Contractor dossier
44 projects on file, including joint ventures this contractor is part of.
Total projects
44
Total budget
₱3.9B
Average progress
76.6%
Completion rate
56.8%
Below 70%
Average risk score
56.1
Medium risk on average, out of 100
Flagged as unusual
5
11.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 34 | ₱1.7B | 53.1 | 3 | 80.0% |
| Region IV-B | 10 | ₱2.2B | 66.4 | 2 | 65.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 22 | ₱1.8B | 52.4 | 0 | 78.6% |
| Flood Control and Drainage | 14 | ₱1.8B | 62.8 | 2 | 67.0% |
| Buildings and Facilities | 4 | ₱161M | 52.7 | 0 | 75.3% |
| OTHER | 3 | ₱120.6M | 60.3 | 3 | 100.0% |
| Bridges | 1 | ₱18.7M | 46.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25E00157CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.2M | 0% | High risk79 | Flagged0.035 |
| 25E00158CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231M | 0% | High risk79 | Flagged0.035 |
| 24E00015FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES ALONG ABRA DE ILOG RIVER, CABACAO SECTION, ABRA DE ILOG, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk68 | —-0.037 |
| 24E00017FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION, ARMADO, ABRA DE ILOG, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk68 | —-0.037 |
| 25OH0083CONSTRUCTION OF BOOSTER PUMPING STATION ALONG ESTERO DE PANDACAN, PACKAGE 2B, MANILA CITY | National Capital Region | South Manila DEO | On-Going | ₱142.8M | 34% | High risk68 | —-0.022 |
| 24E00010FLOOD MANAGEMENT PROGRAM- CONSTRUCTION OF NAGAPI RIVERBANK PROTECTION WORKS ALONG NAGAPI RIVER (UPSTREAM RIGHTSIDE), SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk67 | —-0.042 |
| 25OE0052REHABILITATION OF DRAINAGE ALONG ZONE 58 - 67, MANILA CITY (PHASE IV) | National Capital Region | North Manila DEO | On-Going | ₱93.9M | 16% | High risk65 | —-0.025 |
| 24OE0003INSTALLATION OF BOOSTER PUMP ALONG ESTERO DELA REINA, BARANGAY 9, (PHASE VI) TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.078 |
| 24OE0031INSTALLATION OF BOOSTER PUMP ALONG ESTERO DELA REINA, BARANGAY 9, (PHASE VII) TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱95.3M | 100% | High risk65 | —-0.078 |
| 24OE0009CONSTRUCTION OF PUMPING STATION ALONG ESTERO DE SAN MIGUEL (EARNSHAW DRAINAGE MAIN OUTFALL) | National Capital Region | North Manila DEO | On-Going | ₱96.5M | 88% | High risk64 | —-0.034 |
| 25E00280SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. TAMBONG, STA. 000=000-STA. 000+332.94, GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.2M | 25% | High risk63 | —-0.016 |
| 25E00276SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. PROPER, STA. 000+000-STA. 000+368.64, BANSUD, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.5M | 25% | High risk63 | —-0.016 |
| 24E00027SPECIAL ROAD FUND MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG MINDORO WEST COASTAL ROAD, K0353+000-K0369+000 (INTERMITTENT SECTIONS), OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk63 | —-0.053 |
| 22OE0167CONSTRUCTION OF MULTI-PURPOSE BUILDING NORTH CEMETERY COLUMBARIUM, MANILA | National Capital Region | North Manila DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.080 |
| 24E00119ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE- SECONDARY ROADS- MOGPOG-BALANACAN PORT OAD- K0012+763=-K0013+500 (INTERMITTENT SECTIONS), MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱289.5M | 100% | High risk62 | —-0.049 |
| 25OF0138REHABILITATION OF ROAD ALONG BARANGAY GULOD, PACKAGE 1A, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱94.6M | 29% | High risk62 | —-0.039 |
| 24OE0220REHABILITATION OF ROAD WITH DRAINAGE ALONG RODRIGUEZ ST., TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱43.4M | 100% | High risk61 | Flagged0.014 |
| 24OE0226REHABILITATION OF ROAD WITH DRAINAGE ALONG MINDANAO ST., SAMPALOC, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱38.6M | 100% | High risk61 | Flagged0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25E00157CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.2M | 0% | High risk79 | Flagged0.035 |
| 25E00158CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231M | 0% | High risk79 | Flagged0.035 |
| 24OE0220REHABILITATION OF ROAD WITH DRAINAGE ALONG RODRIGUEZ ST., TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱43.4M | 100% | High risk61 | Flagged0.014 |
| 24OE0226REHABILITATION OF ROAD WITH DRAINAGE ALONG MINDANAO ST., SAMPALOC, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱38.6M | 100% | High risk61 | Flagged0.012 |
| 24OE0229REHABILITATION OF ROAD WITH DRAINAGE ALONG A. LORENZO ST., MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱38.6M | 100% | Medium risk60 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25E00157CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (UPSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.2M | 0% | High risk79 | Flagged0.035 |
| 2 | 25E00158CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF RIVER CAPACITY ENHANCEMENT STRUCTURE ALONG BALITE RIVER, BRGY. PAPANDUNGIN (DOWNSTREAM-LS), GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231M | 0% | High risk79 | Flagged0.035 |
| 3 | 24E00015FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STRUCTURES ALONG ABRA DE ILOG RIVER, CABACAO SECTION, ABRA DE ILOG, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk68 | —-0.037 |
| 4 | 24E00017FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF FLOOD CONTROL STUCTURE ALONG ABRA DE ILOG RIVER, SITIO KULI-KULI SECTION, ARMADO, ABRA DE ILOG, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk68 | —-0.037 |
| 5 | 25OH0083CONSTRUCTION OF BOOSTER PUMPING STATION ALONG ESTERO DE PANDACAN, PACKAGE 2B, MANILA CITY | National Capital Region | South Manila DEO | On-Going | ₱142.8M | 34% | High risk68 | —-0.022 |
| 6 | 24E00010FLOOD MANAGEMENT PROGRAM- CONSTRUCTION OF NAGAPI RIVERBANK PROTECTION WORKS ALONG NAGAPI RIVER (UPSTREAM RIGHTSIDE), SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk67 | —-0.042 |
| 7 | 25OE0052REHABILITATION OF DRAINAGE ALONG ZONE 58 - 67, MANILA CITY (PHASE IV) | National Capital Region | North Manila DEO | On-Going | ₱93.9M | 16% | High risk65 | —-0.025 |
| 8 | 24OE0003INSTALLATION OF BOOSTER PUMP ALONG ESTERO DELA REINA, BARANGAY 9, (PHASE VI) TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.078 |
| 9 | 24OE0031INSTALLATION OF BOOSTER PUMP ALONG ESTERO DELA REINA, BARANGAY 9, (PHASE VII) TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱95.3M | 100% | High risk65 | —-0.078 |
| 10 | 24OE0009CONSTRUCTION OF PUMPING STATION ALONG ESTERO DE SAN MIGUEL (EARNSHAW DRAINAGE MAIN OUTFALL) | National Capital Region | North Manila DEO | On-Going | ₱96.5M | 88% | High risk64 | —-0.034 |
| 11 | 25E00280SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. TAMBONG, STA. 000=000-STA. 000+332.94, GLORIA, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.2M | 25% | High risk63 | —-0.016 |
| 12 | 25E00276SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. PROPER, STA. 000+000-STA. 000+368.64, BANSUD, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱231.5M | 25% | High risk63 | —-0.016 |
| 13 | 24E00027SPECIAL ROAD FUND MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG MINDORO WEST COASTAL ROAD, K0353+000-K0369+000 (INTERMITTENT SECTIONS), OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱241.2M | 100% | High risk63 | —-0.053 |
| 14 | 22OE0167CONSTRUCTION OF MULTI-PURPOSE BUILDING NORTH CEMETERY COLUMBARIUM, MANILA | National Capital Region | North Manila DEO | Completed | ₱96.5M | 100% | High risk62 | —-0.080 |
| 15 | 24E00119ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE- SECONDARY ROADS- MOGPOG-BALANACAN PORT OAD- K0012+763=-K0013+500 (INTERMITTENT SECTIONS), MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱289.5M | 100% | High risk62 | —-0.049 |
| 16 | 25OF0138REHABILITATION OF ROAD ALONG BARANGAY GULOD, PACKAGE 1A, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱94.6M | 29% | High risk62 | —-0.039 |
| 17 | 24OE0220REHABILITATION OF ROAD WITH DRAINAGE ALONG RODRIGUEZ ST., TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱43.4M | 100% | High risk61 | Flagged0.014 |
| 18 | 24OE0226REHABILITATION OF ROAD WITH DRAINAGE ALONG MINDANAO ST., SAMPALOC, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱38.6M | 100% | High risk61 | Flagged0.012 |
| 19 | 24OE0229REHABILITATION OF ROAD WITH DRAINAGE ALONG A. LORENZO ST., MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱38.6M | 100% | Medium risk60 | Flagged0.012 |
| 20 | 23E00146SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG MAMBURAO-PALUAN ROAD, BITUKANG MANOK SECTION (PHASE 1), OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱96.5M | 100% | Medium risk53 | —-0.077 |
| 21 | 23OE0069INSTALLATION OF BOOSTER PUMP AT ESTERO DELA REINA, PHASE V, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱70.4M | 100% | Medium risk53 | —-0.084 |
| 22 | 24OE0156CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 101 ZONE 8, MANILA CITY (PHASE II) | National Capital Region | North Manila DEO | On-Going | ₱29.7M | 1% | Medium risk51 | —-0.022 |
| 23 | 25OE0201PREVENTIVE MAINTENANCE - TERTIARY ROADS - H. LOPEZ BLVD. K0007 + 473.00 - K0007 + 945.00 | National Capital Region | North Manila DEO | On-Going | ₱47.3M | 87% | Medium risk51 | —-0.064 |
| 24 | 25OF0127PREVENTIVE MAINTENANCE - TERTIARY ROADS - TIMES ST - K0010 + (-020) - K0011 + 260, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱48M | 0% | Medium risk51 | —-0.038 |
| 25 | 25OG0137REHABILITATION OF ROAD AT BARANGAY UP VILLAGE, QUEZON CITY (PACKAGE 1) | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48M | 16% | Medium risk51 | —-0.042 |