Opening the dossier…
Opening the dossier…
Contractor dossier
365 projects on file, including joint ventures this contractor is part of.
Total projects
365
Total budget
₱2.5B
Average progress
93.9%
Completion rate
87.7%
Average risk score
37.7
Medium risk on average, out of 100
Flagged as unusual
3
0.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 363 | ₱2.4B | 37.8 | 3 | 93.9% |
| Region IV-B | 2 | ₱28.1M | 35.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 165 | ₱1.1B | 38.4 | 0 | 93.8% |
| Roads | 107 | ₱789.9M | 36.7 | 1 | 97.6% |
| Water Provision and Storage | 52 | ₱202.5M | 33.7 | 0 | 94.6% |
| Flood Control and Drainage | 33 | ₱322.7M | 39.5 | 0 | 82.5% |
| OTHER | 3 | ₱20.2M | 63.9 | 1 | 93.3% |
| Bridges | 3 | ₱8.2M | 30.8 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱19.2M | 94.3 | 1 | 59.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DE0116CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER WORKS AT BRGY SAN MIGUEL, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱4.8M | 90% | High risk95 | —-0.003 |
| 25DE0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO KALINGAG, APAR, LOB | Region IV-A | Batangas 2nd DEO | On-Going | ₱14.4M | 29% | High risk94 | Flagged0.015 |
| 24D00266CONCRETING OF FARM TO MARKET ROAD BARANGAY NAGTOCTOC, LOBO, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱14.7M | 80% | High risk86 | Flagged0.040 |
| 25DB0154CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUIDLING (COVERED COURT), BRGY. CALOOCAN, BALAYAN, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 26% | High risk75 | —-0.017 |
| 25DC0172CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROADS, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.6M | 70% | High risk65 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00266CONCRETING OF FARM TO MARKET ROAD BARANGAY NAGTOCTOC, LOBO, BATANGAS | Region IV-A | Region IV-A | On-Going | ₱14.7M | 80% | High risk86 | Flagged0.040 |
| 24DE0244CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY TABANGAO, A | Region IV-A | Batangas 2nd DEO | On-Going | ₱46.7M | 8% | Medium risk51 | Flagged0.019 |
| 25DE0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO KALINGAG, APAR, LOB | Region IV-A | Batangas 2nd DEO | On-Going | ₱14.4M | 29% | High risk94 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 201 | 20DE0184CONCRETING OF BRGY. MANALUPANG FMR, BRGY. MANALUPANG, BAUAN, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱10M | 100% | Medium risk43 | —-0.056 |
| 202 | 20DE0183CONCRETING OF BRGY. SAN DIEGO FMR, BRGY. SAN DIEGO, BAUAN, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱10M | 100% | Medium risk43 | —-0.056 |
| 203 | 23DD0231CONCRETING OF BRGY. SAN ISIDRO FMR, BRGY. SAN ISIDRO, ROSARIO, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱10.6M | 100% | Medium risk43 | —-0.054 |
| 204 | 24DE0172CY 2024 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN TEODORO ELEMENTARY SCHOOL, BARANGAY SAN TEODORO, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.058 |
| 205 | 18DE0151OPENING AND CONCRETING OF BRGY. SAN JOSE SICO FMR, BARANGAY SAN JOSE SICO, BATANGAS CITY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.055 |
| 206 | 19DB0149CONCRETING OF BRGY. LUMBANG NA MATANDA FMR, BRGY. LUMBANG NA MATANDA, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.050 |
| 207 | 18DE0163CONCRETING OF BRGY. PADRE CASTILLO-SAN MATEO FMR, BRGY. PADRE CASTILLO AND BRGY. SAN MATEO, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.053 |
| 208 | 18DE0170CONCRETING OF BRGY. MALAPAD NA PARANG FMR, BRGY. MALAPAD NA PARANG, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.053 |
| 209 | 18DE0195OPENING AND CONCRETING OF BRGY. PILAHAN FMR, BRGY. PILAHAN, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.053 |
| 210 | 18DE0152CONCRETING OF BRGY. APAR FMR, BRGY. APAR, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.054 |
| 211 | 21DE0136CONCRETING OF BRGY. NATUNUAN SOUTH TO BRGY. KAINGIN FMR, BRGY. NATUNUAN SOUTH TO BRGY. KAINGIN, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱12.4M | 100% | Medium risk42 | —-0.055 |
| 212 | 22DE0138OPENING AND CONCRETING OF BRGY. TULO FMR, BRGY. TULO, BATANGAS CITY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱11.9M | 100% | Medium risk42 | —-0.056 |
| 213 | 17DE0062CY 2017 BASIC EDUCATIONAL FACILITIES FUND (BATCH 4), CONSTRUCTION OF 2 UNITS UNIQUE WORKSHOP (7 X 22.5) AT CONDE LABAC SHS, BATANGAS CITY (CAPITAL), BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5.3M | 100% | Medium risk42 | —-0.033 |
| 214 | 22DE0119CONCRETING OF BRGY. APAR FMR, BRGY. APAR, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱11.9M | 100% | Medium risk42 | —-0.049 |
| 215 | 19DB0153CONCRETING OF BRGY. LATAG FMR, BRGY. LATAG, NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.052 |
| 216 | 23DJ0139CONCRETING OF PUROK 1, BRGY. MANGILAG NORTE FMR, BRGY. MANGILAG NORTE, CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱11.9M | 100% | Medium risk42 | —-0.056 |
| 217 | 24DE0176CY 2024 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT JAYBANGA HIGH SCHOOL, BRGY. JAYBANGA, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.059 |
| 218 | 18DE0207CY 2018 BASIC EDUCATIONAL FACILITIES FUND BATCH 1 - CONSTRUCTION OF 2STY 4CL AT MASAGUITSIT ES, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱9.1M | 100% | Medium risk42 | —-0.060 |
| 219 | 17DE0070CY 2017 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2 STY 4 CL AT ILAT ELEMENTARY SCHOOL, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱9.4M | 100% | Medium risk42 | —-0.034 |
| 220 | 17DE0069CY 2017 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 2 STY 4 CL AT MALAKIMPOOK ELEMENTARY SCHOOL, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱8.9M | 100% | Medium risk42 | —-0.034 |
| 221 | 24DE0177CY 2024 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT BALIBAGO ELEMENTARY SCHOOL, BRGY. BALIBAGO, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.059 |
| 222 | 24DE0170CY 2024 BASIC EDUCATIONAL FACILITIES FUND, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING AT SOLOC ELEMENTARY SCHOOL, BRGY. SOLOC, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.060 |
| 223 | 18DE0215CY 2018 BASIC EDUCATIONAL FACILITIES FUND BATCH 1 - CONSTRUCTION OF 2STY 6CL AT SOLOC ELEMENTARY SCHOOL, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱12.2M | 100% | Medium risk41 | —-0.060 |
| 224 | 25DB0177CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CAWIT, TAAL, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱1.9M | 48% | Medium risk41 | —-0.026 |
| 225 | 18EB0201CONSTRUCTION OF TWO (2) STOREY, FOUR (4) WORKSHOP BUILDING, RIZAL, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱19.5M | 100% | Medium risk36 | —-0.041 |