Contractor dossier
146 projects on file, including joint ventures this contractor is part of.
Total projects
146
Total budget
₱10.7B
Average progress
82.7%
Completion rate
61.0%
Below 70%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
13
8.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 83 | ₱3.9B | 49.4 | 4 | 88.9% |
| Region IV-A | 39 | ₱4.3B | 61.3 | 3 | 71.8% |
| Region V | 9 | ₱1.1B | 71.9 | 5 | 56.4% |
| Region III | 8 | ₱926.8M | 62.5 | 1 | 85.8% |
| Region VIII | 4 | ₱233.3M | 54.4 | 0 | 98.9% |
| Region IV-B | 3 | ₱289.5M | 52.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 74 | ₱5.5B | 53.9 | 2 | 86.6% |
| Flood Control and Drainage | 44 | ₱2.6B | 52.5 | 1 | 90.0% |
| Buildings and Facilities | 10 | ₱281.1M | 45.5 | 0 | 100.0% |
| OTHER | 7 | ₱1B | 68.8 | 4 | 46.4% |
| Bridges | 5 | ₱398.6M | 65.1 | 4 | 9.5% |
| Bridges, Roads | 4 | ₱673.4M | 66.3 | 0 | 74.4% |
| GAA 2025 OO-1 | 1 | ₱88.4M | 95.0 | 1 | 0.5% |
| GAA 2025 SSP | 1 | ₱48M | 95.0 | 1 | 37.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00239CLUSTER III - ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - III-I: MAKALUKSO BR. 1 (B02742LZ) ALONG MAHARLIKA HIGHWAY; III-II: MAKALUKSO BR. 2 (B02743LZ) ALONG MAHARLIKA HIGHWAY | Region V | Region V | On-Going | ₱88.4M | 0% | High risk95 | Flagged0.024 |
| 25DQ0083CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY LANGKAAN 2, DASMARINAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱48M | 38% | High risk95 | Flagged0.012 |
| 24CC0651CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY SAN JUAN (PUROK 1 TO PUROK 3), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 89% | High risk78 | Flagged0.025 |
| 17C00004ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARD (HDM-4 PROJECT ANALYSIS)- TERTIARY ROADS, BAGAC-MARIVELES ROAD, BATAAN 2ND LEGISLATIVE DISTRICT, PROV. OF BATAAN | Region III | Region III | Completed | ₱124.4M | 100% | High risk76 | —-0.044 |
| 25F00200ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-DAGOOK BR. 1 (B02702LZ) ALONG MAHARLIKA HIGHWAY, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱94.7M | 9% | High risk74 | Flagged0.018 |
| 17DC0021MFO-1 NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT, IMPROVEMENT/WIDENING OF NATIONAL ROADS, T | Region IV-A | Batangas 3rd DEO | Completed | ₱105M | 100% | High risk71 | —-0.030 |
| 23F00429CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-INSTALLATION OF ROAD SAFETY DEVICES ALONG ROLANDO A. ANDAYA HIGHWAY, RAGAY, CAMARINES SUR, RAGAY, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱96.6M | 93% | High risk71 | Flagged0.031 |
| 24O00093CONSTRUCTION OF LAGUNA LAKEHIGHWAY, TAGUIG CITY (PHASE6) | National Capital Region | National Capital Region | On-Going | ₱49.5M | 0% | High risk71 | Flagged0.014 |
| 25D00268CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 11% | High risk70 | Flagged0.024 |
| 24O00094CONSTRUCTION OF LAGUNA LAKE HIGHWAY, TAGUIG CITY (PHASE 7) | National Capital Region | National Capital Region | On-Going | ₱49M | 0% | High risk70 | Flagged0.016 |
| 23F00060CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LORENZO CIRCUMFERENTIAL ROAD,SAN VIC | Region V | Region V | On-Going | ₱180.7M | 96% | High risk69 | —-0.035 |
| 24F00113CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR | Region V | Region V | On-Going | ₱183.3M | 97% | High risk69 | —-0.043 |
| 25D00267CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 14% | High risk69 | Flagged0.024 |
| 24F00110CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, BASUD, | Region V | Region V | On-Going | ₱187M | 87% | High risk69 | —-0.038 |
| 25F00135CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - I-I: CALAMBUSING BR. (B02734LZ) ALONG MAHARLIKA HIGHWAY; I-II: KALAGDO BR. (B02736LZ) ALONG MAHARLIKA HIGHWAY (PHASE II), | Region V | Region V | On-Going | ₱77.9M | 13% | High risk69 | Flagged0.014 |
| 23D00073CONSTRUCTION OF DAANG HARI - MUNTINLUPA - CAVITE EXPRESSWAY BYPASS ROAD | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk68 | —-0.065 |
| 18OI0073CONSTRUCTION OF SLOPE PROTECTION INCLUDING BOX CULVERT AND REMOVAL OF INFORMAL SETTLERS ALONG LAS PI | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱120.8M | 100% | High risk67 | —-0.022 |
| 25OI0114CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱218.3M | 25% | High risk67 | —-0.006 |
| 20D00086FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM ROAD WIDENING / SECONDARY ROADS STA. ROSA - ULAT-TAGAYTAY RD. K0065+(-119)-K0065+403, K0067+578.90 - K006, CAVITE | Region IV-A | Region IV-A | Terminated | ₱45.4M | 100% | High risk66 | —-0.051 |
| 23F00059CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD,BASUD,CAMARINES NORTE | Region V | Region V | On-Going | ₱130.3M | 100% | High risk66 | —-0.045 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23F00429CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-INSTALLATION OF ROAD SAFETY DEVICES ALONG ROLANDO A. ANDAYA HIGHWAY, RAGAY, CAMARINES SUR, RAGAY, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱96.6M | 93% | High risk71 | Flagged0.031 |
| 24CC0651CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY SAN JUAN (PUROK 1 TO PUROK 3), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 89% | High risk78 | Flagged0.025 |
| 25D00267CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 14% | High risk69 | Flagged0.024 |
| 25F00239CLUSTER III - ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - III-I: MAKALUKSO BR. 1 (B02742LZ) ALONG MAHARLIKA HIGHWAY; III-II: MAKALUKSO BR. 2 (B02743LZ) ALONG MAHARLIKA HIGHWAY | Region V | Region V | On-Going | ₱88.4M | 0% | High risk95 | Flagged0.024 |
| 25D00268CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 11% | High risk70 | Flagged0.024 |
| 25F00200ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-DAGOOK BR. 1 (B02702LZ) ALONG MAHARLIKA HIGHWAY, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱94.7M | 9% | High risk74 | Flagged0.018 |
| 24O00094CONSTRUCTION OF LAGUNA LAKE HIGHWAY, TAGUIG CITY (PHASE 7) | National Capital Region | National Capital Region | On-Going | ₱49M | 0% | High risk70 | Flagged0.016 |
| 24O00093CONSTRUCTION OF LAGUNA LAKEHIGHWAY, TAGUIG CITY (PHASE6) | National Capital Region | National Capital Region | On-Going | ₱49.5M | 0% | High risk71 | Flagged0.014 |
| 25F00135CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - I-I: CALAMBUSING BR. (B02734LZ) ALONG MAHARLIKA HIGHWAY; I-II: KALAGDO BR. (B02736LZ) ALONG MAHARLIKA HIGHWAY (PHASE II), | Region V | Region V | On-Going | ₱77.9M | 13% | High risk69 | Flagged0.014 |
| 25DQ0083CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY LANGKAAN 2, DASMARINAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱48M | 38% | High risk95 | Flagged0.012 |
| 25F00240CLUSTER IV-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - IV-I: REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES-TALISAY BR. (B02723LZ) ALONG MAHARLIKA HIGHWAY; IV-II: REPLACEMENT OF PERMANENT WEAK BRIDGES-MATNO | Region V | Region V | On-Going | ₱40.9M | 11% | High risk64 | Flagged0.010 |
| 21OI0102CONSTRUCTION OF ROAD, QUIRINO TO C5 EXTENSION, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱91.7M | 0% | Medium risk57 | Flagged0.002 |
| 25OI0075CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALABANG - ZAPOTE DIVERSION ROAD (FROM ALABANG - ZAPOTE FLYOVER TO C5 BRIDGE), LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱114.9M | 1% | High risk64 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25F00239CLUSTER III - ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - III-I: MAKALUKSO BR. 1 (B02742LZ) ALONG MAHARLIKA HIGHWAY; III-II: MAKALUKSO BR. 2 (B02743LZ) ALONG MAHARLIKA HIGHWAY | Region V | Region V | On-Going | ₱88.4M | 0% | High risk95 | Flagged0.024 |
| 2 | 25DQ0083CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY LANGKAAN 2, DASMARINAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱48M | 38% | High risk95 | Flagged0.012 |
| 3 | 24CC0651CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY SAN JUAN (PUROK 1 TO PUROK 3), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 89% | High risk78 | Flagged0.025 |
| 4 | 17C00004ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARD (HDM-4 PROJECT ANALYSIS)- TERTIARY ROADS, BAGAC-MARIVELES ROAD, BATAAN 2ND LEGISLATIVE DISTRICT, PROV. OF BATAAN | Region III | Region III | Completed | ₱124.4M | 100% | High risk76 | —-0.044 |
| 5 | 25F00200ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-DAGOOK BR. 1 (B02702LZ) ALONG MAHARLIKA HIGHWAY, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱94.7M | 9% | High risk74 | Flagged0.018 |
| 6 | 17DC0021MFO-1 NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT, IMPROVEMENT/WIDENING OF NATIONAL ROADS, T | Region IV-A | Batangas 3rd DEO | Completed | ₱105M | 100% | High risk71 | —-0.030 |
| 7 | 23F00429CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-INSTALLATION OF ROAD SAFETY DEVICES ALONG ROLANDO A. ANDAYA HIGHWAY, RAGAY, CAMARINES SUR, RAGAY, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱96.6M | 93% | High risk71 | Flagged0.031 |
| 8 | 24O00093CONSTRUCTION OF LAGUNA LAKEHIGHWAY, TAGUIG CITY (PHASE6) | National Capital Region | National Capital Region | On-Going | ₱49.5M | 0% | High risk71 | Flagged0.014 |
| 9 | 25D00268CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 11% | High risk70 | Flagged0.024 |
| 10 | 24O00094CONSTRUCTION OF LAGUNA LAKE HIGHWAY, TAGUIG CITY (PHASE 7) | National Capital Region | National Capital Region | On-Going | ₱49M | 0% | High risk70 | Flagged0.016 |
| 11 | 23F00060CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LORENZO CIRCUMFERENTIAL ROAD,SAN VIC | Region V | Region V | On-Going | ₱180.7M | 96% | High risk69 | —-0.035 |
| 12 | 24F00113CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR | Region V | Region V | On-Going | ₱183.3M | 97% | High risk69 | —-0.043 |
| 13 | 25D00267CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE | Region IV-A | Region IV-A | On-Going | ₱280.7M | 14% | High risk69 | Flagged0.024 |
| 14 | 24F00110CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, BASUD, | Region V | Region V | On-Going | ₱187M | 87% | High risk69 | —-0.038 |
| 15 | 25F00135CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - I-I: CALAMBUSING BR. (B02734LZ) ALONG MAHARLIKA HIGHWAY; I-II: KALAGDO BR. (B02736LZ) ALONG MAHARLIKA HIGHWAY (PHASE II), | Region V | Region V | On-Going | ₱77.9M | 13% | High risk69 | Flagged0.014 |
| 16 | 23D00073CONSTRUCTION OF DAANG HARI - MUNTINLUPA - CAVITE EXPRESSWAY BYPASS ROAD | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk68 | —-0.065 |
| 17 | 18OI0073CONSTRUCTION OF SLOPE PROTECTION INCLUDING BOX CULVERT AND REMOVAL OF INFORMAL SETTLERS ALONG LAS PI | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱120.8M | 100% | High risk67 | —-0.022 |
| 18 | 25OI0114CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY | National Capital Region | Las Piñas-Muntinlupa DEO | On-Going | ₱218.3M | 25% | High risk67 | —-0.006 |
| 19 | 20D00086FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM ROAD WIDENING / SECONDARY ROADS STA. ROSA - ULAT-TAGAYTAY RD. K0065+(-119)-K0065+403, K0067+578.90 - K006, CAVITE | Region IV-A | Region IV-A | Terminated | ₱45.4M | 100% | High risk66 | —-0.051 |
| 20 | 23F00059CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD,BASUD,CAMARINES NORTE | Region V | Region V | On-Going | ₱130.3M | 100% | High risk66 | —-0.045 |
| 21 | 23D00074CONSTRUCTION OF MISSING LINKS/ NEW ROADSGENERAL NAKAR-DINGALAN (GEN. NAKAR SIDE), PACKAGE B, QUEZON | Region IV-A | Region IV-A | On-Going | ₱140.4M | 97% | High risk66 | —-0.022 |
| 22 | 24D00082CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALABANG - ZAPOTE DIVERSION ROAD, PACKAGE A, BACOOR SECTION, CAVITE | Region IV-A | Region IV-A | On-Going | ₱98.9M | 0% | High risk66 | —-0.015 |
| 23 | 22D00049CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL NAKAR - DINGALAN ROAD (GEN. NAKAR SIDE), PACKAGE A, QUEZON | Region IV-A | Region IV-A | Completed | ₱289.3M | 100% | High risk65 | —-0.041 |
| 24 | 21D00030FY 2021 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS BACOOR BOULEVARD TO AGUINALDO HIGHWAY (BACOOR-IMUS), CAVITE | Region IV-A | Region IV-A | Completed | ₱159.2M | 100% | High risk65 | —-0.080 |
| 25 | 25DQ0048CONSTRUCTION OF SLOPE PROTECTION ALONG JULIAN RIVER, PHASE 2, BARANGAY ZONE I, DASMARIÑAS CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱93.6M | 32% | High risk65 | —-0.026 |