29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱696.5M
Average progress
98.1%
Completion rate
96.6%
Average risk score
25.9
Low risk on average, out of 100
Flagged as unusual
1
3.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 29 | ₱696.5M | 25.9 | 1 | 98.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 16 | ₱426.6M | 25.1 | 0 | 100.0% |
| Buildings and Facilities | 7 | ₱18.9M | 8.2 | 0 | 100.0% |
| OTHER | 2 | ₱164.7M | 75.0 | 1 | 71.9% |
| Flood Control and Drainage | 2 | ₱77.7M | 24.3 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 82.8 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱3.6M | 11.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MG0101CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | High risk83 | —-0.020 |
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 24MG0107CONSTRUCTION OF UPPER MOLOY ROAD, BARANGAY MOLOY, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱29.2M | 100% | High risk74 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25MG0101CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | High risk83 | —-0.020 |
| 2 | 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 3 | 24MG0107CONSTRUCTION OF UPPER MOLOY ROAD, BARANGAY MOLOY, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱29.2M | 100% | High risk74 | —-0.032 |
| 4 | 23M00087CONSTRUCTION OF CONCRETE ROAD - NRJ TO SITIO SEWAL LEADING TO LAGBASAN CAVE PASSING THRU BURIAL CAVE, STA. 7+503-STA. 9+583, BRGY. KUDEN, SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱122.1M | 100% | Medium risk47 | —-0.072 |
| 5 | 22MG0026ROAD WIDENING-ALONG COTABATO-MARBEL RD (S00276MN) K1753+000-K1754+495 | Region XII | South Cotabato 2nd DEO | Completed | ₱38.2M | 100% | Low risk29 | —-0.087 |
| 6 | 21MG0091CONSTRUCTION OF CONCRETE ROAD-ROAD FROM JUNCTION LAKE SEBU TO VILLA ELLAGA-LAMBUSONG ROAD LINKING PROVINCIAL ROAD IN SUPPORT OF PINEAPPLE, PALM OIL, CORN,BANANA, CASSAVA AND SUGARCANE AT BARANGAY COLONGULO TO PACKAGING AND PROCESSING CENTERS, SURALLAH, SO | Region XII | South Cotabato 2nd DEO | Completed | ₱40.1M | 100% | Low risk27 | —-0.088 |
| 7 | 22MG0001CLUSTER I-CONSTRUCTION OF CONCRETE ROAD A.JCT. SURALLAH-LAKE SEBU ROAD LEADING TO NV VOGT SOLAR POWER PLANT, BRGY. CENTRALA, SURALLAH,SOUTH COTABATO B.BRGY. SAN JOSE PROPER-SITIO BOUNDARY-PUROK APOSTOL-TINAGO ROAD IN SUPPORT OF AGRI-PROCESSING ACTIVITIES | Region XII | South Cotabato 2nd DEO | Completed | ₱43.8M | 100% | Low risk27 | —-0.088 |
| 8 | 19MG0090CONCRETING OF ROAD AT BALMORES STREET TO NATIONAL HIGHWAY, BRGY. MORALES, KORONADAL CITY | Region XII | South Cotabato 2nd DEO | Completed | ₱29M | 100% | Low risk26 | —-0.088 |
| 9 | 20MG0125CONSTRUCTION/IMPROVEMENT OF SURALLAH-LAKE SEBU-MAITUM ROAD BETWEEN KOLONBONG BRIDGE AND DATAL LAWA BRIDGE, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱9.7M | 100% | Low risk26 | —-0.089 |
| 10 | 25MG0024CONSTRUCTION OF CONCRETE ROAD, JCT. NATIONAL HIGHWAY, SURALLAH-LAKE SEBU-MAITUM ROAD, TO UBO ELEMENTARY SCHOOL BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱19.2M | 100% | Low risk26 | —-0.089 |
| 11 | 20MG0126CONCRETING OF LOCAL ROAD AT SITIO LUBOL, UPPER SEPAKA, SURALLA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk26 | —-0.087 |
| 12 | 24MG0101CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD-SURALLAH-LAKE SEBU-MAITUM RD-K1758+105-K1758+312,K1758+324-K1758+800,K1758+801.50-K1758+824,K1758+839-K1759+172 | Region XII | South Cotabato 2nd DEO | Completed | ₱15.8M | 100% | Low risk26 | —-0.089 |
| 13 | 20MG0047CONSTRUCTION OF CONCRETE ROAD-ROAD FROM JUNCTION LAKE SEBU TO VILLA ELLAGA-LAMBUSONG ROAD LINKING PROVINCIAL ROAD IN SUPPORT OF PINEAPPLE, PALM OIL, CORN, BANANA, CASSAVA AND SUGARCANE AT BARANGAY COLONGULO TO PACKAGING AND PROCESSING CENTERS, SURALLAH, | Region XII | South Cotabato 2nd DEO | Completed | ₱14.7M | 100% | Low risk26 | —-0.089 |
| 14 | 22MG0012CONSTRUCTION OF RIVER BANK PROTECTION ALONG SAFALI RIVER, BRGY. NACI, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱44.1M | 100% | Low risk24 | —-0.075 |
| 15 | 25MG0047CONSTRUCTION OF RIVERBANK PROTECTION ALONG ALA RIVER, BARANGAY NEW PANAY, STO. NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱33.6M | 100% | Low risk24 | —-0.076 |
| 16 | 21MG0139CONCRETING OF BRGY. UPPER SEPAKA PROPER TO SITIO LUBOL FMR, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱39.8M | 100% | Low risk24 | —-0.026 |
| 17 | 24MH0102CONCRETING OF BALUAN NATIONAL HIGH SCHOOL TO PUROK 5, BRGY. BALUAN FMR, BRGY. BALUAN, PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱14.9M | 100% | Low risk22 | —-0.035 |
| 18 | 24MG0120CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ZONE 3, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk20 | —-0.087 |
| 19 | 21MG0089CONCRETING OF PUROK BALITE TO CROSSING BUNGOT, BRGY. SAN JOSE FMR, BRGY. SAN JOSE, NORALA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱11.9M | 100% | Low risk20 | —-0.033 |
| 20 | 24MG0118CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SANTA CRUZ, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk20 | —-0.086 |
| 21 | 20MG0150CONCRETING OF BRGY. LAMLAHAK TO BRGY. LAMDALAG FMR, BRGY. LAMLAHAK AND BRGY. LAMDALAG, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱12.9M | 100% | Low risk20 | —-0.034 |
| 22 | 18MG0216CONCRETING OF LAKE SELOTON FMR (FROM ALO STEEL BRIDGE APPROACH), BRGY. SELOTON, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk19 | —-0.033 |
| 23 | 20MG0145CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-RAIN WATER COLLECTOR IN PUBLIC FACILITIES, EIGHTEEN (18) UNITS | Region XII | South Cotabato 2nd DEO | Completed | ₱3.6M | 100% | Low risk12 | —-0.050 |
| 24 | 19MG0176CONSTRUCTION OF FARM TO MARKET ROAD AT SITIO LUBOL, UPPER SEPAKA, SURALLA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.7M | 100% | Low risk11 | —-0.034 |
| 25 | 18MG0235CONSTRUCTION OF MONGOCAYO BHS WITH BIRTHING FACILITY, BRGY. MONGOCAYO, T'BOLI, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2M | 100% | Low risk4 | —-0.040 |