Contractor dossier
62 projects on file, including joint ventures this contractor is part of.
Total projects
62
Total budget
₱862.5M
Average progress
93.2%
Completion rate
88.7%
Average risk score
42.4
Medium risk on average, out of 100
Flagged as unusual
2
3.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 60 | ₱837.3M | 42.2 | 2 | 94.6% |
| Negros Island Region | 2 | ₱25.2M | 47.5 | 0 | 49.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 33 | ₱418.7M | 43.3 | 0 | 91.2% |
| Flood Control and Drainage | 15 | ₱291M | 46.3 | 0 | 100.0% |
| Bridges | 8 | ₱123.2M | 40.4 | 2 | 83.1% |
| Buildings and Facilities | 6 | ₱29.6M | 30.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GP0046CONSTRUCTION OF BUNGSUAN- LAWAAN BRIDGE, BARANGAY LAWAAN, DUMARAO, CAPIZ | Region VI | Capiz 2nd DEO | On-Going | ₱24.7M | 5% | Medium risk47 | Flagged0.011 |
| 23GP0079CONSTRUCTION OF BRIDGE AT BARANGAY NAGSULANG - LAWAAN, BARANGAY NAGSULANG, DUMARAO, CAPIZ | Region VI | Capiz 2nd DEO | On-Going | ₱17.8M | 60% | Medium risk47 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21GF0089CONSTRUCTION OF SAGASA-TUGUISAN LOCAL ROAD, BRGY. RIZAL TUGUISAN, MUNICIPALITY OF GUIMBAL, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱5.9M | 100% | Medium risk44 | —-0.087 |
| 52 | 21G00147CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - PRESIDENT CORAZON C. AQUINO AVE. - (S00558PN) CHAINAGE 1203 - CHAINAGE 1857 | Region VI | Region VI | Completed | ₱8.7M | 100% | Medium risk44 | —-0.088 |
| 53 | 21G00025CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - PRESIDENT CORAZON C. AQUINO AVE. - (S00558PN) CHAINAGE 549 - CHAINAGE 1203 | Region VI | Region VI | Completed | ₱8.2M | 100% | Medium risk44 | —-0.088 |
| 54 | 18GH0142CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, BAROTAC VIEJO, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱4.8M | 100% | Medium risk40 | —-0.032 |
| 55 | 20G00091CONSTRUCTION OF CONCRETE ROAD - MUELLE LONEY ROAD EXTENSION, ILOILO CITY | Region VI | Region VI | Terminated | ₱2.5M | 100% | Low risk24 | —-0.049 |
| 56 | 21GH0030CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NANGKA, BATAD, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱2M | 100% | Low risk24 | —-0.080 |
| 57 | 21GH0031CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CABAGOHAN, BATAD, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱2M | 100% | Low risk24 | —-0.081 |
| 58 | 22GF0040REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-BAGUINGIN BR. (B00122PN) ALONG ILOILO-ANTIQUE RD | Region VI | Iloilo 1st DEO | Completed | ₱1.9M | 100% | Low risk23 | —-0.050 |
| 59 | 18GB0168MULTI-PURPOSE BUILDING/EVACUATION CENTER IN LAUA-AN, ANTIQUE | Region VI | Antique DEO | Completed | ₱2.8M | 100% | Low risk22 | —-0.084 |
| 60 | 23GJ0076(RE-BID) CONSTRUCTION OF MULTI PURPOSE BUILDING - COMPLETION OF MULTIPURPOSE BUILDING, BRGY. QUINTIN SALAS, JARO | Region VI | Iloilo City DEO | Completed | ₱4M | 100% | Low risk21 | —-0.085 |
| 61 | 17GF0007REHABILITATION/MAJOR REPAIR OF DAPUYAN BRIDGE (B00139PN) ALONG ILOILO-ANTIQUE ROAD, SAN JOAQUIN, ILOILO | Region VI | Iloilo 1st DEO | Completed | ₱996.8K | 100% | Low risk21 | —-0.025 |
| 62 | 19GP0009CONCRETING OF ROAD AT ARTURO JUGO NHS, BRGY. MANHOY, DAO, CAPIZ | Region VI | Capiz 2nd DEO | Completed | ₱1.5M | 100% | Low risk19 | —-0.086 |