Contractor dossier
312 projects on file, including joint ventures this contractor is part of.
Total projects
312
Total budget
₱13.2B
Average progress
94.3%
Completion rate
84.3%
Average risk score
45.2
Medium risk on average, out of 100
Flagged as unusual
8
2.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 104 | ₱2.7B | 45.9 | 0 | 97.4% |
| Region III | 75 | ₱2.8B | 37.2 | 0 | 96.7% |
| Region IV-A | 30 | ₱1.8B | 53.3 | 1 | 90.5% |
| Region XI | 26 | ₱461.6M | 31.7 | 0 | 100.0% |
| Region I | 18 | ₱1.1B | 57.2 | 2 | 77.5% |
| Region IV-B | 17 | ₱2.3B | 56.0 | 2 | 93.8% |
| Region VIII | 13 | ₱745.2M | 51.7 | 1 | 82.7% |
| Region VI | 8 | ₱306.6M | 47.8 | 0 | 100.0% |
| Region X | 8 | ₱83.4M | 40.5 | 1 | 89.1% |
| Region II | 5 | ₱67.2M | 45.4 | 0 | 100.0% |
| Region IX | 4 | ₱417.5M | 71.6 | 0 | 83.9% |
| Region XII | 2 | ₱257.5M | 61.4 | 1 | 71.9% |
| Negros Island Region | 2 | ₱188.2M | 57.7 | 0 | 83.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 107 | ₱3.9B | 42.3 | 1 | 94.9% |
| Buildings and Facilities | 103 | ₱2B | 38.7 | 2 | 95.4% |
| Flood Control and Drainage | 83 | ₱6.5B | 53.6 | 2 | 93.3% |
| Bridges | 11 | ₱196.8M | 47.3 | 0 | 100.0% |
| OTHER | 5 | ₱431.5M | 69.6 | 1 | 85.8% |
| GAA 2025 OO-2 | 2 | ₱86.7M | 88.1 | 1 | 59.4% |
| GAA 2025 SSP | 1 | ₱95.5M | 95.4 | 1 | 44.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0052CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD (PHASE 2), BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱95.5M | 44% | High risk95 | Flagged0.017 |
| 25OA0005CONSTRUCTION OF RIVERWALLS ALONG TANGOS RIVER, PHASE 8, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱49M | 64% | High risk89 | —-0.012 |
| 25AE0010CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, BARANGAY BULALAAN, SUDIPEN, LA UNION | Region I | La Union 1st DEO | On-Going | ₱37.7M | 55% | High risk87 | Flagged0.004 |
| 24CL0050CONSTRUCTION OF SANTO TOMAS RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 8, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 98% | High risk82 | —-0.013 |
| 24CL0049CONSTRUCTION OF SANTO TOMAS RIVER FLOOD CONTROL STRUCTURE, UPSTREAM, PACKAGE 7, SAN NARCISO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱95.2M | 98% | High risk82 | —-0.013 |
| 24CD0281CONSTRUCTION OF NEW ROGACIANO M. MERCADO MEMORIAL HOSPITAL, MUNICIPALITY OF SANTA MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱74.2M | 100% | High risk77 | —-0.067 |
| 25CP0062CONVERG. AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, PHASE I, BRGY, TALBAK, DONA REMEDIOS TRINIDAD, | Region III | Bulacan 3rd DEO | On-Going | ₱142.5M | 30% | High risk77 | —-0.007 |
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 24I00040CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DIVINUBO, BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱192.9M | 0% | High risk76 | Flagged0.040 |
| 23CC0250CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY PAGALA, BALIUAG, BULACAN (K003+120 TO K003+420) BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.061 |
| 24J00036CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER, SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 3 | Region IX | Region IX | On-Going | ₱138.6M | 93% | High risk75 | —-0.014 |
| 24OB0290CONSTRUCTION OF ROAD NETWORK CONNECTING THE NEW RFU-NCR BUILDING TO THE MAIN GATE OF CAMP BAGONG DIWA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱94.5M | 85% | High risk73 | —-0.001 |
| 23J00023CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE (DOWNSTREAM-BOTHSIDE | Region IX | Region IX | Completed | ₱110.5M | 100% | High risk73 | —-0.062 |
| 23D00099CONSTRUCTION OF REVETMENT ALONG CAÑAS RIVER, GENERAL TRIAS, CAVITE, PHASE 2 | Region IV-A | Region IV-A | Completed | ₱99.6M | 100% | High risk72 | —-0.027 |
| 25A00533BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAGUPAN, PANGASINAN | Region I | Region I | On-Going | ₱57.8M | 0% | High risk71 | Flagged0.010 |
| 24A00425BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BONGO RIVER, BARANGAY MEDINA, DINGRAS, ILOCOS NORTE (PHASE IV) | Region I | Region I | Completed | ₱49.5M | 100% | High risk71 | —-0.034 |
| 25J00051PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) K1928+000.00 - K1928+032.00, K1928+032.00- K 1928+972.00 | Region IX | Region IX | On-Going | ₱72.2M | 43% | High risk71 | —-0.005 |
| 24CC0068CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AND IMPROVEMENT OF WATERWAYS ALONG BOCAUE RIVER, BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱28.9M | 100% | High risk69 | —-0.063 |
| 24A00426BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEMS ALONG BONGO RIVER BARANGAY PERALTA, DINGRAS, ILOCOS NORTE | Region I | Region I | Completed | ₱49.5M | 100% | High risk69 | —-0.061 |
| 25CC0179CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AND IMPROVEMENT OF WATERWAYS ALONG BALAGTAS RIVER, BARANGAY SANTOL, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱46.6M | 99% | High risk69 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00040CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DIVINUBO, BORONGAN CITY, EASTERN SAMAR | Region VIII | Region VIII | On-Going | ₱192.9M | 0% | High risk76 | Flagged0.040 |
| 23M00090CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, STA 6+100 - STA.7+120 (ROAD COMPONENT); STA 5+78 | Region XII | Region XII | On-Going | ₱135.5M | 44% | High risk76 | Flagged0.037 |
| 24E00239LGU HOSPITALS - PALUAN COMMUNITY HOSPITAL, PALUAN, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱38.4M | 22% | Medium risk44 | Flagged0.025 |
| 25DN0052CONSTRUCTION OF BARANGAY LUNSAD TO BARANGAY PILA-PILA COASTAL ROAD (PHASE 2), BINANGONAN, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱95.5M | 44% | High risk95 | Flagged0.017 |
| 25A00533BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI-PURPOSE BUILDING, DAGUPAN, PANGASINAN | Region I | Region I | On-Going | ₱57.8M | 0% | High risk71 | Flagged0.010 |
| 23E00117SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO | Region IV-B | Region IV-B | On-Going | ₱221.9M | 86% | High risk67 | Flagged0.004 |
| 25AE0010CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AMBURAYAN RIVER, BARANGAY BULALAAN, SUDIPEN, LA UNION | Region I | La Union 1st DEO | On-Going | ₱37.7M | 55% | High risk87 | Flagged0.004 |
| 24KL0112CONRETING OF BRGY. TULA FMR, BRGY. TULA, ALUBIJID, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | On-Going | ₱14.9M | 100% | Medium risk46 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 21OB0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY NAPINDAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19.2M | 100% | Medium risk48 | —-0.086 |
| 127 | 20OB0338CONSTRUCTION OF MULTI-PURPOSE BUILDING WITH SITE DEVELOPMENT, BRGY. NAPINDAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19.2M | 100% | Medium risk48 | —-0.085 |
| 128 | 21IL0067CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ACCESS ROAD LEADING TO CRATER LAKE, BRGY. DAYANOG, SAN JUAN (CABALIAN), SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱24.5M | 100% | Medium risk48 | —-0.093 |
| 129 | 22IL0075BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES, MAGAUPAS BRIDGE (B00609LT) ALONG DAANG MAHARLIKA LT, LILOAN, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱20.5M | 100% | Medium risk48 | —-0.054 |
| 130 | 21OI0107CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. ALMANZA 2, LAS PIÑAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.101 |
| 131 | 21IL0152ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROAD - BDRY. SOUTHERN LEYTE-MAASIN-MACROHON-SOGOD-JCT DAANG MAHARLIKA - K1166+418 - K1166+761, PADRE BURGOS, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱15.6M | 100% | Medium risk48 | —-0.093 |
| 132 | 20OB0224CONSTRUCTION (COMPLETION) OF 4-STOREY MULTI-PURPOSE BUILDING (FRONT), BRGY. HAGDAN BATO ITAAS, INCLUDING SITE DEVELOPMENT, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱19M | 100% | Medium risk48 | —-0.102 |
| 133 | 20OB0269CONSTRUCTION OF MULTI-PURPOSE BUILDING AT PLAINVIEW ELEMENTARY SCHOOL, MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.2M | 100% | Medium risk48 | —-0.104 |
| 134 | 23OG0019CONSTRUCTION OF DIALYSIS CENTER, BARANGAY DOÑA IMELDA, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.103 |
| 135 | 21GB0040CONSTRUCTION OF MPB, PANDAN CENTRAL SCHOOL, PANDAN, ANTIQUE | Region VI | Antique DEO | Completed | ₱19.6M | 100% | Medium risk48 | —-0.070 |
| 136 | 21IL0044BRIDGES - RETROFITTING/STRENGTHENING OF PERMANENT WEAK BRIDGES NURSERY BRIDGE (B00637LT) ALONG BDRY ABUYOG - SILAGO ROAD, SILAGO, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱12.2M | 100% | Medium risk48 | —-0.058 |
| 137 | 20OG0074CONSTRUCTION OF 2 STOREY MULTI-PURPOSE BUILDING, BARANGAY SAN VICENTE, QUEZON CITY | National Capital Region | Quezon City 2nd DEO | Completed | ₱7.4M | 100% | Medium risk48 | —-0.103 |
| 138 | 23A00166CONSTRUCTION OF MISSING LINKS/ NEW ROADS - SANTOL-SAN GABRIEL (LA UNION) - KAPANGAN (BENGUET) ROAD, LA UNION | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk48 | —-0.084 |
| 139 | 23A00165CONSTRUCTION OF MISSING LINKS/ NEW ROADS, SANTOL (LA UNION) - KIBUNGAN (BENGUET) ROAD, LA UNION | Region I | Region I | Completed | ₱48.2M | 100% | Medium risk48 | —-0.085 |
| 140 | 20DI0005RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - CABUYAO BR. (B03127LZ) ALONG MANILA SOUTH RD. | Region IV-A | Laguna 2nd DEO | Completed | ₱27.9M | 100% | Medium risk48 | —-0.069 |
| 141 | 23DO0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - SN MATEO - RODRIGUEZ RD - K0030+400 - K0032+000 | Region IV-A | Rizal 2nd DEO | On-Going | ₱46.1M | 79% | Medium risk48 | —-0.053 |
| 142 | 21OB0090CONSTRUCTION OF MULTI-PURPOSE BUILDING, NAPINDAN, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.5M | 100% | Medium risk48 | —-0.088 |
| 143 | 23DO0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF ROAD, F. RODRIGUEZ ST. .. | Region IV-A | Rizal 2nd DEO | On-Going | ₱38.8M | 100% | Medium risk47 | —-0.058 |
| 144 | 21IL0091CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ACCESS ROAD LEADING TO OLLIES WALL DIVE SITE, LILOAN, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.092 |
| 145 | 21IL0172NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG DAANG MAHARLIKA LT, SOGOD, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱9.6M | 100% | Medium risk47 | —-0.094 |
| 146 | 21OH0004LOCAL PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTII-PURPOSE/FACILITIES-CONST/REPAIR/REHAB/IMPV'T OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-REHAB. OF MULTI-PURPOSE/FACILITIES QUIRINO GRANDSTAND, ERMITA,MANILA | National Capital Region | South Manila DEO | Completed | ₱5.1M | 100% | Medium risk47 | —-0.100 |
| 147 | 21OB0275CONSTRUCTION/REHABILITATION OF TWINVILLE SUBDIVISION MULTI-PURPOSE BUILDING, BARANGAY CONCEPCION UNO, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.100 |
| 148 | 22OB0231CONSTRUCTION OF ST. MARY MULTI-PURPOSE BUILDING, PHASE 3, BARANGAY NANGKA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.101 |
| 149 | 24OD0215PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG C-3 ROAD, K0009 + 000 - K0008 - 265 | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱43.2M | 38% | Medium risk47 | —-0.043 |
| 150 | 22OH0124CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)- MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES STRUCTURAL AND RESILIENCE PROGRAM-REHABILITATION OF LUKBAN ELEM. SCHOOL, PACO, MANILA | National Capital Region | South Manila DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.102 |