Opening the dossier…
Opening the dossier…
Contractor dossier
39 projects on file, including joint ventures this contractor is part of.
Total projects
39
Total budget
₱1.9B
Average progress
89.0%
Completion rate
79.5%
Average risk score
56.4
Medium risk on average, out of 100
Flagged as unusual
1
2.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 39 | ₱1.9B | 56.4 | 1 | 89.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 38 | ₱1.9B | 55.9 | 1 | 88.7% |
| GAA 2025 SSP | 1 | ₱4.8M | 76.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0190CONSTRUCTION OF MULTI-PURPOSE BUILDING, (CITY AQUATIC CENTER) BRGY. MINUYAN, CITY OF SAN JOSE DEL MONTE, BULACAN (PHASE 4) | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 46% | High risk80 | —-0.013 |
| 25CD0191CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MUZON SOUTH, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 41% | High risk79 | —-0.011 |
| 25CD0192CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 0% | High risk79 | Flagged0.002 |
| 24CD0248CONSTRUCTION OF MULTI - PURPOSE BUILDING, SAPANG PALAY NATIONAL HIGH SCHOOL, BARANGAY FATIMA V, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱98M | 100% | High risk79 | —-0.057 |
| 24CD0249CONSTRUCTION OF MULTI - PURPOSE BUILDING, (CONVENTION CENTER), BARANGAY SAPANG PALAY PROPER, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱98M | 100% | High risk78 | —-0.056 |
| 24CD0207CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMAND CENTER), SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱98M | 100% | High risk78 | —-0.056 |
| 25CD0130CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINUYAN PROPER, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.8M | 100% | High risk77 | —-0.036 |
| 24CD0268CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY SAN ISIDRO, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱49M | 50% | High risk76 | —-0.021 |
| 25CD0097CONSTRUCTION OF MULTI-PURPOSE BUILDING, ASSOCIATION OF BARANGAY CAPTAINS BUILDING (ABC) - PHASE I, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 81% | High risk76 | —-0.036 |
| 25CD0098CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE V, PABAHAY 2000, BARANGAY MUZON SOUTH, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱47.5M | 50% | High risk76 | —-0.024 |
| 24CD0215CONSTRUCTION OF MULTI PURPOSE BUILDING, (BARANGAY OPERATIONS CENTER-DISTRICT I), BARANGAY KAYPIAN, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱49M | 100% | High risk75 | —-0.069 |
| 24CD0134CONSTRUCTION OF MULTI-PURPOSE BUILDING, (CITY CONVENTION CENTER) BARANGAY SAPANG PALAY PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱48.9M | 100% | High risk75 | —-0.069 |
| 24CD0072CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY FATIMA I, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.8M | 100% | High risk73 | —-0.076 |
| 24CC0487CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MALAMIG, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱14.8M | 65% | High risk73 | —-0.024 |
| 17CD0227CONSTRUCTION OF THE SAN JOSE DEL MONTE CONVENTION CENTER, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱23.5M | 100% | High risk72 | —-0.072 |
| 24CD0229CONSTRUCTION OF MULTI - PURPOSE BUILDING, TOWERVILLE, BARANGAY MINUYAN PROPER, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.6M | 100% | High risk72 | —-0.072 |
| 24CD0064CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINUYAN IV, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.8M | 100% | High risk72 | —-0.074 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0192CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 0% | High risk79 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21CD0099CONSTRUCTION OF CONVENTION CENTER (PHASE IV), SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱47.9M | 100% | Medium risk43 | —-0.098 |
| 27 | 23CD0117CONSTRUCTION OF MULTI-PURPOSE FACILITY, (MUZON PABAHAY 2000 PUBLIC MARKET) BRGY. MUZON, CITY OF SAN JOSE DEL MONTE, BULACAN (PHASE IV) | Region III | Bulacan 2nd DEO | Completed | ₱49.5M | 100% | Medium risk42 | —-0.100 |
| 28 | 22CD0083CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MINUYAN CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱49.5M | 100% | Medium risk42 | —-0.100 |
| 29 | 19CJ0170CONSTRUCTION OF 2 UNITS 4 STOREY 16 CLASSROOMS, VICTORIA NATIONAL HIGH SCHOOL, VICTORIA, TARLAC | Region III | Tarlac DEO | Completed | ₱100M | 100% | Medium risk42 | —-0.013 |
| 30 | 21CD0097CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE V), CSJDM SPORTS COMPLEX, BARANGAY MINUYAN, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱44.7M | 100% | Medium risk40 | —-0.100 |
| 31 | 19CD0245COMPLETION OF SAN JOSE DEL MONTE CONVENTION CENTER, BARANGAY SAPANG PALAY PROPER, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱46.5M | 100% | Medium risk39 | —-0.099 |
| 32 | 19CD0172REHABILITATION OF MULTI-PURPOSE BUILDING, TUNGKONG MANGGA, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱14.1M | 100% | Medium risk39 | —-0.105 |
| 33 | 23CD0029CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUZON PABAHAY PUBLIC MARKET, BARANGAY MUZON, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱34.6M | 100% | Medium risk39 | —-0.101 |
| 34 | 20CD0146CONSTRUCTION OF MULTI-PURPOSE BUILDING, ST. BERNADETTE CHILDREN'S HOSPITAL, BRGY. MUZON, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱28.2M | 100% | Medium risk38 | —-0.101 |
| 35 | 20CD0124CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BRGY. MINUYAN, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱18.8M | 100% | Medium risk37 | —-0.104 |
| 36 | 18CD0307CONSTRUCTION OF SAN JOSE DEL MONTE CONVENTION CENTER, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱24.7M | 100% | Medium risk37 | —-0.103 |
| 37 | 20CD0147CONSTRUCTION AND REHABILITATION OF SAN JOSE DEL MONTE SPORTS COMPLEX, BRGY. MINUYAN, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱14.1M | 100% | Medium risk37 | —-0.104 |
| 38 | 19CD0157CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN JOSE DEL MONTE CENTRAL ELEMENTARY SCHOOL, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | Medium risk36 | —-0.106 |
| 39 | 20CD0126CONSTRUCTION OF ST. BERNADETTE CHILDRENS HOSPITAL CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.7M | 100% | Low risk18 | —-0.107 |