Opening the dossier…
Opening the dossier…
Contractor dossier
10 projects on file, including joint ventures this contractor is part of.
Total projects
10
Total budget
₱367.5M
Average progress
73.2%
Completion rate
60.0%
Below 70%
Average risk score
58.3
Medium risk on average, out of 100
Flagged as unusual
2
20.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 6 | ₱299.8M | 63.6 | 1 | 82.3% |
| Region IV-B | 4 | ₱67.7M | 50.4 | 1 | 59.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱108.5M | 50.1 | 0 | 100.0% |
| Bridges | 3 | ₱140M | 46.8 | 1 | 43.9% |
| GAA 2025 SSP | 1 | ₱14.3M | 93.1 | 1 | 6.7% |
| GAA 2025 OO-1 | 1 | ₱33M | 91.1 | 0 | 93.8% |
| OTHER | 1 | ₱40.2M | 66.1 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱31.6M | 42.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0099REHABILITATION OF BRIDGE, KABILANG IBAYO, BARANGAY BATUHAN, POLA, ORIENTALMINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱14.3M | 7% | High risk93 | Flagged0.032 |
| 25DE0045ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, BAUAN-MABINI RD - K0160+500 - K0161+000, K0164+000 - K0164+316 | Region IV-A | Batangas 2nd DEO | On-Going | ₱33M | 94% | High risk91 | —-0.013 |
| 16DE0183MFO-1 NATIONAL ROAD NETWORK SERVICES, CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGE 1 TO MORE THAN 2 LANES LAGNAS BR. (B02922LZ) ALONG PALICO-BALAYAN-BATANGAS ROAD. | Region IV-A | Batangas 2nd DEO | Completed | ₱40.2M | 100% | High risk66 | —-0.036 |
| 16DE0150MFO1 - NATIONAL ROAD NETWORK SERVICES, ASSETS PRESERVATION OF NATIONAL ROADSREHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADSINCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAYDEVELOPMENT AND MANAGEMENT-4 (HDM-4), SE | Region IV-A | Batangas 2nd DEO | Completed | ₱31.7M | 100% | High risk65 | —-0.072 |
| 23DE0140OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE J, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱96.5M | 0% | High risk63 | Flagged0.013 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0099REHABILITATION OF BRIDGE, KABILANG IBAYO, BARANGAY BATUHAN, POLA, ORIENTALMINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱14.3M | 7% | High risk93 | Flagged0.032 |
| 23DE0140OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE J, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱96.5M | 0% | High risk63 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25ED0099REHABILITATION OF BRIDGE, KABILANG IBAYO, BARANGAY BATUHAN, POLA, ORIENTALMINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱14.3M | 7% | High risk93 | Flagged0.032 |
| 2 | 25DE0045ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, BAUAN-MABINI RD - K0160+500 - K0161+000, K0164+000 - K0164+316 | Region IV-A | Batangas 2nd DEO | On-Going | ₱33M | 94% | High risk91 | —-0.013 |
| 3 | 16DE0183MFO-1 NATIONAL ROAD NETWORK SERVICES, CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGE 1 TO MORE THAN 2 LANES LAGNAS BR. (B02922LZ) ALONG PALICO-BALAYAN-BATANGAS ROAD. | Region IV-A | Batangas 2nd DEO | Completed | ₱40.2M | 100% | High risk66 | —-0.036 |
| 4 | 16DE0150MFO1 - NATIONAL ROAD NETWORK SERVICES, ASSETS PRESERVATION OF NATIONAL ROADSREHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADSINCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAYDEVELOPMENT AND MANAGEMENT-4 (HDM-4), SE | Region IV-A | Batangas 2nd DEO | Completed | ₱31.7M | 100% | High risk65 | —-0.072 |
| 5 | 23DE0140OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BATANGAS CITY-SAN PASCUAL-BAUAN DIVERSION ROAD, PACKAGE J, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱96.5M | 0% | High risk63 | Flagged0.013 |
| 6 | 24DE0013ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE, SECONDARY ROADS, PALICO-BALAYAN-BATANGAS - RD K0141+(-735) - K0141+(-013) | Region IV-A | Batangas 2nd DEO | Completed | ₱66.9M | 100% | Medium risk54 | —-0.102 |
| 7 | 17DE0082CY 2017 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 4 STY 12 CL AT ALANGILAN SENIOR HIGH SCHOOL, BATANGAS CITY (CAPITAL), BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱31.6M | 100% | Medium risk42 | —-0.027 |
| 8 | 25ED0112CONSTRUCTION OF KABILANG IBAYO BRIDGE, BRGY. BATUHAN, POLA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱33.6M | 32% | Medium risk39 | —-0.018 |
| 9 | 24ED0098REHABILITATION OF KABILANG IBAYO BRIDGE, BRGY. BATUHAN, POLA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱9.9M | 100% | Medium risk38 | —-0.056 |
| 10 | 24ED0149CONCRETING OF BRGY. PUTING CACAO FMR, BRGY. PUTING CACAO, POLA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱9.9M | 100% | Medium risk32 | —-0.040 |