38 projects on file, including joint ventures this contractor is part of.
Total projects
38
Total budget
₱377.1M
Average progress
100.0%
Completion rate
100.0%
Average risk score
26.4
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 36 | ₱370.2M | 25.9 | 0 | 100.0% |
| Region IV-A | 2 | ₱6.9M | 36.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱115.8M | 22.8 | 0 | 100.0% |
| Roads | 16 | ₱261.3M | 31.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 19CJ0176CONSTRUCTION OF 2 STOREY 6 CLASSROOMS, LABNEY ES, SAN JOSE, TARLAC | Region III | Tarlac DEO | Completed | ₱16M | 100% | Low risk27 | —-0.046 |
| 27 | 24CJ0301CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CARDONA ELEMENTARY SCHOOL, BARANGAY CARDONA, GERONA, TARLAC | Region III | Tarlac DEO | Completed | ₱4.9M | 100% | Low risk25 | —-0.049 |
| 28 | 20CJ0169CONCRETING OF SITIO CENTRO, BRGY. SAPANG MARAGUL FMR, BRGY. SAPANG MARAGUL, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱11.6M | 100% | Low risk24 | —-0.041 |
| 29 | 24DP0071CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN MARCOS, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.104 |
| 30 | 21CJ0047LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BANABA, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱3.4M | 100% | Low risk12 | —-0.104 |
| 31 | 21CJ0010LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN CARLOS, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱3.4M | 100% | Low risk12 | —-0.104 |
| 32 | 21CJ0046LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING (2-STOREY BARANGAY HALL), BARANGAY SAN RAFAEL, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱3.4M | 100% | Low risk12 | —-0.104 |
| 33 | 24CJ0160CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY BINAUGANAN, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱3M | 100% | Low risk12 | —-0.103 |
| 34 | 23CJ0021BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL) AT BARANGAY TARIJI, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱2.9M | 100% | Low risk12 | —-0.101 |
| 35 | 21CJ0132LOCAL INFRASTRUCTURE PROGRAM REHABILITATION OF MULTI-PURPOSE BUILDING (BARANGAY COVERED COURT AND STAGE) AT BARANGAY BURGOS, SAN JOSE, TARLAC | Region III | Tarlac DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.098 |
| 36 | 21CJ0103LOCAL INFRASTRUCTURE PROGRAM REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT AND STAGE), BARANGAY DELA PAZ, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.101 |
| 37 | 21CJ0079LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY COVERED COURT AND STAGE), BARANGAY ASTURIAS, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.101 |
| 38 | 21CJ0136LOCAL INFRASTRUCTURE PROGRAM REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY SEPUNG CALZADA, TARLAC CITY, TARLAC | Region III | Tarlac DEO | Completed | ₱1.9M | 100% | Low risk10 | —-0.102 |