Opening the dossier…
Opening the dossier…
Contractor dossier
312 projects on file, including joint ventures this contractor is part of.
Total projects
312
Total budget
₱13.2B
Average progress
94.3%
Completion rate
84.3%
Average risk score
45.2
Medium risk on average, out of 100
Flagged as unusual
8
2.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 104 | ₱2.7B | 45.9 | 0 | 97.4% |
| Region III | 75 | ₱2.8B | 37.2 | 0 | 96.7% |
| Region IV-A | 30 | ₱1.8B | 53.3 | 1 | 90.5% |
| Region XI | 26 | ₱461.6M | 31.7 | 0 | 100.0% |
| Region I | 18 | ₱1.1B | 57.2 | 2 | 77.5% |
| Region IV-B | 17 | ₱2.3B | 56.0 | 2 | 93.8% |
| Region VIII | 13 | ₱745.2M | 51.7 | 1 | 82.7% |
| Region VI | 8 | ₱306.6M | 47.8 | 0 | 100.0% |
| Region X | 8 | ₱83.4M | 40.5 | 1 | 89.1% |
| Region II | 5 | ₱67.2M | 45.4 | 0 | 100.0% |
| Region IX | 4 | ₱417.5M | 71.6 | 0 | 83.9% |
| Region XII | 2 | ₱257.5M | 61.4 | 1 | 71.9% |
| Negros Island Region | 2 | ₱188.2M | 57.7 | 0 | 83.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 107 | ₱3.9B | 42.3 | 1 | 94.9% |
| Buildings and Facilities | 103 | ₱2B | 38.7 | 2 | 95.4% |
| Flood Control and Drainage | 83 | ₱6.5B | 53.6 | 2 | 93.3% |
| Bridges | 11 | ₱196.8M | 47.3 | 0 | 100.0% |
| OTHER | 5 | ₱431.5M | 69.6 | 1 | 85.8% |
| GAA 2025 OO-2 | 2 | ₱86.7M | 88.1 | 1 | 59.4% |
| GAA 2025 SSP | 1 | ₱95.5M | 95.4 | 1 | 44.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0052CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD (PHASE 2), BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱95.5M | 44% | High risk95 | Flagged0.017 |
| 25OA0005CONSTRUCTION OF RIVERWALLS ALONG TANGOS RIVER, PHASE 8, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱49M | 64% | High risk89 | —-0.012 |
| 25AE0010CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, BARANGAY BULALAAN, SUDIPEN, LA UNION | Region I | La Union 1st DEO | On-Going | ₱37.7M | 55% | High risk87 | Flagged0.004 |
| 24CL0050CONSTRUCTION OF SANTO TOMAS RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 8, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 98% | High risk82 | —-0.013 |
| 24CL0049CONSTRUCTION OF SANTO TOMAS RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 7, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 98% | High risk82 | —-0.013 |
| 24CD0281CONSTRUCTION OF NEW ROGACIANO M. MERCADO MEMORIAL HOSPITAL, MUNICIPALITY OF SANTA MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱74.2M | 100% | High risk77 | —-0.067 |
| 25CP0062CONVERG. AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, PHASE I, BRGY, TALBAK, DONA REMEDIOS TRINIDAD, | Region III | Bulacan 3rd DEO | On-Going | ₱142.5M | 30% | High risk77 | —-0.007 |
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 24I00040CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DIVINUBO, BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱192.9M | 0% | High risk76 | Flagged0.040 |
| 23CC0250CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY PAGALA, BALIUAG, BULACAN (K003+120 TO K003+420) BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.061 |
| 24J00036CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER, SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 3 | Region IX | Region IX | On-Going | ₱138.6M | 93% | High risk75 | —-0.014 |
| 24OB0290CONSTRUCTION OF ROAD NETWORK CONNECTING THE NEW RFU-NCR BUILDING TO THE MAIN GATE OF CAMP BAGONG DIWA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.5M | 85% | High risk73 | —-0.001 |
| 23J00023CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE (DOWNSTREAM-BOTHSIDE | Region IX | Region IX | Completed | ₱110.5M | 100% | High risk73 | —-0.062 |
| 23D00099CONSTRUCTION OF REVETMENT ALONG CAÑAS RIVER, GENERAL TRIAS, CAVITE, PHASE 2 | Region IV-A | Region IV-A | Completed | ₱99.6M | 100% | High risk72 | —-0.027 |
| 25A00533BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAGUPAN, PANGASINAN | Region I | Region I | On-Going | ₱57.8M | 0% | High risk71 | Flagged0.010 |
| 24A00425BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BONGO RIVER, BARANGAY MEDINA, DINGRAS, ILOCOS NORTE (PHASE IV) | Region I | Region I | Completed | ₱49.5M | 100% | High risk71 | —-0.034 |
| 25J00051PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) K1928+000.00 - K1928+032.00, K1928+032.00- K 1928+972.00 | Region IX | Region IX | On-Going | ₱72.2M | 43% | High risk71 | —-0.005 |
| 24CC0068CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AND IMPROVEMENT OF WATERWAYS ALONG BOCAUE RIVER, BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱28.9M | 100% | High risk69 | —-0.063 |
| 24A00426BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEMS ALONG BONGO RIVER BARANGAY PERALTA, DINGRAS, ILOCOS NORTE | Region I | Region I | Completed | ₱49.5M | 100% | High risk69 | —-0.061 |
| 25CC0179CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AND IMPROVEMENT OF WATERWAYS ALONG BALAGTAS RIVER, BARANGAY SANTOL, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱46.6M | 99% | High risk69 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00040CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DIVINUBO, BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱192.9M | 0% | High risk76 | Flagged0.040 |
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 24E00239LGU HOSPITALS - PALUAN COMMUNITY HOSPITAL, PALUAN, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱38.4M | 22% | Medium risk44 | Flagged0.025 |
| 25DN0052CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD (PHASE 2), BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱95.5M | 44% | High risk95 | Flagged0.017 |
| 25A00533BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAGUPAN, PANGASINAN | Region I | Region I | On-Going | ₱57.8M | 0% | High risk71 | Flagged0.010 |
| 23E00117SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱221.9M | 86% | High risk67 | Flagged0.004 |
| 25AE0010CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, BARANGAY BULALAAN, SUDIPEN, LA UNION | Region I | La Union 1st DEO | On-Going | ₱37.7M | 55% | High risk87 | Flagged0.004 |
| 24KL0112CONRETING OF BRGY. TULA FMR, BRGY. TULA, ALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱14.9M | 100% | Medium risk46 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 24OE0058CONSTRUCTION OF DRAINAGE ALONG LUBIRAN ST., MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱85.5M | 100% | Medium risk53 | —-0.079 |
| 77 | 23OE0090CONSTRUCTION OF BOX CULVERT ALONG C. AGUILA ST., SAN MIGUEL, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱74.7M | 100% | Medium risk53 | —-0.084 |
| 78 | 23OG0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KRUS NA LIGAS, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱44.5M | 100% | Medium risk52 | —-0.091 |
| 79 | 20OF0156CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. RAMON MAGSAYSAY, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱28.8M | 100% | Medium risk52 | —-0.087 |
| 80 | 23OE0246UPGRADING, REHABILITATION, REPAIR, CONSTRUCTION AND/OR COMPLETION OF JUSTICE JOSE ABAD SANTOS GENERAL HOSPITAL | National Capital Region | North Manila DEO | Completed | ₱47.9M | 100% | Medium risk52 | —-0.045 |
| 81 | 23E00106ASSET PRESERVATION PROGRAM- REHAB./RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE- SECONDARY ROADS SIBUYAN CIRCUMFERENTIAL ROAD, STA. 37+000-STA. 37+28-0; STA. 65+255.49-STA. 65+316.16, ROMBLON | Region IV-B | Region IV-B | Completed | ₱97.5M | 100% | Medium risk51 | —-0.080 |
| 82 | 23DP0017ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - SN PABLO-RIZAL-NAGCARLAN-LILIW RD - K0092 + 998 - K0093 + 932, K0093 + 940 - K0095 + 010 | Region IV-A | Laguna 3rd DEO | Completed | ₱51.3M | 100% | Medium risk51 | —-0.103 |
| 83 | 23LE0018CONSTRUCTION OF CONCRETE REVETMENT (RC CUT-OFF WALL), PONGPONG FLOOD CONTROL, STA. MARIA, DAVAO OCCIDENTAL | Region XI | Davao Occidental DEO | Completed | ₱77.2M | 100% | Medium risk51 | —-0.067 |
| 84 | 24OB0250IMPROVEMENT OF MARIKINA POLYTECHNIC COLLEGE ROAD NETWORK, BRGY. STA. ELENA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱47.5M | 100% | Medium risk51 | —-0.098 |
| 85 | 24DE0019ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD (SECTION 5), BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.105 |
| 86 | 24OF0090PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG MARIA CLARA ST., K0006 + (-174) TO K0007 + 809, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.098 |
| 87 | 24OG0045IMPROVEMENT OF ROAD, BARANGAY SOUTH TRIANGLE, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.098 |
| 88 | 24OG0087IMPROVEMENT OF ROAD, BARANGAY LAGING HANDA, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.099 |
| 89 | 21D00045FY 2021 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY REHABILITATION OF PNP TRAINING INSTITUTE, CAMP BGEN P. VICENTE LIM, CALAMBA CITY, LAGUNA | Region IV-A | Region IV-A | Completed | ₱17.2M | 100% | Medium risk50 | —-0.104 |
| 90 | 25OB0210CONSTRUCTION OF NATIONAL LANGUAGE SKILL BUILDING, TESDA COMPOUND CENTRAL OFFICE, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱28.5M | 0% | Medium risk50 | —-0.030 |
| 91 | 23A00245CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER, BARANGAY STA LUCIA, ARINGAY, LA UNION | Region I | Region I | Completed | ₱77.2M | 100% | Medium risk50 | —-0.058 |
| 92 | 24DI0003CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY CALENDOLA, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.7M | 70% | Medium risk50 | —-0.030 |
| 93 | 25DI0040CONSTRUCTION OF STRUCTURE FOR RIVER PROTECTION AT SAINT JOSEPH VILLAGE, SAN PEDRO CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.7M | 30% | Medium risk50 | —-0.032 |
| 94 | 24OI0081REHABILITATION OF MULTI - PURPOSE BLDG., PULANGLUPA 2, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱14.4M | 100% | Medium risk50 | —-0.059 |
| 95 | 24IM0060ROAD WIDENING - TERTIARY ROADS - NAGA-NAGA ANIBONG RD - K0906 + 401 - K0906 + 911 | Region VIII | Tacloban City DEO | On-Going | ₱40.8M | 86% | Medium risk50 | —-0.048 |
| 96 | 24OI0070REHABILITATION OF MULTI - PURPOSE BLDG., MANUYO 2, LAS PINAS CITY LONE DISTRICT | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱14.4M | 100% | Medium risk50 | —-0.058 |
| 97 | 25OG0018REHABILITATION OF SAN JUAN RIVER, PHASE 3, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | On-Going | ₱48M | 43% | Medium risk50 | —-0.042 |
| 98 | 19OB0434CONSTRUCTION OF ST. MARY SUBDIVISION MULTI-PURPOSE GYM, BRGY. NANGKA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱24M | 100% | Medium risk50 | —-0.086 |
| 99 | 19OB0432CONSTRUCTION OF NHA MULTI-PURPOSE GYM, BRGY. NANGKA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱24M | 100% | Medium risk50 | —-0.087 |
| 100 | 21OC0086CONSTRUCTION OF MULTI-PURPOSE BUILDING WITHIN BARANGAY MARCELO GREENPARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱24.7M | 100% | Medium risk49 | —-0.099 |