20 projects on file, including joint ventures this contractor is part of.
Total projects
20
Total budget
₱127.5M
Average progress
100.0%
Completion rate
100.0%
Average risk score
11.4
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 20 | ₱127.5M | 11.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱74.1M | 8.4 | 0 | 100.0% |
| Roads | 4 | ₱50.4M | 22.0 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱2.9M | 13.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 20MF0022CONSTRUCTION OF CONCRETE ROAD-CALEAN-KALANDAGAN ROAD IN SUPPORT TO PALM OIL AND MANGO INDUSTRIES, STA.0+435-STA.0+993-STA.1+305, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.6M | 100% | Low risk27 | —-0.089 |
| 2 | 21MF0008MARBEL - ALLAH VALLEY - COTABATO ROAD - K1763 + 850 - K1764 + 646, ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱16.3M | 100% | Low risk27 | —-0.088 |
| 3 | 18MH0123CONSTRUCTION OF TWO (2) STOREY - TWO (2) LABORATORY (ICT LAB) AT KEYTODAC NATIONAL HIGH SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱10.3M | 100% | Low risk24 | —-0.041 |
| 4 | 21MF0070CONCRETING OF SITIO KALUMPANG TO SITIO KAMANGA, BRGY. LAGUILAYAN FMR, BRGY. LAGUILAYAN, ISULAN, SULTAN KUDARAT, STA. 0+000 - STA. 0+625 | Region XII | Sultan Kudarat 1st DEO | Completed | ₱11.6M | 100% | Low risk20 | —-0.034 |
| 5 | 18MH0108CONSTRUCTION OF TWO (2) STOREY-TWO (2) LABORATORY (ICT LAB) AT MASIAG NATIONAL HIGH SCHOOL - BAGUMBAYAN ANNEX BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱10.3M | 100% | Low risk20 | —-0.042 |
| 6 | 16MF0065CONSTRUCTION OF 1 UNIT 3 STOREY 12 CLASSROOM SB @ ISULAN NHS ISULAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱19.6M | 100% | Low risk19 | —-0.008 |
| 7 | 17MH0280CONSTRUCTION OF TWO (2) UNITS UNIQUE WORKSHOP (7X22.5) BUILDING AT SEN. NINOY AQUINO NATIONAL HIGH SCHOOL SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱6.7M | 100% | Low risk17 | —-0.018 |
| 8 | 17MH0245CONSTRUCTION OF ONE (1) STOREY - FOUR (4) CLASSROOMS SCHOOL BUILDING AT NEW PANAY NATIONAL HIGH SCHOOL ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱5.1M | 100% | Low risk16 | —-0.018 |
| 9 | 21MF0053CONCRETING OF ROAD FROM BRGY. UPPER LOMOYON PROPER TO SITIO BIALONG, BRGY. ELBEBE, COLUMBIO, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱3M | 100% | Low risk14 | —-0.085 |
| 10 | 20MF0067CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF FLOOD CONTROL AT BARAS BIRD SANCTUARY IN BARANGAY BARAS, TACURONG CITY, SULTAN KUDARAT | Region XII | Sultan Kudarat 1st DEO | Completed | ₱2.9M | 100% | Low risk13 | —-0.071 |
| 11 | 19MH0024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. NUMO, ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱920K | 100% | Low risk5 | —-0.085 |
| 12 | 19MG0063CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYM), LAMIAN NATIONAL HIGH SCHOOL, BRGY. LAMIAN, SURALLAH, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱990K | 100% | Low risk3 | —-0.085 |
| 13 | 18MG0231COMPLETION OF BO.10 BHS, BO.10, STO. NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱990K | 100% | Low risk3 | —-0.040 |
| 14 | 18MG0230COMPLETION OF TERESITA BHS, BRGY. TERESITA, STO. NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱999K | 100% | Low risk3 | —-0.042 |
| 15 | 18MG0045CONSTRUCTION (COMPLETION) OF BARANGAY GYM/DRAINAGE, BRGY. MAMBUCAL, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱999K | 100% | Low risk3 | —-0.086 |
| 16 | 17MH0184CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT ESPERANZA NATIONAL HIGH SCHOOL - (A) ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.1M | 100% | Low risk3 | —-0.018 |
| 17 | 17MH0250CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT SALABACA NATIONAL HIGH SCHOOL ESPERANZA, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.8M | 100% | Low risk3 | —-0.019 |
| 18 | 17MH0279CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING AT SEN. NINOY AQUINO NATIONAL HIGH SCHOOL SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱4.1M | 100% | Low risk3 | —-0.019 |
| 19 | 17MH0256CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING WITH TOILET AT BIWANG NHS - BAGUMBAYAN ANNEX BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱4.1M | 100% | Low risk3 | —-0.018 |
| 20 | 17MH0270CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT KALAMANSIG NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.2M | 100% | Low risk2 | —-0.020 |