Contractor dossier
60 projects on file, including joint ventures this contractor is part of.
Total projects
60
Total budget
₱2.4B
Average progress
85.3%
Completion rate
73.3%
Average risk score
52.8
Medium risk on average, out of 100
Flagged as unusual
6
10.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 59 | ₱2.2B | 52.5 | 5 | 86.6% |
| Region IV-B | 1 | ₱232.9M | 68.3 | 1 | 6.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 34 | ₱620M | 47.1 | 2 | 89.7% |
| Buildings and Facilities | 10 | ₱526.4M | 58.9 | 1 | 70.9% |
| Flood Control and Drainage | 8 | ₱225.4M | 49.3 | 0 | 89.0% |
| OTHER | 3 | ₱769.7M | 82.1 | 2 | 68.1% |
| Bridges | 3 | ₱48.1M | 48.6 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱220.2M | 93.5 | 1 | 70.7% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IC0047CONSTRUCTION OF FLOOD CONTROL ALONG BINAHAAN RIVER, BARANGAY TACURANGA, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱96.5M | 94% | High risk94 | —-0.007 |
| 25I00163CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE | Region VIII | Region VIII | On-Going | ₱123.7M | 47% | High risk93 | Flagged0.005 |
| 24I00395SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱482.2M | 24% | High risk84 | Flagged0.046 |
| 23I00128CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2 | Region VIII | Region VIII | On-Going | ₱277.7M | 81% | High risk84 | Flagged0.044 |
| 24IC0069SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - IMPROVEMENT OF INTERSECTION - GOVERNMENT CENTER ROAD NETWORK (S00047LT) - K0913+490 AND GUINDAPUNAN-BARAS-CANDAHUG ROAD, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱9.8M | 100% | High risk78 | —-0.008 |
| 25I00196CLUSTER 2: 1. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF 4-STOREY DPWH REGIONAL OFFICE VIII BUILDING, PAWING, PALO, LEYTE; 2. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUI | Region VIII | Region VIII | On-Going | ₱117.8M | 0% | High risk77 | Flagged0.010 |
| 25E00256SUISTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-- CONST. OF CABIGAAN-APURAWAN CROSS COUNTRY ROAD PACKAGE A, STA. 3+000.00-STA. 4+160.00, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.9M | 7% | High risk68 | Flagged0.039 |
| 23IM0078CONSTRUCTION OF MULTI-PURPOSE BUILDING, ABUCAY NEW BUS TERMINAL ANNEX BUILDING, BRGY. ABUCAY, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱129M | 59% | High risk67 | —-0.010 |
| 25I00150CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), RIZAL RIVER, BABATNGON, LEYTE | Region VIII | Region VIII | On-Going | ₱123.5M | 12% | High risk65 | —-0.003 |
| 24IM0103REHABILITATION OF MULTI-PURPOSE BUILDING, ABUCAY OLD ANNEX BUILDING, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱79.1M | 50% | High risk63 | —-0.030 |
| 22I00084CONSTRUCTION OF THREE STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, BRGY. PAWING, PALO, LEYTE | Region VIII | Region VIII | Completed | ₱57.9M | 100% | High risk62 | —-0.089 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IC0199CONCRETING OF BRGY. LINAO TO BRGY. COGON TO BRGY. TALOLORA FMR, BRGYS. LINAO, BANGON AND TALOLORA, TANAUAN, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱16.9M | 0% | Medium risk59 | Flagged0.050 |
| 24I00395SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱482.2M | 24% | High risk84 | Flagged0.046 |
| 23I00128CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2 | Region VIII | Region VIII | On-Going | ₱277.7M | 81% | High risk84 | Flagged0.044 |
| 25E00256SUISTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-- CONST. OF CABIGAAN-APURAWAN CROSS COUNTRY ROAD PACKAGE A, STA. 3+000.00-STA. 4+160.00, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.9M | 7% | High risk68 | Flagged0.039 |
| 25I00196CLUSTER 2: 1. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF 4-STOREY DPWH REGIONAL OFFICE VIII BUILDING, PAWING, PALO, LEYTE; 2. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUI | Region VIII | Region VIII | On-Going | ₱117.8M | 0% | High risk77 | Flagged0.010 |
| 25I00163CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE | Region VIII | Region VIII | On-Going | ₱123.7M | 47% | High risk93 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 24IC0051CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DRAINAGE SYSTEM), PHASE 1, BARANGAY CANHIDOC, PALO, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱19.8M | 100% | Medium risk47 | —-0.080 |
| 52 | 23IM0029CONSTRUCTION OF DRAINAGE SYSTEM ALONG ATHLETIC ROAD, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱8.9M | 100% | Medium risk47 | —-0.077 |
| 53 | 23IM0028CONSTRUCTION OF DRAINAGE SYSTEM FROM DAANG MAHARLIKA ROAD TO TANGHAS LIRANG CREEK, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.078 |
| 54 | 24IC0032CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DRAINAGE CANAL), ZONE 2, BRGY. CAPANGIHAN, TOLOSA, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱9.9M | 100% | Medium risk47 | —-0.078 |
| 55 | 23IM0020CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - GOV BENJAMIN KOKOY T ROMUALDEZ DIV RD K0908+(-432) | Region VIII | Tacloban City DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.096 |
| 56 | 21IM0003CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD, TACLOBAN BAYBAY SOUTH ROAD-K0911+000-K0911+185 | Region VIII | Tacloban City DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.095 |
| 57 | 21IM0053PREVENTIVE MAINTENANCE - GOV. BENJAMIN KOKOY ROMUALDEZ DIVERSION ROAD (S00255LT) K0908+265-K0908+472, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.091 |
| 58 | 19IM0001PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-RIZAL AVENIDA EXT. RD. (S00006LT) CHAINAGE 000-CHAINAGE 110, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱2.6M | 100% | Low risk24 | —-0.090 |
| 59 | 22IM0056OFF-CARRIAGEWAY IMPROVEMENT - DAANG MAHARLIKA (LT) - K0906+207 | Region VIII | Tacloban City DEO | Completed | ₱4.4M | 100% | Low risk24 | —-0.095 |
| 60 | 22IM0044OFF-CARRIAGEWAY IMPROVEMENT - DAANG MAHARLIKA (LT) - K0905+406 | Region VIII | Tacloban City DEO | Completed | ₱2.9M | 100% | Low risk24 | —-0.095 |