M | 30% | High risk75 | Flagged0.020 |
| 25DF0138CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF BYPASS ROAD (AGUINALDO HI | Region IV-A | Cavite 1st DEO | On-Going | ₱93.5M | 0% | High risk69 | Flagged0.019 |
| 23DF0197ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD FLOOD MANAGEMENT PROGRAM CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONST OF PUMPING STATION INCLUDING DRAINAGE SYSTEM ALONG IMUS R | Region IV-A | Cavite 1st DEO | On-Going | ₱48.5M | 10% | High risk72 | Flagged0.012 |
| 24OH0055ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-CONSTRUCTION OF LOADING AND UNLOADING BAY AT ROXAS BOULEVARD CORNER EDSA, PASAY CITY PHASE II | National Capital Region | South Manila DEO | On-Going | ₱94.5M | 82% | High risk68 | Flagged0.006 |
| 24OE0027REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - DIMASALANG BR. (B01820LZ) ALONG DIMASALANG ST | National Capital Region | North Manila DEO | On-Going | ₱66M | 0% | Medium risk55 | Flagged0.003 |
| 23D00134CONSTRUCTION OF MALAGASANG FLYOVER, IMUS CITY, CAVITE | Region IV-A | Region IV-A | On-Going | ₱149.6M | 70% | High risk67 | Flagged0.002 |
| 24D00099FY 2024 DPWH INFRASTRUCTURE PROGRAM -ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - CALAMBA OVERPASS (B03132LZ) ALONG MANILA SOUTH ROAD | Region IV-A | Region IV-A | On-Going | ₱41.2M | 46% | Medium risk58 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23OH0051ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-IMPROVEMENT OF HARBOR VIEW PUMPING STATION, SOUTH DR. ERMITA, MANILA CITY PHASE 2 | National Capital Region | South Manila DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.077 |
| 27 | 16OE0105MFO 2-FLOOD MANAGEMENT SERVICES-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF RIVERWALL, ESTERO DE MAYPAJO (HERMOSA SECTION) TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | High risk63 | —-0.041 |
| 28 | 23OH0092ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS-CONSTRUCTION OF LOADING AND UNLOADING BAY AT ROXAS BOULEVARD, CORNER EDSA, PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱96.4M | 100% | High risk61 | —-0.082 |
| 29 | 23DF0108CONVERGENCE & SPECIAL SUPPORT PROGRAM SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG) ACCESS ROADS &/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES CONST. OF CAVITEX-COVELANDIA RD, BRGY. BINAKAYAN, KAWIT | Region IV-A | Cavite 1st DEO | Completed | ₱106.2M | 100% | High risk60 | —-0.093 |
| 30 | 24CD0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 00+208 STA. 00+312, (TAWIRAN PALIWAS SECTION), OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱144.7M | 100% | High risk60 | —-0.067 |
| 31 | 24CD0048CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 00+312 STA. 00+416, (TAWIRAN PALIWAS SECTION), OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱144.7M | 100% | High risk60 | —-0.068 |
| 32 | 24D00099FY 2024 DPWH INFRASTRUCTURE PROGRAM -ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - CALAMBA OVERPASS (B03132LZ) ALONG MANILA SOUTH ROAD | Region IV-A | Region IV-A | On-Going | ₱41.2M | 46% | Medium risk58 | Flagged0.000 |
| 33 | 21OH0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTOR SYSTEM/WATER SUPPLY SYSTEM-CONSTRUCTION OF WATERLINE DISTRIBUTION SYSTEM,COLONEL JESUS VILLAMOR AIRBASE (CJVAB), PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱31.8M | 100% | Medium risk58 | —-0.042 |
| 34 | 22OG0093CONSTRUCTION OF PERIMETER WALL, CAMP GENERAL EMILIO AGUINALDO, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱77.2M | 100% | Medium risk58 | —-0.081 |
| 35 | 24CD0105REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, BARANGAY TAWIRAN TO WAWANG PULO, STA. 02+106 STA. 02+231, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.079 |
| 36 | 24CD0046REPLACEMENT OF MARCOS BRIDGE (PHASE II), MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱95M | 100% | Medium risk57 | —-0.054 |
| 37 | 23OE0237CONSTRUCTION OF DRAINAGE SYSTEM ALONG S.H. LOYOLA ST. CROSSING A.H. LACSON AVE., BARANGAY 460 AND 461 ZONE 45, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱48.2M | 100% | Medium risk56 | —-0.028 |
| 38 | 23OE0239REHABILITATION OF DRAINAGE SYSTEM ALONG T. ALONZO ST., BARANGAY 299, 313 AND 314 ZONE 29 AND 31, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱48.2M | 100% | Medium risk56 | —-0.029 |
| 39 | 21OG0149PROPOSED CONSTRUCTION OF THE UNIVERSITY OF THE PHILIPPINES DILIMAN SWIMMING POOL AND STADIUM, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱84.5M | 25% | Medium risk56 | Flagged0.031 |
| 40 | 22CD0044REPLACEMENT OF MARCOS BRIDGE, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱95.2M | 100% | Medium risk56 | —-0.054 |
| 41 | 22OG0140COMPLETION OF PROPOSED CONSTRUCTION OF THE UNIVERSITY OF THE PHILIPPINES DILIMAN SWIMMING POOL AND STADIUM, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱62.8M | 0% | Medium risk56 | Flagged0.033 |
| 42 | 23DN0046CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, HALANG CREEK TO MUNTINDILAW RIVER, ALONG MARIKINA DIVERSION ROAD TO MARIKINA-INFANTA ROAD (PHASE 4), ANTIPOLO CITY (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱91.7M | 94% | Medium risk55 | —-0.024 |
| 43 | 23OE0227REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - VELASQUEZ INFANTA BRIDGE ALONG VELASQUEZ ST., TONDO, MANILA | National Capital Region | North Manila DEO | Completed | ₱67.5M | 100% | Medium risk55 | —-0.058 |
| 44 | 24OE0027REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - DIMASALANG BR. (B01820LZ) ALONG DIMASALANG ST | National Capital Region | North Manila DEO | On-Going | ₱66M | 0% | Medium risk55 | Flagged0.003 |
| 45 | 22OE0014REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - NAGTAHAN FLY-OVER (B03338LZ) ALONG NAGTAHAN BRIDGE / FLY-OVER | National Capital Region | North Manila DEO | Completed | ₱71.4M | 100% | Medium risk55 | —-0.059 |
| 46 | 25OE0164CONSTRUCTION OF DPWH NORTH MANILA DISTRICT ENGINEERING OFFICE (PHASE IV) (COMPLETION), MANILA | National Capital Region | North Manila DEO | On-Going | ₱48M | 47% | Medium risk55 | —-0.047 |
| 47 | 24D00193CONSTRUCTION OF LUKUTANG MALAKI BRIDGE 2, MONTALBAN, RIZAL | Region IV-A | Region IV-A | On-Going | ₱57.9M | 67% | Medium risk54 | —-0.023 |
| 48 | 23OE0148CONSTRUCTION (COMPLETION) OF DPWH NORTH MANILA DISTRICT ENGINEERING OFFICE (PERMANENT OFFICE), MANILA CITY, PHASE II | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk54 | —-0.097 |
| 49 | 22OE0124CONSTRUCTION (COMPLETION) OF DPWH NORTH MANILA DISTRICT ENGINEERING OFFICE (PERMANENT OFFICE), MANILA CITY, PHASE II | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk54 | —-0.098 |
| 50 | 17DN0087CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES BILIBIRAN BRIDGE (B02842LZ) ALONG MANILA EAST ROAD, BINANGONAN, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.6M | 100% | Medium risk54 | —-0.039 |