Contractor dossier
523 projects on file, including joint ventures this contractor is part of.
Total projects
523
Total budget
₱38.5B
Average progress
89.7%
Completion rate
69.2%
Below 70%
Average risk score
57.0
Medium risk on average, out of 100
Flagged as unusual
71
13.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 407 | ₱33B | 57.9 | 58 | 88.9% |
| Negros Island Region | 114 | ₱5.3B | 54.0 | 13 | 92.5% |
| Region VII | 2 | ₱182.6M | 54.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 362 | ₱22.9B | 52.2 | 13 | 94.2% |
| Flood Control and Drainage | 74 | ₱6.4B | 58.6 | 9 | 89.7% |
| Bridges | 23 | ₱2.2B | 58.2 | 8 | 83.6% |
| OTHER | 20 | ₱2B | 75.9 | 11 | 82.3% |
| GAA 2025 OO-1 | 18 | ₱1.7B | 94.7 | 14 | 58.1% |
| GAA 2025 OO-2 | 11 | ₱1.5B | 93.8 | 10 | 37.6% |
| Bridges, Roads | 10 | ₱1.2B | 62.9 | 3 | 87.7% |
| Buildings and Facilities | 4 | ₱514.6M | 68.0 | 2 | 63.6% |
| GAA 2025 SSP | 1 | ₱128.6M | 96.0 | 1 | 3.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25G00072CONSTRUCTION OF SLOPE PROTECTION WORK ALONG DUNGON CREEK, ILOILO CITY | Region VI | Region VI | On-Going | ₱128.6M | 3% | High risk96 | Flagged0.056 |
| 25GB0067PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - K0104+000 - K0106+103, ANTIQUE | Region VI | Antique DEO | On-Going | ₱93.6M | 37% | High risk96 | Flagged0.021 |
| 25GK0132PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD - K0038 + 829 - K0038 + 909, K0039 + 596 - K0039 + 727, K0041 + 000 - K0041 + 358, K0045 + 965 - K0046 + 093, K0048 + 384 - K0049 + 366, K0060 + 670 - K0061 + 630, K0088 + 294 - K0088 + 59 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱141.6M | 81% | High risk95 | Flagged0.011 |
| 25GO0141PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY BACOLOD CIRCUMFERENTIAL RD - K0003 + (-535) - K0006 +000 | Negros Island Region | Bacolod City DEO | On-Going | ₱141.6M | 53% | High risk95 | Flagged0.018 |
| 25GB0070PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ODIONG - SIBALOM - SN REMIGIO - LEON RD - K0113+174 - K0117+000, ANTIQUE | Region VI | Antique DEO | On-Going | ₱113.8M | 10% | High risk95 | Flagged0.032 |
| 25GK0114PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - JCT NAT'L RD SAGAY-BATO-DIAN-MARCELO-BALEA JCT RD K0098 + 000 - K0099 + 194, K0099 + 639 - K0102 + 462 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱141.6M | 94% | High risk95 | Flagged0.007 |
| 25GK0124PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD (OLD ROUTE) - K0074 + 800 - K0076 + 666 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱143.5M | 9% | High risk95 | Flagged0.034 |
| 25GK0131PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - JCT NAT'L RD SAGAY-BATO-DIAN-MARCELO-BALEA JCT RD K0084 + (-966) - K0085 + 000, K0085 + 361 - K0085 + 484, K0085 + 776 - K0086 + 000, K0087 + 000 - K0087 + 360 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱143.5M | 16% | High risk95 | Flagged0.032 |
| 25GL0109PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY -VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD - K0065 + 092 - K0066 + 617 | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱97.4M | 61% | High risk95 | Flagged0.010 |
| 25HJ0146ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROAD-DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BDRY) - K0051 + (-343) - K0051 + 765, K0051 + 790 - K0052 + 650, MANJUYOD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱70.4M | 94% | High risk95 | —-0.006 |
| 25GL0106PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BINALBAGANISABELA RD - K0062 + 000 - K0063 + 250, K0065 + 435 - K0066 + 511, CHAINAGE 0 - CHAINAGE 29 | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱72M | 35% | High risk95 | Flagged0.011 |
| 25G00040KALIBO CIRCUMFERENTIAL ROAD (MAKATO- LEZO SECTION), AKLAN | Region VI | Region VI | On-Going | ₱48M | 82% | High risk95 | —-0.001 |
| 25GO0140PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY BACOLOD SOUTH RD - K0000 + 000 - K0002 +982, K0003 + 300 - K0004 + 085 | Negros Island Region | Bacolod City DEO | On-Going | ₱141.6M | 100% | High risk95 | Flagged0.005 |
| 25GL0105PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - HINIGARANISABELA RD - K0063 + 100 - K0065 + 163 | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱69.6M | 42% | High risk95 | Flagged0.008 |
| 25GL0101PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD SOUTH RD - K0064 + 538 - K0065 + 364 | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱54.2M | 52% | High risk95 | Flagged0.004 |
| 25GL0110PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD SOUTH RD - K0055 + 174 - K0056 + 000, K0056 + 570 - K0056 + 720 | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱63.8M | 68% | High risk95 | Flagged0.003 |
| 25G00033CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUAGE RIVER, SECTION 9, JANIUAY, ILOILO | Region VI | Region VI | On-Going | ₱147.4M | 1% | High risk94 | Flagged0.029 |
| 25G00038CONSTRUCTION OF FLOOD CONTROL ALONG JALAUR RIVER IN CALINOG, ILOILO (PACKAGE 6) | Region VI | Region VI | On-Going | ₱145M | 0% | High risk94 | Flagged0.027 |
| 25G00039CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ULIAN RIVER, SECTION 8, DUEÑAS, ILOILO | Region VI | Region VI | On-Going | ₱147.4M | 22% | High risk94 | Flagged0.023 |
| 25G00020CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG SUAGE RIVER IN JANIUAY, ILOILO (PACKAGE 6) | Region VI | Region VI | On-Going | ₱145M | 44% | High risk94 | Flagged0.015 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GR0003CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG JALAUR RIVER(PACKAGE 3), CALINOG, ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱140.2M | 46% | High risk83 | Flagged0.067 |
| 24GG0274CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ULIAN RIVER, LAMBUNAO, ILOILO (SECTION 2) | Region VI | Iloilo 2nd DEO | On-Going | ₱120M | 38% | High risk83 | Flagged0.065 |
| 22G00140CONSTRUCTION OF ROAD, ILOILO RIVER NORTH BANK ROAD EXTENSION, OTON, ILOILO | Region VI | Region VI | On-Going | ₱289.5M | 73% | High risk85 | Flagged0.057 |
| 25G00072CONSTRUCTION OF SLOPE PROTECTION WORK ALONG DUNGON CREEK, ILOILO CITY | Region VI | Region VI | On-Going | ₱128.6M | 3% | High risk96 | Flagged0.056 |
| 21G00007ROXAS CITY CIRCUMFERENTIAL ROAD-C1 (SECTION 1), CAPIZ | Region VI | Region VI | On-Going | ₱70.4M | 33% | High risk79 | Flagged0.051 |
| 23G00063CONSTRUCTION OF PANDAN-IBAJAY ROAD, BRGY. STA. ANA, PANDAN, ANTIQUE | Region VI | Region VI | On-Going | ₱118.8M | 15% | High risk80 | Flagged0.050 |
| 24G00071CONSTRUCTION OF MULTIPURPOSE FACILITIES, MALAY, AKLAN PACKAGE 1 | Region VI | Region VI | On-Going | ₱296.2M | 0% | High risk77 | Flagged0.044 |
| 21G00023AGANAN FLYOVER, ILOILO | Region VI | Region VI | On-Going | ₱48.3M | 0% | Medium risk50 | Flagged0.041 |
| 23G00077ILOILO RIVER NORTH BANK ROAD, ILOILO CITY | Region VI | Region VI | On-Going | ₱94.8M | 32% | High risk85 | Flagged0.039 |
| 22G00028PANAY EAST-WEST ROAD, ILOILO SECTION, ILOILO | Region VI | Region VI | On-Going | ₱147.3M | 92% | High risk85 | Flagged0.039 |
| 24GJ0070CONSTRUCTION OF DUNGON B BRIDGE, BRGY. DUNGON B, JARO, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱46.5M | 5% | Medium risk59 | Flagged0.034 |
| 25GK0124PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD (OLD ROUTE) - K0074 + 800 - K0076 + 666 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱143.5M | 9% | High risk95 | Flagged0.034 |
| 23G00021PASSI BY-PASS ROAD, ILOILO | Region VI | Region VI | On-Going | ₱84.5M | 50% | High risk82 | Flagged0.034 |
| 25GK0131PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - JCT NAT'L RD SAGAY-BATO-DIAN-MARCELO-BALEA JCT RD K0084 + (-966) - K0085 + 000, K0085 + 361 - K0085 + 484, K0085 + 776 - K0086 + 000, K0087 + 000 - K0087 + 360 | Negros Island Region | Negros Occidental 1st DEO | On-Going | ₱143.5M | 16% | High risk95 | Flagged0.032 |
| 19G00014CONSTRUCTION OF GRAVEL ROAD AND CONCRETE BRIDGE - PANAY EAST - WEST ROAD, ILOILO | Region VI | Region VI | On-Going | ₱97.5M | 3% | High risk62 | Flagged0.032 |
| 25GB0070PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ODIONG - SIBALOM - SN REMIGIO - LEON RD - K0113+174 - K0117+000, ANTIQUE | Region VI | Antique DEO | On-Going | ₱113.8M | 10% | High risk95 | Flagged0.032 |
| 21G00131AGANAN FLYOVER, ILOILO (PHASE 2) | Region VI | Region VI | On-Going | ₱69.8M | 36% | Medium risk53 | Flagged0.031 |
| 19G00106CONSTRUCTION OF UNGKA FLYOVER (PHASE 2), BRGY. UNGKA, PAVIA, ILOILO | Region VI | Region VI | Completed | ₱190.1M | 100% | High risk66 | Flagged0.031 |
| 25G00033CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUAGE RIVER, SECTION 9, JANIUAY, ILOILO | Region VI | Region VI | On-Going | ₱147.4M | 1% | High risk94 | Flagged0.029 |
| 25G00024CONSTRUCTION OF RIVER CONTROL STRUCTURE ALONG JALAUR RIVER, POTOTAN, ILOILO (PACKAGE 7) | Region VI | Region VI | On-Going | ₱145M | 6% | High risk94 | Flagged0.029 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 22GI0053PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - SEN. BENIGNO S. AQUINO, JR. AVE - (S00552PN) K0014+ (-617) - K0012 + 767 | Region VI | Iloilo 4th DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.076 |
| 227 | 23GI0081CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD, K0044 + 500 - K0044 + 545 (PHASE II) | Region VI | Iloilo 4th DEO | Completed | ₱98M | 100% | Medium risk58 | —-0.072 |
| 228 | 23GI0065CONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, ACCESS ROAD LEADING TO AGRI-TOURISM SITE, BRGY. MANASA ROAD SECTION, ALIMODIAN, ILOILO (SITE 2) | Region VI | Iloilo 4th DEO | Completed | ₱99M | 100% | Medium risk58 | —-0.073 |
| 229 | 20G00009CONSTRUCTION OF CONCRETE ROAD-ILOILO R-1 BYPASS ROAD, ILOILO | Region VI | Region VI | Completed | ₱97.5M | 100% | Medium risk58 | —-0.073 |
| 230 | 23GI0064CONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, ACCESS ROAD LEADING TO AGRI-TOURISM SITE, BRGY. MANASA ROAD SECTION, ALIMODIAN, ILOILO (SITE 1) | Region VI | Iloilo 4th DEO | Completed | ₱99M | 100% | Medium risk58 | —-0.074 |
| 231 | 24GI0078PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO CITY - LEGANES - DUMANGAS COASTAL RD., K0010 + 710 - K0013 + 530, K0013 + 644 - K0014 + 121 | Region VI | Iloilo 4th DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.075 |
| 232 | 23GI0054CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD- K0045 + 830 - K0045 + 930 | Region VI | Iloilo 4th DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.075 |
| 233 | 23GI0073CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD, K0043 + 250 - K0043 + 330, K0042 + 1015 - K0043 + 020 | Region VI | Iloilo 4th DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.076 |
| 234 | 25GG0196PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - POTOTAN - TABUGON RD - K0031 + 799 - K0035 + 000, K0035 + 391 - K0036 + 687, K0036 + 697 - K0037 + 382 (WITH EXCEPTION) | Region VI | Iloilo 2nd DEO | On-Going | ₱100.8M | 85% | Medium risk58 | —-0.042 |
| 235 | 18G00001CONSTRUCTION OF ROAD - PASSI BYPASS ROAD INCL. ROW | Region VI | Region VI | Completed | ₱103.5M | 100% | Medium risk58 | —-0.065 |
| 236 | 24GG0122PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - LAMBUNAO - INCA RD - K0048 + (-278) - K0055 + 000 | Region VI | Iloilo 2nd DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.077 |
| 237 | 17GJ0023RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, ILOILO BRIDGE (B00501PN) ALONG SEN. BENIGNO S. AQUINO, JR. AVE | Region VI | Iloilo City DEO | Completed | ₱39.2M | 100% | Medium risk58 | —-0.029 |
| 238 | 20G00069ROXAS CITY CIRCUMFERENTIAL ROAD, CAPIZ | Region VI | Region VI | Completed | ₱87.5M | 100% | Medium risk55 | —-0.042 |
| 239 | 23GB0025CONSTRUCTION OF ANTIQUE BREAKWATER STRUCTURE ALONG BARANGAY MAYBATO SOUTH TO BARANGAY MAYBATO NORTH | Region VI | Antique DEO | On-Going | ₱90.8M | 91% | Medium risk55 | —-0.008 |
| 240 | 23GB0020CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG CANGARANAN RIVER AT VALDERRAMA BRIDGE, ABUTMENT B, UP | Region VI | Antique DEO | On-Going | ₱90M | 88% | Medium risk55 | —-0.010 |
| 241 | 20G00011CONSTRUCTION OF PARALLEL BRIDGE - JALAUR BR. (B00194PN) ALONG ILOILO-CAPIZ RD (NEW ROUTE) | Region VI | Region VI | Completed | ₱91.2M | 100% | Medium risk55 | —-0.017 |
| 242 | 21GG0088WIDENING OF BRIDGE, ULIAN BRIDGE (B00193PN) ALONG ILOILO - CAPIZ (NEW ROUTE) | Region VI | Iloilo 2nd DEO | Completed | ₱91.2M | 100% | Medium risk55 | —-0.027 |
| 243 | 23GB0026CONSTRUCTION OF ANTIQUE BREAKWATER STRUCTURE ALONG BARANGAY SAN ANGEL TO BARANGAY MALAIBA SAN JOSE, | Region VI | Antique DEO | On-Going | ₱90M | 91% | Medium risk55 | —-0.008 |
| 244 | 19GH0061CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION/REHAB. OF BAROTAC VIEJO FLOOD CONTROL ALONG ILOILO EAST COAST CAPIZ ROAD, BRGY. ILAWOD, BAROTAC VIEJO, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱91.6M | 100% | Medium risk55 | —-0.060 |
| 245 | 22GI0075CONSTRUCTION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, ACCESS ROAD FROM JUNCTION NATIONAL ROAD TO BRGY. BOBON ROAD SECTION, LEON, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱91.6M | 100% | Medium risk55 | —-0.074 |
| 246 | 22GI0065CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD - K0044 + 600 - K0044 + 700 | Region VI | Iloilo 4th DEO | Completed | ₱91.7M | 100% | Medium risk55 | —-0.077 |
| 247 | 20GI0072REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - K0045+777 - K0045+877, JUNCTION BANCAL - LEON - ANTIQUE NATIONAL ROAD, LEON, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱90.1M | 100% | Medium risk54 | —-0.075 |
| 248 | 19GJ0222CONSTRUCTION OF CONCRETE ROAD, METRO ILOILO RADIAL ROAD (R-4 BY PASS ROAD), ILOILO CITY | Region VI | Iloilo City DEO | Completed | ₱91M | 100% | Medium risk54 | —-0.076 |
| 249 | 24GI0071PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - CABATUAN - NEW LUCENA - BANGA BANTE RD, K0041+(-677) - K0042+309, K0042+326-K0045+620 | Region VI | Iloilo 4th DEO | Completed | ₱90.6M | 100% | Medium risk54 | —-0.076 |
| 250 | 24GI0077PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MANDURRIAO-SN MIGUEL-ALIMODIAN-MAASIN-CABATUAN RD - K0017 + 650 - K0018 + 400, K0021 + 054 - K0021 + 460, K0024 + 166 - K0024 + 305, K0025 + 988 - K0028 + 250 | Region VI | Iloilo 4th DEO | Completed | ₱90.6M | 100% | Medium risk54 | —-0.077 |