Contractor dossier
106 projects on file, including joint ventures this contractor is part of.
Total projects
106
Total budget
₱8.9B
Average progress
94.5%
Completion rate
84.9%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
6
5.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 73 | ₱3.7B | 46.5 | 0 | 96.7% |
| Region III | 11 | ₱799M | 49.0 | 0 | 97.2% |
| Region IX | 6 | ₱436.9M | 63.1 | 1 | 96.8% |
| Region XII | 6 | ₱428.5M | 34.8 | 0 | 100.0% |
| Region I | 4 | ₱1.5B | 62.4 | 2 | 90.6% |
| Region XIII | 3 | ₱286.1M | 65.3 | 1 | 45.9% |
| Central Office | 2 | ₱1.7B | 75.5 | 2 | 52.1% |
| Region VII | 1 | ₱46M | 47.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 52 | ₱3.1B | 46.1 | 0 | 95.7% |
| Flood Control and Drainage | 25 | ₱1.7B | 53.5 | 1 | 94.0% |
| Bridges | 23 | ₱2.5B | 45.5 | 3 | 94.0% |
| Buildings and Facilities | 3 | ₱79.5M | 44.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱95.3M | 94.1 | 1 | 36.5% |
| OTHER | 1 | ₱233.2M | 79.0 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱1.2B | 78.5 | 1 | 87.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NG0097REHABILITATION OF SEAWALL, BARANGAY LIPATA, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱95.3M | 37% | High risk94 | Flagged0.026 |
| 24CL0037CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱98.9M | 100% | High risk80 | —-0.043 |
| 18KJ0190CONSTRUCTION OF USUGAN RIVER RIVER CONTROL INCLUDING BRIDGE, BONIFACIO, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱233.2M | 100% | High risk79 | —-0.003 |
| 19Z00015PR-09A, GUICAM BRIDGE, ZAMBOANGA SIBUGAY UNDER ADB LOAN NO. 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT (IGCMRSP) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.2B | 88% | High risk78 | Flagged0.022 |
| 18A00097CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - PALLAS - PARPAROROC ROAD LEADING TO ABKIR-PF ALVIAR - SALSALAMAGUI - ALSEM (BRIDGE CONSTRUCTION) IN SUPPORT OF DIFFERENT AGRICULTURAL PRODUCTS, ILOCOS NORTE | Region I | Region I | Completed | ₱289.5M | 100% | High risk74 | Flagged0.003 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
| 24CC0344CONSTRUCTION OF RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAY ALONG ANGAT RIVER, K000+551 TO K000+701, BARANGAY BONGA MENOR, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.063 |
| 20J00158CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/EXTENSION OF FLOOD CONTROL AT SAAZ RIVER, SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱111.1M | 100% | High risk73 | —-0.048 |
| 16Z00010CONTRACT PACKAGE 3, BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON | Central Office | Bridges Management Cluster | On-Going | ₱538M | 16% | High risk73 | Flagged0.065 |
| 21J00043CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER ALONG SAN RAMON BR. 2 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA SECONDARY ROAD, TALISAYAN, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱89.1M | 100% | High risk64 | —-0.056 |
| 19A00119CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD (PHASE I), PANGASINAN | Region I | Region I | On-Going | ₱890.5M | 77% | High risk63 | Flagged0.048 |
| 18KJ0189CONSTRUCTION OF MT. MALINDANG ECO TOURISM ROAD, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱237.2M | 100% | High risk62 | —-0.053 |
| 18K00156ROAD WIDENING OF OROQUIETA CITY-PLARIDEL-CALAMBA-SAPANG DALAGA RD-K1762+227-K1764+177,K1764+276-K176 | Region X | Region X | Completed | ₱162.9M | 100% | High risk62 | —-0.065 |
| 23C00072FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER NORTH APPROACH DOWNSTREAM, BOTOLAN, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | Completed | ₱96.5M | 100% | High risk62 | —-0.074 |
| 19K00325CONSTRUCTION OF OROQUIETA CITY BYPASS ROAD, MISAMIS OCCIDENTAL | Region X | Region X | Completed | ₱102.8M | 100% | High risk60 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 16Z00010CONTRACT PACKAGE 3, BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON | Central Office | Bridges Management Cluster | On-Going | ₱538M | 16% | High risk73 | Flagged0.065 |
| 19A00119CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD (PHASE I), PANGASINAN | Region I | Region I | On-Going | ₱890.5M | 77% | High risk63 | Flagged0.048 |
| 25NG0097REHABILITATION OF SEAWALL, BARANGAY LIPATA, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱95.3M | 37% | High risk94 | Flagged0.026 |
| 19Z00015PR-09A, GUICAM BRIDGE, ZAMBOANGA SIBUGAY UNDER ADB LOAN NO. 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT (IGCMRSP) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.2B | 88% | High risk78 | Flagged0.022 |
| 18A00097CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - PALLAS - PARPAROROC ROAD LEADING TO ABKIR-PF ALVIAR - SALSALAMAGUI - ALSEM (BRIDGE CONSTRUCTION) IN SUPPORT OF DIFFERENT AGRICULTURAL PRODUCTS, ILOCOS NORTE | Region I | Region I | Completed | ₱289.5M | 100% | High risk74 | Flagged0.003 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22KJ0031WIDENING OF PERMANENT BRIDGE SINONOC BR (B01145MN) ALONG OZAMIS-OROQUIETA RD, OZAMIS-OROQUIETA RD | Region X | Misamis Occidental 2nd DEO | Completed | ₱23.6M | 100% | Medium risk46 | —-0.056 |
| 52 | 21KJ0018WIDENING OF PERMANENT BRIDGE MAN-AN BR (B01142MN) ALONG OZAMIZ-OROQUIETA RD, MAN-AN BR (B01142MN) ALONG OZAMIZ-OROQUIETA RD | Region X | Misamis Occidental 2nd DEO | Completed | ₱15.1M | 100% | Medium risk46 | —-0.063 |
| 53 | 22KJ0018WIDENING OF PERMANENT BRIDGE LITAPAN BR (B00357MN) ALONG OZAMIZ-PAGADIAN ROAD | Region X | Misamis Occidental 2nd DEO | Completed | ₱12.9M | 100% | Medium risk46 | —-0.053 |
| 54 | 18KJ0109CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF TANGUB CITY URBAN DRAINAGE SYSTEM, INCLUDING ROW, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.080 |
| 55 | 22KJ0047CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DRAINAGE SYSTEM, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱37.2M | 100% | Medium risk46 | —-0.067 |
| 56 | 18KJ0122CONSTRUCTION OF CLARIN DRAINAGE SYSTEM, INCLUDING ROW, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.4M | 100% | Medium risk46 | —-0.080 |
| 57 | 23KI0069CONSTRUCTION OF ROAD, MISAMIS OCCIDENTAL HINTERLAND ALTERNATIVE ROAD NETWORK, JIMENEZ TO PANAON TO ALORAN, BARANGAY GUINTOMOYAN-SAN JUAN-TUGAYA SECTION, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | Completed | ₱29.4M | 100% | Medium risk46 | —-0.087 |
| 58 | 23KI0092CONSTRUCTION OF DIVERSION ROAD, OROQUIETA CITY, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | On-Going | ₱41.2M | 12% | Medium risk46 | —-0.022 |
| 59 | 21KI0124ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS, OROQUIETA CITY-PLARIDEL-CALAMBA-SAPANG DALAGA ROAD, K1761+200-K1761+550; K1789+706-K1790+400, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | Completed | ₱36.6M | 100% | Medium risk45 | —-0.094 |
| 60 | 23KI0072NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - OROQUIETA CITY - CALAMBA MT. RD K1772+000 - K1772+022, K1772+048 - K1773+000 | Region X | Misamis Occidental 1st DEO | Completed | ₱39.2M | 100% | Medium risk45 | —-0.093 |
| 61 | 21KJ0008CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, OZAMIZ CITY COASTAL BYPASS ROAD, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱41.9M | 100% | Medium risk45 | —-0.090 |
| 62 | 21KJ0061CONSTRUCTION OF ECO-TOURSIM HIGHWAY CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.091 |
| 63 | 18KJ0003REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS OZAMIZ-OROQUIETA ROAD K1701+675 - K1702+000, K1703+680-K1705+022 | Region X | Misamis Occidental 2nd DEO | Completed | ₱38.8M | 100% | Medium risk45 | —-0.091 |
| 64 | 20KJ0049CONSTRUCTION OF BYPASS AND DIVERSION ROADS, OZAMIZ COASTAL BYPASS ROAD EXTENSION, MALAUBANG-TINAGO SECTION, PACKAGE B, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.092 |
| 65 | 21KJ0086CONSTRUCTION OF BY-PASS ROAD AND DIVERSION ROADS OZAMIZ CITY COASTAL BYPASS ROAD (MALAUBANG-TINAGO-SECTION-PACKAGE B) MISAMIS OCCIDENTAL, OZAMIZ CITY, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱41.8M | 100% | Medium risk45 | —-0.092 |
| 66 | 21KJ0005ROAD WIDENING-PRIMARY ROADS, OZAMIZ-PAGADIAN ROAD-K1664+696-K1665+550, OZAMIZ-PAGADIAN ROAD-K1664+696-K1665+550, | Region X | Misamis Occidental 2nd DEO | Completed | ₱37.2M | 100% | Medium risk45 | —-0.093 |
| 67 | 22KJ0075CONSTRUCTION OF BYPASS DIVERSION ROADS MT MALINDANG ECO TOURISM BYPASS HIGHWAY, BITOON-DALINGAP SECTION, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.091 |
| 68 | 22KJ0050CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TANGUB-BONIFACIO BYPASS ROAD, BONIFACIO SECTION, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.085 |
| 69 | 22KJ0010CONSTRUCTION OF SLOPE PROTECTION DOWNSTREAM OF MALUBOG BRIDGE I ALONG LABUYO-TANGUB-SILANGA ROAD, TANGUB CITY, MISAMIS OCCIDENTAL, TANGUB CITY, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱14M | 100% | Medium risk45 | —-0.079 |
| 70 | 22KJ0013CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MT. MALINDANG ECO-TOURISM BYPASS HIGHWAY, MALIBANGCAO-CANIBUNGAN PUTOL SECTION, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱28.5M | 100% | Medium risk45 | —-0.079 |
| 71 | 17K00020REHAB/RECONST. OF NATL RDS W/SLIPS,SLOPE COLLAPSE & LANDSLIDE,LUMBIA-UGUIABAN BY-PASS RD CHAINAGE 85 | Region X | Region X | Completed | ₱91.7M | 100% | Medium risk45 | —-0.056 |
| 72 | 25KH0082CONSTRUCTION OF PEDESTRIAN OVERPASS AT CDO-AIRPORT-BUKIDNON RD - K1444 + 791, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | On-Going | ₱24.1M | 30% | Medium risk45 | —-0.039 |
| 73 | 19KF0022CONSTRUCTION OF RIVER REVETMENT/FLOOD CONTROL ALONG MANDULOG RIVER, KAPUSO VILLAGE, PHASE 1, BRGY. MANDULOG, ILIGAN CITY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱41.8M | 100% | Medium risk45 | —-0.082 |
| 74 | 19KF0023CONSTRUCTION OF RIVER REVETMENT/FLOOD CONTROL ALONG MANDULOG RIVER, KAPUSO VILLAGE, PHASE II, BRGY. MANDULOG, ILIGAN CITY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱41.8M | 100% | Medium risk45 | —-0.082 |
| 75 | 20KF0089CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MANDULOG RIVER AT BRGY. MANDULOG, ILIGAN CITY PACKAGE 3 | Region X | Lanao del Norte 1st DEO | Completed | ₱44.2M | 100% | Medium risk45 | —-0.082 |