Contractor dossier
57 projects on file, including joint ventures this contractor is part of.
Total projects
57
Total budget
₱1.2B
Average progress
73.8%
Completion rate
50.9%
Below 70%
Average risk score
51.8
Medium risk on average, out of 100
Flagged as unusual
4
7.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 54 | ₱1.1B | 52.2 | 4 | 74.2% |
| Cordillera Administrative Region | 2 | ₱49M | 44.4 | 0 | 100.0% |
| Region IV-A | 1 | ₱29.2M | 46.9 | 0 | 0.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Water Provision and Storage | 34 | ₱410.3M | 48.8 | 0 | 72.2% |
| Buildings and Facilities | 13 | ₱376M | 50.2 | 0 | 86.0% |
| Bridges | 3 | ₱173.9M | 53.7 | 1 | 87.2% |
| Flood Control and Drainage | 3 | ₱78.2M | 45.2 | 0 | 66.7% |
| GAA 2025 SSP | 2 | ₱25.2M | 94.0 | 2 | 31.1% |
| GAA 2025 OO-2 | 1 | ₱96.5M | 93.8 | 0 | 72.3% |
| OTHER | 1 | ₱11.8M | 63.0 | 1 | 37.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HD0160CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY BAIRAN, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 25HD0175CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY SANGAT, SAN FERNANDO, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 25HD0095ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD MITIGATION STRUCTURE ALONG NAGA RIVER, BRGY MAINIT (DOWNSTREAM), NAG | Region VII | Cebu 1st DEO | On-Going | ₱96.5M | 72% | High risk94 | —-0.004 |
| 24HA0131CONSTRUCTION OF TAGBILARAN CITY WHARP PORT TO PICR SONGCULAN - TOTOLAN, DAUIS, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱144.5M | 62% | High risk66 | Flagged0.009 |
| 24HN0206CSSP: CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SYSTEM - CONSTRUCTION OF WATER PUMPING STATION AT MAGUIKAY, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱11.8M | 38% | High risk63 | Flagged0.017 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HD0160CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY BAIRAN, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 25HD0175CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY SANGAT, SAN FERNANDO, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 24HN0206CSSP: CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SYSTEM - CONSTRUCTION OF WATER PUMPING STATION AT MAGUIKAY, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱11.8M | 38% | High risk63 | Flagged0.017 |
| 24HA0131CONSTRUCTION OF TAGBILARAN CITY WHARP PORT TO PICR SONGCULAN - TOTOLAN, DAUIS, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱144.5M | 62% | High risk66 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HD0160CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY BAIRAN, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 2 | 25HD0175CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY SANGAT, SAN FERNANDO, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 31% | High risk94 | Flagged0.027 |
| 3 | 25HD0095ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD MITIGATION STRUCTURE ALONG NAGA RIVER, BRGY MAINIT (DOWNSTREAM), NAG | Region VII | Cebu 1st DEO | On-Going | ₱96.5M | 72% | High risk94 | —-0.004 |
| 4 | 24HA0131CONSTRUCTION OF TAGBILARAN CITY WHARP PORT TO PICR SONGCULAN - TOTOLAN, DAUIS, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱144.5M | 62% | High risk66 | Flagged0.009 |
| 5 | 24HN0206CSSP: CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SYSTEM - CONSTRUCTION OF WATER PUMPING STATION AT MAGUIKAY, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱11.8M | 38% | High risk63 | Flagged0.017 |
| 6 | 24HF0033CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DUMLOG, TOLEDO CITY, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱29.7M | 100% | Medium risk51 | —-0.084 |
| 7 | 24HH0099CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. BASAK SAN NICOLAS, CEBU CITY | Region VII | Cebu City DEO | On-Going | ₱29.7M | 87% | Medium risk51 | —-0.043 |
| 8 | 24HF0093CONSTRUCTION OF MULTI - PURPOSE BUILDING (EVACUATION CENTER), BRGY. BOLOCBOLOC, BARILI, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱29.7M | 100% | Medium risk51 | —-0.089 |
| 9 | 24HF0048CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), SITIO SAN JUAN, SAN JUAN, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱29.7M | 100% | Medium risk51 | —-0.089 |
| 10 | 24HN0171CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. NANGKA, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱29.7M | 99% | Medium risk50 | —-0.051 |
| 11 | 24HG0104CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. USMAD, ARGAO, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱29.7M | 100% | Medium risk50 | —-0.052 |
| 12 | 24HE0134CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), POBLACION, SIBONGA, CEBU | Region VII | Cebu 1st DEO | Completed | ₱29.7M | 100% | Medium risk50 | —-0.090 |
| 13 | 25HD0154CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY CALIDNGAN (COVERED COURT) CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.9M | 46% | Medium risk50 | —-0.019 |
| 14 | 25HD0161CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY INUBURAN, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 44% | Medium risk50 | —-0.019 |
| 15 | 25HD0166CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY CABUNGAHAN, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 47% | Medium risk50 | —-0.019 |
| 16 | 25HD0155CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY WEST POBLACION, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.9M | 42% | Medium risk50 | —-0.018 |
| 17 | 25HD0149CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY EAST POBLACION, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 46% | Medium risk50 | —-0.018 |
| 18 | 25HD0173CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY CENTRAL POBLACION, NAGA CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 81% | Medium risk50 | —-0.026 |
| 19 | 25HO0156CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY LAWAAN, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱12.6M | 5% | Medium risk50 | —-0.005 |
| 20 | 25HO0144CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY POBLACION EAST, MOALBOAL, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱12.6M | 10% | Medium risk50 | —-0.006 |
| 21 | 25HO0171CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY LIONG, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱12.6M | 10% | Medium risk50 | —-0.007 |
| 22 | 25HO0170CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY CAMBOANG, DUMANJUG, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱12.6M | 10% | Medium risk50 | —-0.007 |
| 23 | 25HD0150CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY VALENCIA (COVERED COURT), CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 46% | Medium risk50 | —-0.019 |
| 24 | 25HD0151CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY NAPO, CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 49% | Medium risk50 | —-0.020 |
| 25 | 25HD0174CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY POBLACION 2, CARCAR CITY, CEBU | Region VII | Cebu 1st DEO | On-Going | ₱12.6M | 81% | Medium risk50 | —-0.027 |