Contractor dossier
106 projects on file, including joint ventures this contractor is part of.
Total projects
106
Total budget
₱8.9B
Average progress
94.5%
Completion rate
84.9%
Average risk score
48.7
Medium risk on average, out of 100
Flagged as unusual
6
5.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 73 | ₱3.7B | 46.5 | 0 | 96.7% |
| Region III | 11 | ₱799M | 49.0 | 0 | 97.2% |
| Region IX | 6 | ₱436.9M | 63.1 | 1 | 96.8% |
| Region XII | 6 | ₱428.5M | 34.8 | 0 | 100.0% |
| Region I | 4 | ₱1.5B | 62.4 | 2 | 90.6% |
| Region XIII | 3 | ₱286.1M | 65.3 | 1 | 45.9% |
| Central Office | 2 | ₱1.7B | 75.5 | 2 | 52.1% |
| Region VII | 1 | ₱46M | 47.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 52 | ₱3.1B | 46.1 | 0 | 95.7% |
| Flood Control and Drainage | 25 | ₱1.7B | 53.5 | 1 | 94.0% |
| Bridges | 23 | ₱2.5B | 45.5 | 3 | 94.0% |
| Buildings and Facilities | 3 | ₱79.5M | 44.4 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱95.3M | 94.1 | 1 | 36.5% |
| OTHER | 1 | ₱233.2M | 79.0 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱1.2B | 78.5 | 1 | 87.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NG0097REHABILITATION OF SEAWALL, BARANGAY LIPATA, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱95.3M | 37% | High risk94 | Flagged0.026 |
| 24CL0037CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BANCAL DANAC BUNGA SECTION, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱98.9M | 100% | High risk80 | —-0.043 |
| 18KJ0190CONSTRUCTION OF USUGAN RIVER RIVER CONTROL INCLUDING BRIDGE, BONIFACIO, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱233.2M | 100% | High risk79 | —-0.003 |
| 19Z00015PR-09A, GUICAM BRIDGE, ZAMBOANGA SIBUGAY UNDER ADB LOAN NO. 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT (IGCMRSP) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.2B | 88% | High risk78 | Flagged0.022 |
| 18A00097CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - PALLAS - PARPAROROC ROAD LEADING TO ABKIR-PF ALVIAR - SALSALAMAGUI - ALSEM (BRIDGE CONSTRUCTION) IN SUPPORT OF DIFFERENT AGRICULTURAL PRODUCTS, ILOCOS NORTE | Region I | Region I | Completed | ₱289.5M | 100% | High risk74 | Flagged0.003 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
| 24CC0344CONSTRUCTION OF RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAY ALONG ANGAT RIVER, K000+551 TO K000+701, BARANGAY BONGA MENOR, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | High risk73 | —-0.063 |
| 20J00158CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION/EXTENSION OF FLOOD CONTROL AT SAAZ RIVER, SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱111.1M | 100% | High risk73 | —-0.048 |
| 16Z00010CONTRACT PACKAGE 3, BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON | Central Office | Bridges Management Cluster | On-Going | ₱538M | 16% | High risk73 | Flagged0.065 |
| 21J00043CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER ALONG SAN RAMON BR. 2 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA SECONDARY ROAD, TALISAYAN, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱89.1M | 100% | High risk64 | —-0.056 |
| 19A00119CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD (PHASE I), PANGASINAN | Region I | Region I | On-Going | ₱890.5M | 77% | High risk63 | Flagged0.048 |
| 18KJ0189CONSTRUCTION OF MT. MALINDANG ECO TOURISM ROAD, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱237.2M | 100% | High risk62 | —-0.053 |
| 18K00156ROAD WIDENING OF OROQUIETA CITY-PLARIDEL-CALAMBA-SAPANG DALAGA RD-K1762+227-K1764+177,K1764+276-K176 | Region X | Region X | Completed | ₱162.9M | 100% | High risk62 | —-0.065 |
| 23C00072FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER NORTH APPROACH DOWNSTREAM, BOTOLAN, ZAMBALES, PROVINCE OF ZAMBALES | Region III | Region III | Completed | ₱96.5M | 100% | High risk62 | —-0.074 |
| 19K00325CONSTRUCTION OF OROQUIETA CITY BYPASS ROAD, MISAMIS OCCIDENTAL | Region X | Region X | Completed | ₱102.8M | 100% | High risk60 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 16Z00010CONTRACT PACKAGE 3, BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON | Central Office | Bridges Management Cluster | On-Going | ₱538M | 16% | High risk73 | Flagged0.065 |
| 19A00119CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN BYPASS ROAD (PHASE I), PANGASINAN | Region I | Region I | On-Going | ₱890.5M | 77% | High risk63 | Flagged0.048 |
| 25NG0097REHABILITATION OF SEAWALL, BARANGAY LIPATA, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱95.3M | 37% | High risk94 | Flagged0.026 |
| 19Z00015PR-09A, GUICAM BRIDGE, ZAMBOANGA SIBUGAY UNDER ADB LOAN NO. 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT (IGCMRSP) | Central Office | Roads Management Cluster II (Multilateral) | On-Going | ₱1.2B | 88% | High risk78 | Flagged0.022 |
| 18A00097CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - PALLAS - PARPAROROC ROAD LEADING TO ABKIR-PF ALVIAR - SALSALAMAGUI - ALSEM (BRIDGE CONSTRUCTION) IN SUPPORT OF DIFFERENT AGRICULTURAL PRODUCTS, ILOCOS NORTE | Region I | Region I | Completed | ₱289.5M | 100% | High risk74 | Flagged0.003 |
| 22J00091CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 1 ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (PCA SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱100.3M | 81% | High risk73 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 17K00008REHAB./RECONST. OF NATL ROADS WITH SLIPS,SLOPE COLLAPSE & LANDSLIDE,BUK-DAVAO CITY RD K1606+263-K160 | Region X | Region X | Completed | ₱91M | 100% | Medium risk45 | —-0.052 |
| 77 | 17KI0066WIDENING OF PERMANENT BRIDGES, PINES BRIDGE (B00367MN) , OZAMIZ CITY - OROQ. CITY ROAD, OROQUIETA CITY | Region X | Misamis Occidental 1st DEO | Completed | ₱37.2M | 100% | Medium risk45 | —-0.026 |
| 78 | 23KI0084CONSTRUCTION OF BY-PASS ROAD IN BARANGAY CALUBE - MACUBON MUNICIPALITY OF ALORAN,OROQUIETA CITY BY-PASS ROADS SECTION OF ALORAN, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | Completed | ₱27.9M | 100% | Medium risk45 | —-0.087 |
| 79 | 21K00189CONST./REPAIR/REHAB./IMPRVT. OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONCRETING OF SAPANG DALAGA-CONCEPTION-MANSAWAN-DON VICTORIANO ROAD (MISAMIS OCCIDENTAL HINTERLAND ALTERNATE NATIONAL ROAD NETWORK) ST.05+175-STA.06+180 (PACKAGE 1) SAPANG DA | Region X | Region X | Completed | ₱27.6M | 100% | Medium risk45 | —-0.092 |
| 80 | 23KJ0069CONSTRUCTION OF MULTI-PURPOSE BUILDING (AQUAMARINE PARK), SINACABAN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱14M | 100% | Medium risk45 | —-0.085 |
| 81 | 23KI0064ASSET PRESERVATION PROGRAM -CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAMBA - BALIANGAO RD - K1780+225 - K1781+296 | Region X | Misamis Occidental 1st DEO | Completed | ₱24.5M | 100% | Medium risk45 | —-0.093 |
| 82 | 24KD0069INSTALLATION OF STREET LIGHTS ALONG NAZARETH CAGAYAN DE ORO CITY MIS OR | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.095 |
| 83 | 21KJ0003REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGEDPAVED ROADS-SECONDARY ROADS, OZAMIZ PORT ROAD (DUAL)-(S01002MN) CHAINAGE0-CHAINAGE 381, OZAMIZ-PORT ROAD (DUAL)-(S01002MN) CHAINAGE0-CHAINAGE 381 | Region X | Misamis Occidental 2nd DEO | Completed | ₱14.5M | 100% | Medium risk45 | —-0.094 |
| 84 | 21KJ0002REHABILITAION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, OZAMIZ PORT ROAD (S01003MN) CHAINAGE 117-CHAINAGE 498OZAMIZ-PORT ROAD (S01003MN) CHAINAGE 117-CHAINAGE 498 | Region X | Misamis Occidental 2nd DEO | Completed | ₱14.5M | 100% | Medium risk45 | —-0.094 |
| 85 | 18KF0051CONSTRUCTION/REHABILITATION OF REVETMENT ALONG MANDULOG BRIDGE I (UPSTREAM) INCLUDING ROW, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱35.2M | 100% | Medium risk45 | —-0.082 |
| 86 | 23KI0082CONSTRUCTION OF ROAD, BARANGAY MABINI, BALIANGAO, MISAMIS OCCIDENTAL. | Region X | Misamis Occidental 1st DEO | Completed | ₱14.7M | 100% | Medium risk45 | —-0.095 |
| 87 | 25KD0021CONSTRUCTION OF ROAD/ PATHWAY, BARANGAY BALUBAL, CAGAYAN DE ORO CITY (PHASE 2) | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱9.8M | 92% | Medium risk45 | —-0.057 |
| 88 | 24KD0033INSTALLATION OF STREET LIGHT ALONG BARANGAY CAMAMAN-AN, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱9.7M | 100% | Medium risk45 | —-0.096 |
| 89 | 23KD0025INST O STREET LIGHTS ALONG BIGAAN BRIDGE, BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD CDOC | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱11M | 100% | Medium risk44 | —-0.095 |
| 90 | 24KD0046INSTALLATION OF STREET LIGHTS ALONG BARANGAY AGUSAN, CDOC MIS OR | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱9.8M | 100% | Medium risk44 | —-0.096 |
| 91 | 24KD0034INSTALLATION OF STREET LIGHTS ALONG BARANGAY BUGO, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | Completed | ₱9.7M | 100% | Medium risk44 | —-0.096 |
| 92 | 19KJ0194CONSTRUCTION OF CLASSROOMS (BATCH1) 2STY4CL, TINACLAAN ES, CLARIN, MISAMIS OCCIDENTAL | Region X | Misamis Occidental 2nd DEO | Completed | ₱19M | 100% | Medium risk40 | —-0.047 |
| 93 | 24CJ0351REPAIR/REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL LEFT DIKE, TIBAG SECTION, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱76.9M | 100% | Medium risk38 | —-0.095 |
| 94 | 21M00055PREVENTIVE MAINTENANCE, ALONG SARANGANI SULTAN KUDARAT COASTAL ROAD K1747+549-K1747+849, K1747+889-K1748+000, K1749+000-K1749+428, K1749+856-K1750+484, K1751+300-K1752+058, K1753+520 -K1753+1004, K1754+412-K1754+871, | Region XII | Region XII | Completed | ₱97.3M | 100% | Medium risk38 | —-0.072 |
| 95 | 21M00054PREVENTIVE MAINTENANCE, ALONG SARANGANI SULTAN KUDARAT COASTAL ROAD, K1744+053-K1746+032, K1746+085-K1747+549, KIAMBA, SARANGANI | Region XII | Region XII | Completed | ₱97.4M | 100% | Medium risk38 | —-0.072 |
| 96 | 22C00024BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, SAN FERNANDO FLYOVER ALONG JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA | Region III | Region III | Completed | ₱67.5M | 100% | Medium risk35 | —-0.060 |
| 97 | 23CI0086SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES, CONSTRUCTION OF DIKE WITH SLOPE PROTECTION AND GROUNDSILL ALONG SAPANG BALEN CREEK (LEFT SIDE), MABALACAT CITY, PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱72.3M | 100% | Medium risk35 | —-0.086 |
| 98 | 22CI0066CONVERGENCE AND SPECIAL SUPPORT PROGRAM; FLOOD MITIGATION STRUCTURES PROTECTING INFRA/FACILITIES, CONST. OF REINFORCED CONCRETE SLOPE PROTECTION ALONG ABACAN RIVER, UPSTREAM OF FRIENDSHIP BRIDGE STA 0+050 TO 0+650 (R/D), BRGY ANUNAS, ANGELES CITY, PAMPANG | Region III | Pampanga 3rd DEO | Completed | ₱57.9M | 100% | Medium risk35 | —-0.087 |
| 99 | 22CG0026SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF TALBA - TINAJERO ROAD INCLUDING DRAINAGE SYSTEM, BACOLOR, PAMPA | Region III | Pampanga 1st DEO | Completed | ₱37.2M | 100% | Medium risk33 | —-0.103 |
| 100 | 18CG0112IMPROVEMENT/CONCRETING OF ROAD, BALAS, POTRERO-MALIWALU, POTRERO-MITLA, SAN ANTONIO-DUAT AND DUAT-POTRERO, BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱23.9M | 100% | Medium risk32 | —-0.103 |