Contractor dossier
171 projects on file, including joint ventures this contractor is part of.
Total projects
171
Total budget
₱6.5B
Average progress
99.2%
Completion rate
95.9%
Average risk score
48.6
Medium risk on average, out of 100
Flagged as unusual
6
3.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 57 | ₱1.8B | 46.4 | 0 | 100.0% |
| Region IV-A | 53 | ₱1.9B | 52.7 | 1 | 100.0% |
| Region III | 16 | ₱602.7M | 50.2 | 0 | 100.0% |
| Region XI | 11 | ₱709.3M | 51.1 | 2 | 97.0% |
| Region XIII | 11 | ₱427.3M | 47.1 | 1 | 100.0% |
| Region VIII | 9 | ₱414.4M | 50.6 | 0 | 100.0% |
| Region XII | 7 | ₱482.4M | 45.6 | 1 | 85.7% |
| Region X | 5 | ₱43.9M | 20.3 | 0 | 100.0% |
| Negros Island Region | 1 | ₱13.9M | 64.7 | 0 | 100.0% |
| Region II | 1 | ₱44.7M | 57.4 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 50 | ₱1.9B | 49.5 | 1 | 100.0% |
| Roads | 49 | ₱1.8B | 47.8 | 0 | 99.5% |
| Buildings and Facilities | 37 | ₱1.2B | 41.3 | 2 | 100.0% |
| Bridges | 21 | ₱625.7M | 51.2 | 0 | 100.0% |
| OTHER | 12 | ₱572.7M | 63.1 | 1 | 91.7% |
| Bridges, Roads | 2 | ₱305.2M | 67.8 | 2 | 95.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18NC0067CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, NRJ HUBANG-MANAGBAY-ALEGRIA DIVERSION ROAD WITH BRIDGE INCLUDING ROW 0+000.00 - 2+000.00, SAN FRANCISCO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱95M | 100% | High risk79 | —-0.008 |
| 17CD0160CONSTRUCTION OF SAN RAFAEL GOVERNMENT CENTER ANNEX BUILDING, SAN RAFAEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱47.4M | 100% | High risk76 | —-0.068 |
| 18ND0071CONSTRUCTION OF URBAN DRAINAGE/FLOOD CONTROL PROJECT (VILLA KANANGA-LIBERTAD), AGUSAN DEL NORTE | Region XIII | Butuan City DEO | Completed | ₱29.2M | 100% | High risk74 | —-0.031 |
| 22M00060OFF-CARRIAGEWAY IMPROVEMENT - MARBEL-MAKAR RD - K1664+000 - K1665+487, K1667+038 K1667+670, K1667+780 - K1671+980, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱91.6M | 0% | High risk73 | Flagged0.058 |
| 18DF0079ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, TERTIARY ROADS, CRISANTO M DE LOS REYES AVE - K0055+753 - K0056+031, K0056+332 - K0057+505, K0059+033 - K0059+542, K0055+427 - K0056+031, | Region IV-A | Cavite 1st DEO | Completed | ₱92.4M | 100% | High risk73 | —-0.031 |
| 19DD0376ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, SN JUAN-LAIYA RD - K0144 + 710 - K0146 + 403 | Region IV-A | Batangas 4th DEO | Completed | ₱52.6M | 100% | High risk71 | —-0.041 |
| 17CD0064CONCRETING OF ACCESS ROAD LEADING TO PNP - PHILIPPINE ARMY, RESETTLEMENT AND HOUSING PROJECT, SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱47M | 100% | High risk70 | —-0.069 |
| 18DF0080LOCAL PROGRAM - CONSTRUCTION/REPAIR/ REHABILITATION/IMPROVEMENT OF VARIOUSINFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS,CONCRETING OF BARANGAY SAHUD ULAN - TRES CRUSES ROAD, KM. 41+236.29 - KM. 43+660,TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱91.6M | 100% | High risk69 | —-0.013 |
| 17CD0033IMPROVEMENT / REHABILITATION / REBLOCKING OF BRGY. FRANCISCO HOMES ROAD, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | High risk69 | —-0.070 |
| 17CD0081ASSET PRESERVATION OF NATIONAL ROADS CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUL-BIAK NA BATO ROAD K0089+000 - K0090+066 | Region III | Bulacan 2nd DEO | Completed | ₱18.6M | 100% | High risk69 | —-0.070 |
| 17DQ0023MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG SAMPALOC RIVER,PHASE II, EAST SIDE,BRGY. SAMPALOC I, DASMARINAS, CAVITE AND CONSTRUCTION OF REVETMENT ALONG | Region IV-A | Cavite 3rd DEO | Completed | ₱46.7M | 100% | High risk69 | —-0.059 |
| 17CD0017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER (PHASE I - RIGHT SIDE), STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱42.3M | 100% | High risk68 | —-0.062 |
| 17DF0005MFO2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINA | Region IV-A | Cavite 1st DEO | Completed | ₱37.5M | 100% | High risk68 | —-0.060 |
| 21L00071CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE D), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱168.7M | 98% | High risk68 | Flagged0.009 |
| 17DQ0008MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGESYSTEMS, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, STA.16+343 - STA. 16+843, WEST SIDE. BRGY. SALITRAN III,DASMARINAS, CAVITE, 4TH LD | Region IV-A | Cavite 3rd DEO | Completed | ₱46.4M | 100% | High risk68 | —-0.059 |
| 17DQ0009MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGESYSTEMS, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, STA.16+843 - STA. 17+343, WEST SIDE. BRGY. SALITRAN III,DASMARINAS, CAVITE, 4TH LD | Region IV-A | Cavite 3rd DEO | Completed | ₱46.5M | 100% | High risk68 | —-0.059 |
| 21L00072CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE E), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱136.5M | 93% | High risk68 | Flagged0.006 |
| 16HM0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT CANGMUNAG, SAN JUAN, SIQUIJOR LONE DISTRICT | Negros Island Region | Siquijor DEO | Completed | ₱13.9M | 100% | High risk65 | —-0.038 |
| 21L00073CONSTRUCTION OF GRAVEL ROAD - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE F), DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱130.7M | 100% | High risk63 | —-0.056 |
| 17DB0041CONST. AND MAINT. OF BRIDGES ALONG NATIONAL ROADS - WIDENING OF PERMANENT BRIDGES TO MORE THAN 2 LANES - SECONDARY, P00117145LZ, KASUYAN BR. (B00006LZ) ALONG PALICO-BALAYAN-BATANGAS RD., CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱48.1M | 100% | High risk62 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22M00060OFF-CARRIAGEWAY IMPROVEMENT - MARBEL-MAKAR RD - K1664+000 - K1665+487, K1667+038 K1667+670, K1667+780 - K1671+980, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱91.6M | 0% | High risk73 | Flagged0.058 |
| 18DF0143CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT FLORENTINO JOYA ES,TANZA, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱30.8M | 100% | Medium risk48 | Flagged0.017 |
| 17NE0149CONSTRUCTION OF 2 STOREY SCIENCE LABORATORY @ TUBAJON NHS, SCHOOL ID. 304854, TUBAJON, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Terminated | ₱11.2M | 100% | Medium risk41 | Flagged0.014 |
| 21L00071CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE D), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱168.7M | 98% | High risk68 | Flagged0.009 |
| 17BH0175REHABILITATION/IMPROVEMENT OF VARIOUS FLOOD CONTROL PROJECTS IN ISABELA - FLOOD CONTROL (STA. 0+000 - STA. 0+259.725 AND STA. 0+000 - STA. -0+432.645), CAMARAG | Region II | Isabela 4th DEO | Completed | ₱44.7M | 100% | Medium risk57 | Flagged0.009 |
| 21L00072CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE E), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱136.5M | 93% | High risk68 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18NC0067CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, NRJ HUBANG-MANAGBAY-ALEGRIA DIVERSION ROAD WITH BRIDGE INCLUDING ROW 0+000.00 - 2+000.00, SAN FRANCISCO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱95M | 100% | High risk79 | —-0.008 |
| 2 | 17CD0160CONSTRUCTION OF SAN RAFAEL GOVERNMENT CENTER ANNEX BUILDING, SAN RAFAEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱47.4M | 100% | High risk76 | —-0.068 |
| 3 | 18ND0071CONSTRUCTION OF URBAN DRAINAGE/FLOOD CONTROL PROJECT (VILLA KANANGA-LIBERTAD), AGUSAN DEL NORTE | Region XIII | Butuan City DEO | Completed | ₱29.2M | 100% | High risk74 | —-0.031 |
| 4 | 22M00060OFF-CARRIAGEWAY IMPROVEMENT - MARBEL-MAKAR RD - K1664+000 - K1665+487, K1667+038 K1667+670, K1667+780 - K1671+980, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱91.6M | 0% | High risk73 | Flagged0.058 |
| 5 | 18DF0079ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, TERTIARY ROADS, CRISANTO M DE LOS REYES AVE - K0055+753 - K0056+031, K0056+332 - K0057+505, K0059+033 - K0059+542, K0055+427 - K0056+031, | Region IV-A | Cavite 1st DEO | Completed | ₱92.4M | 100% | High risk73 | —-0.031 |
| 6 | 19DD0376ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, SN JUAN-LAIYA RD - K0144 + 710 - K0146 + 403 | Region IV-A | Batangas 4th DEO | Completed | ₱52.6M | 100% | High risk71 | —-0.041 |
| 7 | 17CD0064CONCRETING OF ACCESS ROAD LEADING TO PNP - PHILIPPINE ARMY, RESETTLEMENT AND HOUSING PROJECT, SAN MIGUEL, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱47M | 100% | High risk70 | —-0.069 |
| 8 | 18DF0080LOCAL PROGRAM - CONSTRUCTION/REPAIR/ REHABILITATION/IMPROVEMENT OF VARIOUSINFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS,CONCRETING OF BARANGAY SAHUD ULAN - TRES CRUSES ROAD, KM. 41+236.29 - KM. 43+660,TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱91.6M | 100% | High risk69 | —-0.013 |
| 9 | 17CD0033IMPROVEMENT / REHABILITATION / REBLOCKING OF BRGY. FRANCISCO HOMES ROAD, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.4M | 100% | High risk69 | —-0.070 |
| 10 | 17CD0081ASSET PRESERVATION OF NATIONAL ROADS CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUL-BIAK NA BATO ROAD K0089+000 - K0090+066 | Region III | Bulacan 2nd DEO | Completed | ₱18.6M | 100% | High risk69 | —-0.070 |
| 11 | 17DQ0023MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG SAMPALOC RIVER,PHASE II, EAST SIDE,BRGY. SAMPALOC I, DASMARINAS, CAVITE AND CONSTRUCTION OF REVETMENT ALONG | Region IV-A | Cavite 3rd DEO | Completed | ₱46.7M | 100% | High risk69 | —-0.059 |
| 12 | 17CD0017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. MARIA RIVER (PHASE I - RIGHT SIDE), STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱42.3M | 100% | High risk68 | —-0.062 |
| 13 | 17DF0005MFO2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINA | Region IV-A | Cavite 1st DEO | Completed | ₱37.5M | 100% | High risk68 | —-0.060 |
| 14 | 21L00071CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE D), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱168.7M | 98% | High risk68 | Flagged0.009 |
| 15 | 17DQ0008MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGESYSTEMS, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, STA.16+343 - STA. 16+843, WEST SIDE. BRGY. SALITRAN III,DASMARINAS, CAVITE, 4TH LD | Region IV-A | Cavite 3rd DEO | Completed | ₱46.4M | 100% | High risk68 | —-0.059 |
| 16 | 17DQ0009MFO 2 - FLOOD MANAGEMENT SERVICES, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGESYSTEMS, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, STA.16+843 - STA. 17+343, WEST SIDE. BRGY. SALITRAN III,DASMARINAS, CAVITE, 4TH LD | Region IV-A | Cavite 3rd DEO | Completed | ₱46.5M | 100% | High risk68 | —-0.059 |
| 17 | 21L00072CONSTRUCTION OF CONCRETE BRIDGE - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE E), DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱136.5M | 93% | High risk68 | Flagged0.006 |
| 18 | 16HM0049CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT CANGMUNAG, SAN JUAN, SIQUIJOR LONE DISTRICT | Negros Island Region | Siquijor DEO | Completed | ₱13.9M | 100% | High risk65 | —-0.038 |
| 19 | 21L00073CONSTRUCTION OF GRAVEL ROAD - CARMEN - TAGUM CITY COASTAL ROAD (PACKAGE F), DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱130.7M | 100% | High risk63 | —-0.056 |
| 20 | 17DB0041CONST. AND MAINT. OF BRIDGES ALONG NATIONAL ROADS - WIDENING OF PERMANENT BRIDGES TO MORE THAN 2 LANES - SECONDARY, P00117145LZ, KASUYAN BR. (B00006LZ) ALONG PALICO-BALAYAN-BATANGAS RD., CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱48.1M | 100% | High risk62 | —-0.034 |
| 21 | 17CD0080REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED NATIONAL ROAD INCLUDING DRAINAGE STA. RITA - CAMIAS OLD ROAD K0075+198 - K0075+360 K0075+792 - K0075+992 | Region III | Bulacan 2nd DEO | Completed | ₱18.6M | 100% | High risk62 | —-0.041 |
| 22 | 17DF0045CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUSINFRASTRUCTURE INCLUDING LOCAL PROJECTS - ROADS AND BRIDGES, LOCALBRIDGES, CONSTRUCTION OF ALINGARO BRIDGE (PERMANENT BRIDGE), BARANGAYALINGARO, GEN. TRIAS, CAVITE 6TH LD | Region IV-A | Cavite 1st DEO | Completed | ₱47M | 100% | High risk61 | —-0.040 |
| 23 | 17DH0039CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF BRIDGES INCLUDING ROW TO MORE THAN 2 LANES, DALITIWAN BRIDGE (BO2497LZ) ALONG MAJAYJAY-LUCBAN ROAD, BRGY. BAKIA, MAJAYJAY, LAGUNA, 4TH LD | Region IV-A | Laguna 1st DEO | Completed | ₱30.6M | 100% | Medium risk58 | —-0.035 |
| 24 | 17DO0041MFO1-NATIONAL ROAD NETWORK SERVICES-CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF PERMANENT BRIDGES INCLUDING ROW-TO MORE THAN 2 LANES-TANAY BR. (B02460LZ) ALONG MANILA EAST RD. TANAY RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱41.1M | 100% | Medium risk58 | —-0.019 |
| 25 | 17DF0033MFO1 NATIONAL ROAD NETWORK SERVICES - CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD, WIDENING OF PERMANENT BRIDGES, INCLUDING ROW TO MORE THAN 2 LANES, SORIANO BRIDGE (B02891LZ) ALONG MANILA-CAVITE ROAD (PHASE II) | Region IV-A | Cavite 1st DEO | Completed | ₱36.3M | 100% | Medium risk58 | —-0.041 |