Contractor dossier
60 projects on file, including joint ventures this contractor is part of.
Total projects
60
Total budget
₱890.9M
Average progress
75.5%
Completion rate
40.0%
Below 70%
Average risk score
58.2
Medium risk on average, out of 100
Flagged as unusual
8
13.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 56 | ₱823.5M | 57.4 | 6 | 76.3% |
| Region II | 3 | ₱61.8M | 62.2 | 2 | 51.6% |
| Cordillera Administrative Region | 1 | ₱5.7M | 89.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 34 | ₱508.3M | 55.6 | 5 | 79.5% |
| Buildings and Facilities | 16 | ₱233.8M | 52.5 | 0 | 68.9% |
| GAA 2025 OO-1 | 5 | ₱59.6M | 89.1 | 1 | 82.1% |
| GAA 2025 SSP | 2 | ₱22.4M | 93.2 | 1 | 56.8% |
| Bridges | 2 | ₱47.5M | 48.6 | 1 | 50.3% |
| Flood Control and Drainage | 1 | ₱19.3M | 30.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CN0058CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), MUCDOL ELEMENTARY SCHOOL, BARANGAY MUCDOL, DIPACULAO, AURORA | Region III | Aurora DEO | On-Going | ₱6.8M | 100% | High risk94 | —-0.006 |
| 25CL0106CONSTRUCTION OF MULTI-PURPOSE BLDG., LIBABA, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱15.6M | 14% | High risk93 | Flagged0.026 |
| 25CN0018NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, A. CASTAÑEDA - MA AURORA - SN LUIS RD K0220+080.00 - K0220+411.00 K0222+850.00 - K0223+553.00 K0223+705.00 - K0223+727.00 K0224+380.00 - K0224+509.00 K0224+758.00 - K0224+900.0... | Region III | Aurora DEO | On-Going | ₱16.4M | 98% | High risk90 | —-0.013 |
| 25B00097OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BANGAN BR.2 (B04426LZ) ALONG MANILA NORTH RD | Region II | Region II | On-Going | ₱14.2M | 54% | High risk90 | Flagged0.009 |
| 25PB0022ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, BULUAN BR. (B02243LZ) ALONG CONNER-KABUGAO RD | Cordillera Administrative Region | Apayao 1st DEO | On-Going | ₱5.7M | 100% | High risk89 | —-0.005 |
| 25CN0013REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, MADELLA - DINADIAWAN RD, K0411 + 050 - K0411 + 070, K0419 + 500 - K0419 + 515, K0419 + 731 - K0419 + 749, K0420 + 000 - K0420 + 030, K0422 + 920 - K0422 .. | Region III | Aurora DEO | On-Going | ₱12M | 77% | High risk89 | —-0.005 |
| 25CN0012REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, BALER - CASIGURAN RD (BALER - DINADIAWAN), K0249 + 590 - K0249 + 690, K0249 + 830 - K0249 + 860 | Region III | Aurora DEO | On-Going | ₱11.3M | 81% | High risk89 | —-0.007 |
| 25CL0240IMPROVEMENT OF BANOWA TAMO, BOTOLAN PUBLIC MARKET, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱29M | 0% | High risk74 | —-0.004 |
| 25CL0198REPAIR / IMPROVEMENT OF BULWAGAN NG KATARUNGAN, BALILI, BARANGAY PALANGINAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱29.3M | 62% | High risk73 | —-0.020 |
| 25CL0249CONSTRUCTION OF MULTI-PURPOSE BUILDING, ZONE 5, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱7.8M | 0% | High risk72 | —-0.006 |
| 25CL0114CONSTRUCTION OF MULTI-PURPOSE BUILDING, BABUYAN INTEGRATED SCHOOL, BARANGAY BABUYAN, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱17.6M | 100% | High risk71 | —-0.037 |
| 25CL0143CONSTRUCTION OF MULTI-PURPOSE BUILDING, AT LIBERTADOR IS, BRGY. LIBERTADOR, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱23.5M | 40% | High risk71 | —-0.015 |
| 25CL0098CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LOCLOC, PALAUIG, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱15.7M | 0% | High risk71 | —-0.005 |
| 25CL0122CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABALONG, SANTA CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱7.8M | 100% | High risk71 | —-0.038 |
| 25CL0009CONSTRUCTION OF ROAD, PUROK 3A, BARANGAY ALUSIIS, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱4.9M | 100% | High risk70 | —-0.039 |
| 24CL0195IMPROVEMENT OF LONGOS ROAD (PAMALENGPENGAN), CABANGAN, ZAMBALES (PHASE 2) | Region III | Zambales 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.060 |
| 23CL0159CONCRETING OF FELIX ROAD, BRGY. SAN ISIDRO, CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱23.6M | 100% | High risk69 | Flagged0.031 |
| 25CL0177CONCRETING OF SITIO OLPOY FMR, BRGY. AMUNGAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱29.5M | 0% | High risk69 | Flagged0.043 |
| 25CL0208CONCRETING OF ALLEY ROAD INCLUDING DRAINAGE, BRGY. BANCAL, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱4.9M | 0% | High risk69 | —-0.010 |
| 25CL0135CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱19.4M | 15% | High risk69 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CL0203CONCRETING OF SITIO SAN JUAN, BRGY. MALABON FMR, BRGY. MALABON, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱14.5M | 0% | High risk67 | Flagged0.047 |
| 25CL0179CONCRETING OF BRGY. GUISGUIS FMR, BRGY. GUISGUIS, STA. CRUZ, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱24.6M | 0% | High risk67 | Flagged0.044 |
| 25CL0177CONCRETING OF SITIO OLPOY FMR, BRGY. AMUNGAN, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱29.5M | 0% | High risk69 | Flagged0.043 |
| 23CL0159CONCRETING OF FELIX ROAD, BRGY. SAN ISIDRO, CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱23.6M | 100% | High risk69 | Flagged0.031 |
| 25CL0106CONSTRUCTION OF MULTI-PURPOSE BLDG., LIBABA, IBA, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱15.6M | 14% | High risk93 | Flagged0.026 |
| 24CL0200CONCRETING OF BRGY. TAUGTOG TO BRGY. TAMPO FMR, BRGY. TAUGTOG AND BRGY. TAMPO, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱14.5M | 100% | High risk69 | Flagged0.021 |
| 25B00097OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BANGAN BR.2 (B04426LZ) ALONG MANILA NORTH RD | Region II | Region II | On-Going | ₱14.2M | 54% | High risk90 | Flagged0.009 |
| 25B00091OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - CARORONAN BR. (B04773LZ) ALONG MANILA NORTH RD | Region II | Region II | On-Going | ₱22.1M | 1% | Medium risk49 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 23CL0140CONSTRUCTION OF DR. FLORENTINO DOBLE MEMORIAL HOSPITAL, PHASE 4, BRGY. TAUGTOG, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱19.6M | 100% | Medium risk35 | —-0.095 |
| 52 | 23CL0111CONSTRUCTION OF STO. ROSARIO COVERED COURT, BRGY. STO. ROSARIO, IBA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.6M | 100% | Medium risk33 | —-0.096 |
| 53 | 23CL0139CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN'S OFFICE), BRGY. PAMONORAN, STA. CRUZ, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.094 |
| 54 | 23CL0088CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT DR. FLORENTINO DOBLE MEMORIAL HOSPITAL, BARANGAY TAUGTOG, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.8M | 100% | Medium risk33 | —-0.097 |
| 55 | 23CL0147CONSTRUCTION OF FISHERMAN'S WHARF/CAUSEWAY, BRGY. SAN SALVADOR, MASINLOC, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱9.6M | 0% | Medium risk33 | —-0.026 |
| 56 | 23CL0110CONSTRUCTION OF ROADS, BRGY. MALOMA, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱9.6M | 100% | Medium risk32 | —-0.097 |
| 57 | 23CL0132CONSTRUCTION OF ROAD AT PUROK 3, (TONGSON AREA) LUCAPON NORTH, STA. CRUZ, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱5.9M | 100% | Medium risk31 | —-0.093 |
| 58 | 23CL0131CONSTRUCTION OF DRAINAGE SYSTEM, MAESTRE ST., BRGY. POBLACION, STA. CRUZ, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱19.3M | 100% | Medium risk31 | —-0.082 |
| 59 | 25CN0010ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, MADELLA - DINADIAWAN RD, K0409 + 303 - K0409 + 309, K0409 + 352 - K0409 + 358, K0411 + 076 - K0411 + 094, K0413 + 060 - K0413 + 114, ........... | Region III | Aurora DEO | On-Going | ₱4M | 92% | Low risk26 | —-0.069 |
| 60 | 25CN0016NETWORK DEVELOPMENT PROGRAM, OFF - CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS, MADDELA - DINADIAWAN RD, K0413 + 054 - K0413 + 149, K0418 + 700 - K0418 + 720, K0418 + 800 - K0418 + 848, K0419 + 727 - K0419 + 742, K0421 + 230 - K0421 + 248, K0421 + 788.... | Region III | Aurora DEO | On-Going | ₱1.3M | 100% | Low risk25 | —-0.072 |