3 projects on file, including joint ventures this contractor is part of.
Total projects
3
Total budget
₱29.6M
Average progress
99.8%
Completion rate
33.3%
Below 70%
Average risk score
60.9
High risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 3 | ₱29.6M | 60.9 | 0 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 2 | ₱19.7M | 52.9 | 0 | 99.8% |
| OTHER | 1 | ₱9.9M | 77.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IE0103CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY FERDINAND E. MARCOS, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱9.9M | 100% | High risk77 | —-0.038 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24IE0103CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY FERDINAND E. MARCOS, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱9.9M | 100% | High risk77 | —-0.038 |
| 2 | 24IE0100CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SHAMROCK, BARANGAY POBLACION, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱9.9M | 100% | Medium risk53 | —-0.060 |
| 3 | 24IE0099CONSTRUCTION OF MULTI-PURPOSE BUILDING (BUILDING 2), SHAMROCK, BARANGAY POBLACION, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱9.9M | 100% | Medium risk53 | —-0.061 |