Opening the dossier…
Opening the dossier…
Contractor dossier
25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱1.5B
Average progress
100.0%
Completion rate
100.0%
Average risk score
41.2
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 23 | ₱1.3B | 38.6 | 0 | 100.0% |
| Central Office | 2 | ₱110.1M | 71.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 12 | ₱452.7M | 36.1 | 0 | 100.0% |
| Buildings and Facilities | 8 | ₱623.1M | 46.3 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱203M | 46.8 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱142.7M | 53.7 | 0 | 100.0% |
| Roads | 1 | ₱30.1M | 32.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17CG0083LAHAR CONTROL WORKS IN PASIG-POTRERO/GUGU RIVER STA. 0+188-STA. 2+100 GUGU RIVER STA. 2+300-STA.2+700 MINALIN TAIL DIKE, STA. 2+125.24-STA. 0+715 WEST MEGA DIKE, BACOLOR, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱95M | 100% | High risk75 | —-0.067 |
| 17CI0017CONST AND MAINT OF BRIDGES ALONG NATL ROADS WIDENING OF PERMANENT BRIDGES, INCL ROW TO MORE THAN 2 L | Region III | Region III | Completed | ₱122.5M | 100% | High risk71 | —-0.013 |
| 17Z00027CONSTRUCTION OF THE SUPPLEMENTAL WORKS (E.G. CONSTRUCTION OF BRS LABORATORY BUILDING, CAR PORT, SITE DEVELOPMENT, VOICE AND DATA WORKS, MERALCO POWER PERMANENT CONNECTION AND MANILA WATER SUPPLY PERMANENT CONNECTION) FOR THE THREE (3) STOREY BUREAU OF RES | Central Office | Bureau of Construction | Completed | ₱15.1M | 100% | High risk67 | —-0.098 |
| 17CG0052CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-REPLACEMENT OF PERMANENT WEAK BRIDGES AT BAHAY PARE BRIDGE ALONG BALIWAG-CANDABA-STA. ANA ROAD, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱32.1M | 100% | High risk60 | —-0.039 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17CG0083LAHAR CONTROL WORKS IN PASIG-POTRERO/GUGU RIVER STA. 0+188-STA. 2+100 GUGU RIVER STA. 2+300-STA.2+700 MINALIN TAIL DIKE, STA. 2+125.24-STA. 0+715 WEST MEGA DIKE, BACOLOR, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱95M | 100% | High risk75 | —-0.067 |
| 2 | 17CI0017CONST AND MAINT OF BRIDGES ALONG NATL ROADS WIDENING OF PERMANENT BRIDGES, INCL ROW TO MORE THAN 2 L | Region III | Region III | Completed | ₱122.5M | 100% | High risk71 | —-0.013 |
| 3 | 17Z00027CONSTRUCTION OF THE SUPPLEMENTAL WORKS (E.G. CONSTRUCTION OF BRS LABORATORY BUILDING, CAR PORT, SITE DEVELOPMENT, VOICE AND DATA WORKS, MERALCO POWER PERMANENT CONNECTION AND MANILA WATER SUPPLY PERMANENT CONNECTION) FOR THE THREE (3) STOREY BUREAU OF RES | Central Office | Bureau of Construction | Completed | ₱15.1M | 100% | High risk67 | —-0.098 |
| 4 | 17CG0052CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-REPLACEMENT OF PERMANENT WEAK BRIDGES AT BAHAY PARE BRIDGE ALONG BALIWAG-CANDABA-STA. ANA ROAD, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱32.1M | 100% | High risk60 | —-0.039 |
| 5 | 19C00019NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD (PACKAGE 2), PROVINCE OF ZAMBALES | Region III | Region III | Completed | ₱142.7M | 100% | Medium risk54 | —-0.055 |
| 6 | 24CG0315SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES STRUCTURAL AND RESILIENCE PROGRAM - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVENTION CENTER) INCLUDING SITE DEVELOPMENT, SAN FERNAND | Region III | Pampanga 1st DEO | Completed | ₱187.2M | 100% | Medium risk51 | —-0.067 |
| 7 | 19CM0060REPAIR AND REHABILITATION OF SUBIC BAY EXHIBITION AND CONVENTION CENTER (SBECC), SUBIC BAY FREEPORT ZONE | Region III | Zambales 2nd DEO | Completed | ₱92.6M | 100% | Medium risk50 | —-0.079 |
| 8 | 20CG0267LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVENTION CENTER), PHASE II, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱95M | 100% | Medium risk49 | —-0.082 |
| 9 | 23CG0090SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVENTION CENTER) INCLUDING SITE DEVELOPMENT, SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱93.7M | 100% | Medium risk49 | —-0.082 |
| 10 | 21CG0265LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVENTION CENTER - PHASE III), SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱47.7M | 100% | Medium risk37 | —-0.098 |
| 11 | 19CG0201CONSTRUCTION OF MULTI-PURPOSE BUILDING (CONVENTION CENTER), SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱47.5M | 100% | Medium risk36 | —-0.098 |
| 12 | 18CG0210CONSTRUCTION OF SLOPE PROTECTION AT CALULUT SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱54.9M | 100% | Medium risk33 | —-0.090 |
| 13 | 20CG0087FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION/ RESTORATION OF SLOPE PROTECTION ALONG SAPANG BALEN (RIGHT SIDE FACING DOWNSTREAM) BRGY. PULUNGBULU, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱53.1M | 100% | Medium risk33 | —-0.086 |
| 14 | 19CG0167CONSTRUCTION OF BRIDGE AT TALBA-MESALIPIT, BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT) | Region III | Pampanga 1st DEO | Completed | ₱47M | 100% | Medium risk32 | —-0.057 |
| 15 | 19CG0168CONSTRUCTION OF BRIDGE AT TINAJERO-TALBA, BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT) | Region III | Pampanga 1st DEO | Completed | ₱47M | 100% | Medium risk32 | —-0.066 |
| 16 | 18CG0364CONSTRUCTION OF DELA PAZ SUR - DELA PAZ NORTE - SAGUIN - LARA BYPASS ROAD (LEADING TO MNR), CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱30.1M | 100% | Medium risk32 | —-0.103 |
| 17 | 20CM0056ADDITIONAL WORKS FOR REPAIR AND REHABILITATION OF SUBIC BAY, EXHIBITION AND CONVENTION CENTER (SBECC), SUBIC BAY FREEPORT ZONE | Region III | Zambales 2nd DEO | Completed | ₱44.1M | 100% | Medium risk31 | —-0.036 |
| 18 | 18CI0066LOCAL PROGRAM:CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS;LOCAL ROADS AND BRIDGES,LOCAL BRIDGES;REPLACEMENT OF PULUNG CACUTUD BRIDGE ALONG ANGELES-MAGALANG ROAD, ANGELES CITY PAMPANGA | Region III | Pampanga 3rd DEO | Completed | ₱24.4M | 100% | Low risk30 | —-0.059 |
| 19 | 23CG0104SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TALBA-MESALIPIT BRIDGE INCLUDING SLOPE PROTECTION, BACOLOR, PAMPA | Region III | Pampanga 1st DEO | Completed | ₱28.4M | 100% | Low risk30 | —-0.067 |
| 20 | 22CG0038SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF BRIDGE AT TALBA - MESALIPIT, BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱28.4M | 100% | Low risk30 | —-0.067 |
| 21 | 22CG0037SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF BRIDGE AT TINAJERO - TALBA, INCLUDING APPROACHES, BACOLO | Region III | Pampanga 1st DEO | Completed | ₱28.4M | 100% | Low risk30 | —-0.067 |
| 22 | 20CG0026BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES-LAGUNDI BR. (B01477LZ) ALONG JOSE ABAD SANTOS AVE. (JASA), MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱37.6M | 100% | Low risk30 | —-0.062 |
| 23 | 21CG0214CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS: LOCAL ROADS AND BRIDGES-COMPLETION OF BRIDGE AT TALBA - MESALIPIT, BACOLOR, PAMPANGA (R.A. 9506 - BACOLOR REHABILITATION ACT) BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱18.9M | 100% | Low risk30 | —-0.066 |
| 24 | 21CG0213CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS: LOCAL ROADS AND BRIDGES-COMPLETION OF BRIDGE AT TINAJERO - TALBA, INCLUDING APPROACHES AND SLOPE PROTECTION, BACOLOR, PAMPANGA (R.A. 9506 - BACOLOR RE | Region III | Pampanga 1st DEO | Completed | ₱18.9M | 100% | Low risk30 | —-0.066 |
| 25 | 23CG0135SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF TINAJERO - TALBA BRIDGE, BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱19M | 100% | Low risk30 | —-0.068 |