Contractor dossier
80 projects on file, including joint ventures this contractor is part of.
Total projects
80
Total budget
₱625.8M
Average progress
99.7%
Completion rate
96.3%
Average risk score
30.4
Medium risk on average, out of 100
Flagged as unusual
1
1.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 80 | ₱625.8M | 30.4 | 1 | 99.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 36 | ₱298.7M | 29.8 | 0 | 100.0% |
| Buildings and Facilities | 32 | ₱207M | 26.0 | 0 | 99.4% |
| Flood Control and Drainage | 4 | ₱65.7M | 33.9 | 0 | 100.0% |
| Bridges | 3 | ₱30.2M | 32.8 | 0 | 100.0% |
| OTHER | 2 | ₱18.4M | 75.9 | 0 | 99.8% |
| Water Provision and Storage | 2 | ₱2.9M | 27.7 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱3M | 88.4 | 1 | 91.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0169COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MASAGUISI, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱3M | 91% | High risk88 | Flagged0.010 |
| 25EI0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE - TRIP), INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA LEADING TO MANIHALA WATERFALLS II, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱9.7M | 100% | High risk76 | —-0.006 |
| 21EI0025ROAD WIDENING - SECONDARY ROADS - BONGABONG- SAGANA - ROXAS - SN AQUILINO RD - K0128 + 808 - K0129 + 059, ROXAS, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱8.8M | 100% | High risk76 | —-0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EI0169COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MASAGUISI, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱3M | 91% | High risk88 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EI0169COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MASAGUISI, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱3M | 91% | High risk88 | Flagged0.010 |
| 2 | 25EI0034CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE - TRIP), INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA LEADING TO MANIHALA WATERFALLS II, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱9.7M | 100% | High risk76 | —-0.006 |
| 3 | 21EI0025ROAD WIDENING - SECONDARY ROADS - BONGABONG- SAGANA - ROXAS - SN AQUILINO RD - K0128 + 808 - K0129 + 059, ROXAS, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱8.8M | 100% | High risk76 | —-0.027 |
| 4 | 23EI0072CONSTRUCTION OF MULTI-PURPOSE FACILITY (PINAMALAYAN MARKET), PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱49.5M | 100% | Medium risk43 | —-0.076 |
| 5 | 24EI0103CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | On-Going | ₱9.7M | 82% | Medium risk38 | —-0.042 |
| 6 | 20EI0026WIDENING OF PERMANENT BRIDGES, MATUOD - TUOD BR., (B00206MR) ALONG CALAPAN SOUTH ROAD, PINAMALAYAN, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱12.5M | 100% | Medium risk38 | —-0.054 |
| 7 | 18EI0024WIDENING OF PERMANENT BRIDGE LANGGANG BR. (B00038MR) ALONG CALAPAN SOUTH ROAD, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱13.5M | 100% | Medium risk38 | —-0.054 |
| 8 | 19EI0082CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES, (GABIONS), AT SAN ISIDRO, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱19.6M | 100% | Medium risk38 | —-0.076 |
| 9 | 24ED0145CONCRETING OF BRGY. CALIMA FMR, BRGY. CALIMA, POLA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱29.8M | 100% | Medium risk38 | —-0.036 |
| 10 | 23EI0020ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH ROAD - K0122+999 - K0123+772, BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱36.7M | 100% | Medium risk38 | —-0.093 |
| 11 | 21EI0157CONSTRUCTION OF BANSUD RIVER CONTROL, CONRAZON SECTION, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱19.6M | 100% | Medium risk37 | —-0.076 |
| 12 | 20EI0109CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALITE RIVER, BRGY. M. ADRIATICO, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱24.5M | 100% | Medium risk37 | —-0.076 |
| 13 | 24ED0053CONSTRUCTION OF ROAD, SITIO BAGONG POOK, PANIKIAN, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱4.9M | 100% | Medium risk37 | —-0.091 |
| 14 | 22EI0079CONSTRUCTION OF ROAD, BARANGAY MALO, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4.8M | 100% | Medium risk37 | —-0.092 |
| 15 | 23ED0049CONSTRUCTION OF ROAD AT PALHI - SAPUL, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱19.6M | 100% | Medium risk37 | —-0.094 |
| 16 | 21EI0132CONSTRUCTION OF MULTI - PURPOSE BUILDING (BARANGAY HALL) AT BONGABONG, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱26.5M | 100% | Medium risk37 | —-0.086 |
| 17 | 18EI0033PREVENTIVE MAINTENANCE OF SECONDARY ROADS MOOECR (K0190+530 - K0190+733, K0193+000 - K0193+229 AND K0199+730 - K0200+000), BULALACAO, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱6M | 100% | Medium risk37 | —-0.091 |
| 18 | 22EI0073CONSTRUCTION OF ROAD AT BARANGAY SALCEDO, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱4.8M | 100% | Medium risk37 | —-0.091 |
| 19 | 22EI0025CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - BRGY. MALUBAY TO BRGY. BUONG LUPA LEADING TO WALANG LANGIT FALLS, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱15.8M | 100% | Medium risk37 | —-0.093 |
| 20 | 21EI0047CONSTRUCTION/IMPROVEMENT ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS BRGY. BUONG LUPA LEADING TO WALANG LANGIT FALLS, PACKAGE II, GLORIA, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱14.7M | 100% | Medium risk37 | —-0.093 |
| 21 | 24EI0027CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA, LEADING TO MANIHALA WATERFALLS II, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱14.7M | 100% | Medium risk37 | —-0.093 |
| 22 | 25ED0047REHABILITATION OF ROAD, SITIO BABALOAN, BARANGAY POBLACION III, VICTORIA,ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱4.9M | 100% | Medium risk37 | —-0.092 |
| 23 | 21EI0048CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION - INTERNAL ACCESS ROAD TO SITIO PALAMANG, MANIHALA LEADING TO MANIHALAWATERFALLS II, BANSUD, ORIENTAL MINDORO, PACKAGE II, BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱14.2M | 100% | Medium risk37 | —-0.092 |
| 24 | 23ED0020ROAD WIDENING ALONG CSR JCT - MINAS RD - K0036+012 - K0036+101, K0036+387 - K0036+776, VICTORIA, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱12.1M | 100% | Medium risk37 | —-0.093 |
| 25 | 24EI0106CONSTRUCTION OF MULTI- PURPOSE BUILDING (MUNICIPAL GYMNASIUM), BANSUD, ORIENTAL MINDORO | Region IV-B | Southern Mindoro DEO | Completed | ₱9.9M | 100% | Medium risk37 | —-0.086 |