203 projects on file, including joint ventures this contractor is part of.
Total projects
203
Total budget
₱5.8B
Average progress
97.4%
Completion rate
75.9%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
1
0.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 203 | ₱5.8B | 51.3 | 1 | 97.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 89 | ₱3B | 48.9 | 1 | 99.6% |
| Buildings and Facilities | 52 | ₱433.6M | 45.4 | 0 | 97.5% |
| Flood Control and Drainage | 28 | ₱1.4B | 50.6 | 0 | 99.7% |
| Water Provision and Storage | 16 | ₱160M | 47.8 | 0 | 98.8% |
| GAA 2025 OO-1 | 9 | ₱590.7M | 94.2 | 0 | 79.2% |
| GAA 2025 OO-2 | 3 | ₱170.5M | 89.7 | 0 | 54.4% |
| Bridges | 3 | ₱76.1M | 48.6 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱9.7M | 94.6 | 0 | 95.6% |
| OTHER | 1 | ₱5M | 72.4 | 0 | 87.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DM0116ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0347 + 000 - K0349 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 87% | High risk96 | —-0.003 |
| 25DM0115ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0345 + 000 - K0347 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 92% | High risk96 | —-0.004 |
| 25DM0117ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES- SN NARCISO RD - K0343 + 000 - K0345 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 92% | High risk96 | —-0.004 |
| 25DM0126ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0351 + (-700) - K0353 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 85% | High risk96 | —-0.003 |
| 25DM0125ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0349 + 000 - K0351 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 89% | High risk96 | —-0.004 |
| 25DJ0029CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY POBLACION 1, SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱4.9M | 91% | High risk95 | —-0.005 |
| 25DJ0129CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY MASIN SUR, CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱4.8M | 100% | High risk95 | —-0.009 |
| 25DJ0115OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, QUEZON-BATANGAS RD - K0101 + 725 - K0102 + 425 | Region IV-A | Quezon 2nd DEO | On-Going | ₱47.5M | 63% | High risk94 | —-0.004 |
| 25DJ0082OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF IYAM RIVER FLOOD CONTROL STRUCTURE, PACKAGE 5, LUCE | Region IV-A | Quezon 2nd DEO | On-Going | ₱137.1M | 64% | High risk93 | —-0.008 |
| 25DJ0114OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, PAGBILAO-DALAHICAN PORT RD (OLD MSR-MAYAO-TALAO-TALAO-DALAHICAN PORT) - (S06106LZ) CHAINAGE 10 - CHAINAGE 213, CHAINAGE 246 - CHAINAGE 690 | Region IV-A | Quezon 2nd DEO | On-Going | ₱47.5M | 47% | High risk93 | —-0.003 |
| 25DJ0111OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, LUCENA COTTA PORT RD - K0132 + (-030) - K0132 + 290 | Region IV-A | Quezon 2nd DEO | On-Going | ₱9.5M | 57% | High risk92 | —-0.003 |
| 25DJ0113OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, CANDELARIA BYPASS RD - K0106+935 - K0107+124.5 | Region IV-A | Quezon 2nd DEO | On-Going | ₱18.1M | 100% | High risk91 | —-0.018 |
| 25DJ0120OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SMALL RIVER IMPROVEMENT PROJECT, PILI PIP, SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱14.3M | 77% | High risk88 | —-0.029 |
| 25DJ0083OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL AND DRAINAGE STRUCTURE, BARANGAY 10, LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱19.2M | 22% | High risk88 | —-0.014 |
| 24DJ0109CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY STA. LUCIA, DOLORES, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱5M | 87% | High risk72 | —-0.007 |
| 24DJ0065CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LALIG, TIAONG, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱7.4M | 97% | High risk72 | —-0.035 |
| 22DJ0114CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS) CONSTRUCTION OF AFP RESERVE CENTERS (AFPRCENS), CAMP GUILL | Region IV-A | Quezon 2nd DEO | Completed | ₱14.7M | 100% | High risk67 | —-0.070 |
| 20DM0034ASSET PRESERVATION: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-MULANAY-SAN FRANCISCO RD-K0291+106-K029+156 | Region IV-A | Quezon 3rd DEO | Completed | ₱13.7M | 100% | High risk64 | —-0.069 |
| 23DJ0117CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL (PACKAGE 11), LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱96.5M | 90% | High risk64 | —-0.022 |
| 22DJ0131OO2: PROTECTION LIVES AND PROPERTIES AGAINST MAJOR FLOODS-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG LAGNAS RIVER (UPSTREAM-PACKAGE 5), SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.076 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DJ0190CONCRETING OF BRGY. PILI FMR, BRGY. PILI, SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱9.8M | 91% | High risk61 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 20DM0013NETWORK DEVELOPMENT: OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - GUMACA - PITOGO - MULANAY - SN NARCISO RD - K0221+328 - K0222+000, K0224+000 - K0225+000, K0226+000 - K0226+792, K0226+852 - K0230+355, MACALELON, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱93.8M | 100% | High risk61 | —-0.093 |
| 27 | 21DJ0098CONCRETING OF BRGY. SAN ANDRES FMR BRGY. SAN ANDRES, CANDELARIA, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱9.7M | 100% | High risk61 | —-0.018 |
| 28 | 24DJ0190CONCRETING OF BRGY. PILI FMR, BRGY. PILI, SARIAYA, QUEZON | Region IV-A | Quezon 2nd DEO | On-Going | ₱9.8M | 91% | High risk61 | Flagged0.013 |
| 29 | 18DM0007OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION-MSR JCT-LOPEZ-BUENAVISTA RD-K0238+ (-1055) - K0240+310, K0240+332 - K0245+530, K0245+575 - K0249+181, LOPEZ -BUENAVISTA SECTION | Region IV-A | Quezon 3rd DEO | Completed | ₱93.1M | 100% | High risk61 | —-0.095 |
| 30 | 22DJ0006CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF STA. LUCIA-BULAKIN BY-PASS R | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.089 |
| 31 | 24DJ0102OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, SARIAYA BYPASS ROAD-K0120+472 - K0121+722 | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.097 |
| 32 | 24DJ0085OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, SARIAYA BYPASS ROAD-K0121+722-K0122+052, K0122+173-K0122+655, K0123+029-K0123+467 | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.098 |
| 33 | 23DJ0003OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD (PACKAGE 11), QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.094 |
| 34 | 23DJ0111CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY ( | Region IV-A | Quezon 2nd DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.095 |
| 35 | 18DM0006OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION - GUMACA-PITOGO-MULANAY-SN NARCISO RD- K0213+000 - K0213+853, K0214+140 - K0214+235, K0215+ -514 - K0216+316, K0216+355 - K0217+014, K0217+027 - K0218+000, K0222+000 -K0224+000, K0225+000 - K0226+ | Region IV-A | Quezon 3rd DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.094 |
| 36 | 24DJ0197OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING-SECONDARY ROADS, QUEZON-BATANGAS RD-K0096+175 - K0097+620 | Region IV-A | Quezon 2nd DEO | On-Going | ₱56.7M | 98% | Medium risk54 | —-0.070 |
| 37 | 21DM0038NETWORK DEVELOPMENT: OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS -MULANAY-SN FRANCISCO RD - K0291 + 402 - K0291 + 702, K0291 + 727 - K0293 + 349,K0293 + 362 - K0293 + 793, K0302 + 769 - K0303 + 353, MULANAY, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱56.1M | 100% | Medium risk54 | —-0.100 |
| 38 | 22DM0012ASSET PRESERVATION - REHAB/ RECONS/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS- MULANAY-SN FRANCISCO RD - K0283 + 000 - K0284 + 800, K0285 + 741 - K0286 + 727, K0290 + 760 - K0291 + 000, K0294 + 000 - K0295 + 000, K0299 + 882 - K0300 + 000 | Region IV-A | Quezon 3rd DEO | Completed | ₱73.1M | 100% | Medium risk54 | —-0.095 |
| 39 | 19DM0052NETWORK DEVELOPMENT PROGRAM: OFF-CARRIAGEWAY IMPROVMENT - TERTIARY ROADS - CATANAUAN - BUENAVISTA RD - K0255+868 - K0260+696, K0260+712 - K0261+189, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱79.3M | 100% | Medium risk54 | —-0.096 |
| 40 | 20DM0028NETWORK DEVELOPMENT : OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - MSR JCT LOPEZ -CATANAUAN RD - K0252+370 - K0255+199, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱76.2M | 100% | Medium risk54 | —-0.096 |
| 41 | 19DM0088NETWORK DEVELOPMENT PROGRAM: OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS MSR JCT - LOPEZ - CATANAUAN RD K0237+(-744) - K0238+899, K0243+636 - K0243+993, CATANAUAN, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱65M | 100% | Medium risk54 | —-0.099 |
| 42 | 19DM0086ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - GUMACA - PITOGO - MULANAY - SN NARCISO ROAD, K0225+000 - K0226+000, K0233+838 - K0234+000, K0234+371 - K0235+000 & K0241+600 - K0242+300 | Region IV-A | Quezon 3rd DEO | Completed | ₱61.2M | 100% | Medium risk54 | —-0.099 |
| 43 | 19DM0089NETWORK DEVELOPMENT PROGRAM: OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - GUMACA - PITOGO - MULANAY - SAN NARCISO RD (S04256LZ) K0238+624 - K0241+454, GENERAL LUNA, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱60.2M | 100% | Medium risk54 | —-0.100 |
| 44 | 19DM0006NETWORK DEVELOPMENT PROGRAM: OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD-K0207+(-295) - K0211+000, PITOGO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱59.5M | 100% | Medium risk54 | —-0.097 |
| 45 | 20DM0036CONSTRUCTION OF FLOOD CONTROL SYSTEM SITIO TALISAY, PAGSANGAHAN, QUEZON, SAN FRANCISCO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱71.8M | 100% | Medium risk53 | —-0.077 |
| 46 | 24DJ0008OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL (PACKAGE 1), LUCENA CITY, QUEZON | Region IV-A | Quezon 2nd DEO | Completed | ₱79.1M | 100% | Medium risk53 | —-0.076 |
| 47 | 18DM0080CONSTRUCTION OF WATER SUPPLY PROJECT, SAN NARCISO, QUEZON | Region IV-A | Quezon 3rd DEO | Completed | ₱55.1M | 100% | Medium risk52 | —-0.061 |
| 48 | 18DM0002RETROFITTING/STRENGTHENING OF BRIDGES - MACALELON BR. (B02532LZ) AND CATANAUAN BR. (B02540LZ), GUMACA-PITOGO-MULANAY- SAN NARCISO RD | Region IV-A | Quezon 3rd DEO | Completed | ₱52.7M | 100% | Medium risk52 | —-0.062 |
| 49 | 22DJ0074OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT-ROAD WIDENING-TERTIARY ROADS, SN PABLO BDRY-DOLORES-PINAGDANLAYAN RD-K0099+486-K0101+288 | Region IV-A | Quezon 2nd DEO | Completed | ₱54M | 100% | Medium risk52 | —-0.105 |
| 50 | 19DM0049ASSET PRESERVATION PROGRAM: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD- K0219+700 - K0219+800, K0221+020 - K0221+060, K0221+100 - K0221+140, K0233+780 - K0233+838 | Region IV-A | Quezon 3rd DEO | Completed | ₱54M | 100% | Medium risk52 | —-0.099 |