Contractor dossier
11 projects on file, including joint ventures this contractor is part of.
Total projects
11
Total budget
₱201.8M
Average progress
77.6%
Completion rate
54.5%
Below 70%
Average risk score
51.0
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 11 | ₱201.8M | 51.0 | 0 | 77.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 11 | ₱201.8M | 51.0 | 0 | 77.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IM0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH TACLOBAN CITY DISTRICT ENGINEERING OFFICE ANNEX BUILDING, PHASE II, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱24.4M | 75% | High risk69 | —-0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25IM0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH TACLOBAN CITY DISTRICT ENGINEERING OFFICE ANNEX BUILDING, PHASE II, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱24.4M | 75% | High risk69 | —-0.027 |
| 2 | 25IM0024REHABILITATION OF MULTI-PURPOSE BUILDING, LEGISLATIVE BUILDING, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱39.4M | 0% | Medium risk57 | —-0.025 |
| 3 | 23IM0112CONSTRUCTION OF DPWH TACLOBAN CITY DISTRICT ENGINEERING OFFICE, ANNEX BUILDING, BRGY. ABUCAY, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱34.2M | 78% | Medium risk56 | —-0.038 |
| 4 | 22IM0069CONSTRUCTION OF COMELEC REGIONAL OFFICE 8 BUILDING (PHASE 4), TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱24.7M | 100% | Medium risk54 | —-0.094 |
| 5 | 24IM0107REHABILITATION OF DPWH - TACLOBAN CITY DEO BUILDING, TACLOBAN CITY | Region VIII | Tacloban City DEO | On-Going | ₱24.4M | 0% | Medium risk54 | —-0.019 |
| 6 | 19IM0064CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMELEC OFFICE) PHASE 2, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱24.1M | 100% | Medium risk54 | —-0.094 |
| 7 | 19IM0045CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMELEC OFFICE) TACLOBAN CITY, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.096 |
| 8 | 21IM0055CONSTRUCTION OF COMELEC REGIONAL OFFICE 8 BUILDING (PHASE 3), TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱9.6M | 100% | Medium risk51 | —-0.096 |
| 9 | 24IM0127INSTALLATION OF SOLAR PANELS AT DPWH-TACLOBAN CITY DEO ANNEX BUILDING PHASE 2, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.092 |
| 10 | 24ID0087CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CANCARAJA ELEMENTARY SCHOOL,BRGY. CANCARAJA,PASTRANA,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱4.9M | 100% | Medium risk47 | —-0.018 |
| 11 | 21ID0006CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING(BARANGAY HEALTH STATION),BRGY. CAPAHUAN,TABONTABON,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱1.5M | 100% | Low risk15 | —-0.094 |