Opening the dossier…
Opening the dossier…
Contractor dossier
365 projects on file, including joint ventures this contractor is part of.
Total projects
365
Total budget
₱2.5B
Average progress
93.9%
Completion rate
87.7%
Average risk score
37.7
Medium risk on average, out of 100
Flagged as unusual
3
0.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 363 | ₱2.4B | 37.8 | 3 | 93.9% |
| Region IV-B | 2 | ₱28.1M | 35.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 165 | ₱1.1B | 38.4 | 0 | 93.8% |
| Roads | 107 | ₱789.9M | 36.7 | 1 | 97.6% |
| Water Provision and Storage | 52 | ₱202.5M | 33.7 | 0 | 94.6% |
| Flood Control and Drainage | 33 | ₱322.7M | 39.5 | 0 | 82.5% |
| OTHER | 3 | ₱20.2M | 63.9 | 1 | 93.3% |
| Bridges | 3 | ₱8.2M | 30.8 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱19.2M | 94.3 | 1 | 59.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DE0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER WORKS AT BRGY SAN MIGUEL, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱4.8M | 90% | High risk95 | —-0.003 |
| 25DE0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO KALINGAG, APAR, LOB | Region IV-A | Batangas 2nd DEO | On-Going | ₱14.4M | 29% | High risk94 | Flagged0.015 |
| 24D00266CONCRETING OF FARM TO MARKET ROAD BARANGAY NAGTOCTOC, LOBO, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱14.7M | 80% | High risk86 | Flagged0.040 |
| 25DB0154CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUIDLING (COVERED COURT), BRGY. CALOOCAN, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 26% | High risk75 | —-0.017 |
| 25DC0172CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROADS, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.6M | 70% | High risk65 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00266CONCRETING OF FARM TO MARKET ROAD BARANGAY NAGTOCTOC, LOBO, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱14.7M | 80% | High risk86 | Flagged0.040 |
| 24DE0244CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY TABANGAO, A | Region IV-A | Batangas 2nd DEO | On-Going | ₱46.7M | 8% | Medium risk51 | Flagged0.019 |
| 25DE0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO KALINGAG, APAR, LOB | Region IV-A | Batangas 2nd DEO | On-Going | ₱14.4M | 29% | High risk94 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 22DE0008CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY TALAHIB PANDAYAN, BATANGAS CITY, BATAN | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.103 |
| 152 | 24DE0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY NATUNUAN SOUTH, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.103 |
| 153 | 24DE0112CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN MARIANO, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.104 |
| 154 | 24DE0054CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MASAGUITSIT, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 155 | 23DE0013CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROAD, SITIO BUGTONG NA RUHAT, BARANGAY SAN MIGUEL, | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 156 | 24DE0004CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MALALIM NA SANOG, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 157 | 21DE0012LOCAL INFRASTRUCTURE PROGRAM-CONCRETING OF ROAD,SITIO BALOGBOG,BARANGAY SAN ISIDRO,BATANGAS CITY,BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 158 | 22DE0097CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY BALAGTASIN, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 159 | 25DB0050CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE IN NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱10.8M | 53% | Medium risk46 | —-0.035 |
| 160 | 18DD0433LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, A.) CONCRETING OF ROAD, BRGY. GUINHAWA B.) ROAD CONCRETING, BRGY. BACAO C.) ROAD CONCRETING, BRGY. MABAYABAS D.) ROAD CONCRETING, SAN ISIDRO, TAYSAN, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱6.7M | 100% | Medium risk46 | —-0.105 |
| 161 | 22DE0082CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY SULOC, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.108 |
| 162 | 22DE0053CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, MUNICIPALITY OF LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱11.9M | 100% | Medium risk46 | —-0.109 |
| 163 | 17DE0036LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTIPURPOSE BUILDING, DELA PAZ PULOT APLAYA, BATANGAS CITY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱2M | 100% | Medium risk46 | —-0.074 |
| 164 | 24DE0027CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MALAPAD NA PARANG, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 165 | 24DE0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN FRANCISCO, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.102 |
| 166 | 24DE0037CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY GAMAO, TINGLOY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.101 |
| 167 | 22DE0071CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, MUNICIPALITY OF TINGLOY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.108 |
| 168 | 24DE0074CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, PHASE 2, SITIO BAGONG POOK, BARANGAY MALABRIGO, | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.105 |
| 169 | 21DB0099CONCRETING OF ROAD, BARANGAY PANTAY, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.104 |
| 170 | 20DB0122CONCRETING OF LOCAL ROAD, BRGY. POBLACION IV, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱9.9M | 100% | Medium risk45 | —-0.104 |
| 171 | 23DB0019(SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF PALICO RIVER IRRIGATION SYSTEM SERVICE ROAD, BARANGAY BUNGAHAN, LIAN, BATANGAS (KATUBIGAN - KALSADA TUNGO SA PATUBI | Region IV-A | Batangas 1st DEO | Completed | ₱5.2M | 100% | Medium risk45 | —-0.104 |
| 172 | 20DE0158CONSTRUCTION OF MPB FOR THE PROVINCIAL CAPITOL SITE, BATANGAS CITY (PHASE 2) | Region IV-A | Batangas 2nd DEO | Completed | ₱4.8M | 100% | Medium risk45 | —-0.061 |
| 173 | 18DE0224CY 2018 BASIC EDUCATIONAL FACILITIES FUND BATCH 1 - CONSTRUCTION OF 4STY 8CL AT BANABA WEST NHS, BATANGAS CITY (CAPITAL), BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱17.5M | 100% | Medium risk45 | —-0.058 |
| 174 | 23DE0158CY 2023 BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 1: CONSTRUCTION OF 2STY4CL AT SAN TEODORO ELEMENTARY SCHOOL | Region IV-A | Batangas 2nd DEO | Completed | ₱18.5M | 100% | Medium risk45 | —-0.057 |
| 175 | 19DE0198CY 2019 BASIC EDUCATIONAL FACILITIES FUND - CONSTRUCTION OF 4STY 8CL AT TABANGAO SENIOR HIGH SCHOOL, BATANGAS CITY (CAPITAL), BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱17.5M | 100% | Medium risk45 | —-0.054 |