6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱230.3M
Average progress
98.4%
Completion rate
66.7%
Below 70%
Average risk score
44.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 3 | ₱140.5M | 62.2 | 0 | 96.8% |
| Region XII | 3 | ₱89.8M | 26.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 3 | ₱140.5M | 62.2 | 0 | 96.8% |
| Buildings and Facilities | 3 | ₱89.8M | 26.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23J00056CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 2, ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (S01185MN) SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱101.2M | 90% | High risk74 | —-0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23J00056CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAAZ RIVER, SAN RAMON BRIDGE 2, ALONG ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (S01185MN) SAN RAMON, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱101.2M | 90% | High risk74 | —-0.009 |
| 2 | 23JA0063FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MERCEDES RIVER, BARANGAY MERCEDES, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱29.4M | 100% | Medium risk57 | —-0.026 |
| 3 | 23JA0044BASIC INFRASTRUCTURE PROGRAM(BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF DRAINAGE SYSTEM, BARANGAY TETUAN, ZAMBOANGA CITY, ZAMBOANGA DEL SUR | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.9M | 100% | Medium risk56 | —-0.067 |
| 4 | 21M00130CONSTRUCTION/IMPROVEMENT OF SULTAN KUDARAT (NULING) SPORTS COMPLEX (PHASE II), BRGY. DALUMANGCOB, SULTAN KUDARAT, MAGUINDANAO | Region XII | Region XII | Completed | ₱62.1M | 100% | Medium risk34 | —-0.078 |
| 5 | 20MA0116CONSTRUCTION OF SULTAN KUDARAT (NULING) SPORTS COMPLEX, BRGY. DALUMANGCOB, SULTAN KUDARAT, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱24.7M | 100% | Low risk29 | —-0.086 |
| 6 | 20MA0070CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. META, DATU UNSAY, MAGUINDANAO | Region XII | Cotabato City DEO | Completed | ₱2.9M | 100% | Low risk17 | —-0.059 |