Contractor dossier
14 projects on file, including joint ventures this contractor is part of.
Total projects
14
Total budget
₱809.2M
Average progress
82.5%
Completion rate
57.1%
Below 70%
Average risk score
63.6
High risk on average, out of 100
Flagged as unusual
3
21.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 4 | ₱177.6M | 58.8 | 0 | 66.6% |
| Region III | 3 | ₱285.6M | 63.2 | 0 | 95.8% |
| Region II | 2 | ₱123.3M | 72.8 | 1 | 72.8% |
| Region I | 2 | ₱61.2M | 64.7 | 1 | 100.0% |
| Region XII | 1 | ₱47.5M | 88.7 | 1 | 56.0% |
| Region VII | 1 | ₱89.4M | 52.9 | 0 | 100.0% |
| National Capital Region | 1 | ₱24.5M | 49.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 6 | ₱441.3M | 64.0 | 1 | 92.3% |
| Buildings and Facilities | 2 | ₱29.3M | 62.0 | 0 | 50.0% |
| Bridges | 2 | ₱92.3M | 50.2 | 0 | 100.0% |
| Roads | 2 | ₱128.6M | 50.1 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱70.2M | 93.1 | 1 | 45.6% |
| GAA 2025 OO-2 | 1 | ₱47.5M | 88.7 | 1 | 56.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BB0111OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF WEAK BRIDGE - NADDUNGAN BR. 1 (B02132LZ) ALONG JCT. MAGAPIT CAPISSAYAN ROAD, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱70.2M | 46% | High risk93 | Flagged0.014 |
| 25MC0016CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER PACKAGE 4, BARANGAY KISANTE, MAKILALA, COTABATO (RE-PUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱47.5M | 56% | High risk89 | Flagged0.001 |
| 25DO0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TICULIO, CARDONA, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.8M | 0% | High risk75 | —-0.009 |
| 17AB0016CONSTRUCTION OF SAGPATAN FLOOD CONTROL BONGO RIVER, BRGY. SAGPATAN, DINGRAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱15M | 100% | High risk71 | —-0.042 |
| 25DO0107CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURES ALONG MANGGAHAN RIVER, MONTALBAN, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱94.4M | 66% | High risk65 | —-0.035 |
| 23CL0050CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PAMATAWAN RIVER, PHASE III, SAN MIGUEL, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 97% | High risk64 | —-0.030 |
| 23CL0034REHABILITATION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER, UPSTREAM, PHASE I, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 90% | High risk63 | —-0.026 |
| 23CL0045CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PAMATAWAN RIVER, PHASE I, SAN MIGUEL, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱94.6M | 100% | High risk63 | —-0.072 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17AB0244REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER, (BREACHED & ERODED DIKE) LEFT BANK, BRGY. ELIZABETH, MARCOS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱46.2M | 100% | Medium risk59 | Flagged0.016 |
| 25BB0111OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF WEAK BRIDGE - NADDUNGAN BR. 1 (B02132LZ) ALONG JCT. MAGAPIT CAPISSAYAN ROAD, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱70.2M | 46% | High risk93 | Flagged0.014 |
| 25MC0016CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER PACKAGE 4, BARANGAY KISANTE, MAKILALA, COTABATO (RE-PUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱47.5M | 56% | High risk89 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25BB0111OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF WEAK BRIDGE - NADDUNGAN BR. 1 (B02132LZ) ALONG JCT. MAGAPIT CAPISSAYAN ROAD, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱70.2M | 46% | High risk93 | Flagged0.014 |
| 2 | 25MC0016CONSTRUCTION OF FLOOD CONTROL DIKE ALONG BULATUKAN RIVER PACKAGE 4, BARANGAY KISANTE, MAKILALA, COTABATO (RE-PUBLISHED) | Region XII | Cotabato 2nd DEO | On-Going | ₱47.5M | 56% | High risk89 | Flagged0.001 |
| 3 | 25DO0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TICULIO, CARDONA, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱4.8M | 0% | High risk75 | —-0.009 |
| 4 | 17AB0016CONSTRUCTION OF SAGPATAN FLOOD CONTROL BONGO RIVER, BRGY. SAGPATAN, DINGRAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱15M | 100% | High risk71 | —-0.042 |
| 5 | 25DO0107CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURES ALONG MANGGAHAN RIVER, MONTALBAN, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱94.4M | 66% | High risk65 | —-0.035 |
| 6 | 23CL0050CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PAMATAWAN RIVER, PHASE III, SAN MIGUEL, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱94.6M | 97% | High risk64 | —-0.030 |
| 7 | 23CL0034REHABILITATION OF FLOOD CONTROL STRUCTURE AT BUCAO RIVER, UPSTREAM, PHASE I, BOTOLAN, ZAMBALES | Region III | Zambales 1st DEO | On-Going | ₱96.5M | 90% | High risk63 | —-0.026 |
| 8 | 23CL0045CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PAMATAWAN RIVER, PHASE I, SAN MIGUEL, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱94.6M | 100% | High risk63 | —-0.072 |
| 9 | 17AB0244REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER, (BREACHED & ERODED DIKE) LEFT BANK, BRGY. ELIZABETH, MARCOS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱46.2M | 100% | Medium risk59 | Flagged0.016 |
| 10 | 24HC0016ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING- SECONDARY ROADS -TAGBILARAN NORTH ROAD (TAGBILARAN-JETAFE SECT)- K0083+553-K0085+626, BUENAVISTA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱89.4M | 100% | Medium risk53 | —-0.081 |
| 11 | 23BB0147OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF BRIDGE -AGGUNGAN BR. (B02025LZ) ALONG DUGO-SAN VICENTE RD (DUGO-MISSION SECT.), BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱53.1M | 100% | Medium risk52 | —-0.041 |
| 12 | 22OE0108REHABILITATION OF PSG - MULTI-PURPOSE BUILDING (COAST GUARD BARRACKS), MALACAÑANG PARK, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱24.5M | 100% | Medium risk49 | —-0.090 |
| 13 | 21DO0041ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES-TANAY BR. (B0246OLZ) MANILA EAST RD | Region IV-A | Rizal 2nd DEO | Completed | ₱39.2M | 100% | Medium risk48 | —-0.055 |
| 14 | 21DO0006ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS - MARIKINA-INFANTA RD. - K0052+000 - K0054+000 TANAY, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.103 |