Contractor dossier
55 projects on file, including joint ventures this contractor is part of.
Total projects
55
Total budget
₱1.4B
Average progress
96.4%
Completion rate
83.6%
Average risk score
46.6
Medium risk on average, out of 100
Flagged as unusual
3
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 55 | ₱1.4B | 46.6 | 3 | 96.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 32 | ₱609.6M | 48.1 | 0 | 97.6% |
| Buildings and Facilities | 11 | ₱31.7M | 23.3 | 0 | 98.4% |
| Flood Control and Drainage | 6 | ₱654.1M | 57.6 | 1 | 85.0% |
| GAA 2025 OO-1 | 2 | ₱47.1M | 93.0 | 0 | 95.8% |
| OTHER | 2 | ₱53.9M | 86.2 | 2 | 96.3% |
| Water Provision and Storage | 1 | ₱4.5M | 35.5 | 0 | 100.0% |
| Bridges | 1 | ₱974.2K | 27.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FG0027CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS ALONG TIGAON-GOA-SN JOSE-GUIJALO VIA SAN VICENTE RDK0481+775- K0481+880; K0482+010-K0482+045K0484+693- K0484+713; K0485+385-K0485+427 & K0485+693 K0485+723GOA, CAMARINES SUR | Region V | Camarines Sur 4th DEO | On-Going | ₱23.7M | 94% | High risk93 | —-0.011 |
| 25FG0022REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TIGAON-GOA-SN JOSE-LAGONOY VIA SN VICENTE RDK0546+151 - K0547+224K0547+262 - K0547+360K0549+959 - K0550+000K0550+1003 - K0551+093K0551+361 - K0551+494CARAMOAN, CAMARINES SUR | Region V | Camarines Sur 4th DEO | On-Going | ₱23.4M | 97% | High risk93 | —-0.012 |
| 24FG0113CONCRETING OF BRGY. BICALEN - BRGY. BANTUGAN FMR PHASE 1 (BANTUGAN SECTION), BRGY. BANTUGAN, PRESENTACION, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱14.5M | 100% | High risk87 | Flagged0.005 |
| 24F00441CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - LGU HOSPITALS-CAMARINES NORTE PROVINCIAL HOSPITAL, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱39.4M | 93% | High risk85 | Flagged0.038 |
| 25F00077ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TALISAY RIVER, PACKAGE 2, BARANGA | Region V | Region V | On-Going | ₱237.4M | 92% | High risk75 | Flagged0.003 |
| 24F00192ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TALISAY RIVER, BARANGAY BINA | Region V | Region V | On-Going | ₱234M | 96% | High risk71 | —-0.017 |
| 17FF0032ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG TINAMBAC-SIRUMA ROAD K0521+1002-K0521+1020, K0549+939.40-K0550+503 | Region V | Camarines Sur 4th DEO | Completed | ₱77.2M | 100% | High risk68 | —-0.059 |
| 17FF0007REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED NATIONAL ROAD INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) ALONG JCT. BALAYNAN-TABGON-PINAMIHAGAN ROAD, KO505+478 - K0505+769 | Region V | Camarines Sur 4th DEO | Completed | ₱7.9M | 100% | High risk64 | —-0.063 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24F00441CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - LGU HOSPITALS-CAMARINES NORTE PROVINCIAL HOSPITAL, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱39.4M | 93% | High risk85 | Flagged0.038 |
| 24FG0113CONCRETING OF BRGY. BICALEN - BRGY. BANTUGAN FMR PHASE 1 (BANTUGAN SECTION), BRGY. BANTUGAN, PRESENTACION, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱14.5M | 100% | High risk87 | Flagged0.005 |
| 25F00077ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TALISAY RIVER, PACKAGE 2, BARANGA | Region V | Region V | On-Going | ₱237.4M | 92% | High risk75 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21FG0074CONSTRUCTION OF MULTI-PURPOSE BUILDING,PILITAB/TABOG, CARAMOAN, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.9M | 100% | Low risk17 | —-0.096 |
| 52 | 19FF0129CY-2019 LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDINGBRGY. SAN VICENTE, SAN JOSE, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.098 |
| 53 | 19FF0128CY-2019 LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. BUYO, GOA, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.099 |
| 54 | 19FF0144CY-2019 LOCAL INFRASTRUCTURE PROGRAM - IMPROVEMENT OF BARANGAY ABO MULTI-PURPOSE AND SPORTS COMPLEXBARANGAY ABO, TIGAON, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.097 |
| 55 | 19FF0130CY-2019 LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDINGSBRGY. BAGACAY, SAN JOSE, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.4M | 100% | Low risk16 | —-0.099 |